This is a Standard Specifications document for Temporary Facilities and Controls (Section 01500) issued by the Washington Suburban Sanitary Commission (WSSC Water) for use in water and wastewater construction projects in Prince George's and Montgomery Counties, Maryland. The specifications establish general requirements for temporary construction facilities, controls, and environmental protection measures required during project execution. Key facility requirements include temporary barricades, fences (minimum 6 feet high), pedestrian bridges, guards, temporary utilities (water, electricity, toilets, and heating), haul roads, and traffic control measures. The contractor is responsible for obtaining Engineer approval before locating temporary facilities, maintaining site safety to prevent unauthorized access, and conducting operations to minimize inconvenience to the public. Specific signage requirements are detailed for different project types: no-parking signs (11" x 17" weather-resistant board posted 48 hours prior to work), water and sewer main project signs (24" x 36" metal signs with WSSC water drop symbol and QR code), and portable sandwich board signs for sewer rehabilitation and MDE-funded projects.

The contractor bears all costs associated with temporary facilities and utilities except for water service, which WSSC Water furnishes at no cost. The contractor must arrange for electricity service and pay all associated costs, including permanent power authorized by the Engineer and used through substantial completion. Traffic control plans must follow Maryland Department of Transportation requirements, the Manual on Uniform Traffic Control Devices (MUTCD), and applicable jurisdictional permits, with flaggers required to be certified in the State of Maryland and equipped with proper identification and STOP/SLOW paddles with reflective sheeting. Environmental protection requirements include dust control measures, prevention of water contamination in adjacent watercourses, compliance with federal Clean Water Act and Resource Conservation and Recovery Act provisions, adherence to Maryland Department of the Environment air quality and noise pollution regulations, and compliance with county-specific ordinances in Montgomery and Prince George's Counties. All costs for providing and complying with these temporary facility and control requirements are considered incidental to the contract and will not be separately measured for payment.

View the file

Other files

File Type Posted
Urgent_Repairs,_Rehabilitation,_and_or_Replacement_of_Water_and_Wastewater_Assets_(Addendum_#7_Revision).pdf PDF
Prince_George's_County_Wage_Determinatio.pdf PDF
Montgomery_County_Wage_Determination_8.25.26.pdf PDF
Exhibit_A_-_Company_Experience_Statement.pdf PDF
Section_VI_-_Corrosion_Details.pdf PDF
Section_VIII_-_Sediment_Control_Details.pdf PDF
WSSC_Construction_IDIQ_Terms_and_Conditions.pdf PDF
OSHA_Recordkeeping_Forms_(PDF_Fillable).pdf PDF
Section_IV_-_Water_Details.pdf PDF
Section_III_-_Sewer_Details.pdf PDF
Section_II_-_Miscellaneous_Details.pdf PDF
SCENARIO_2_Watermain_Replacement_Pkg_R.pdf PDF
SCENARIO_1_Valve_Replacement_Pkg_R.pdf PDF
SCENARIO_3_Sewer_Replacement_and_SHC_Pkg_R.pdf PDF
Section_I_-_General_Notes_0.pdf PDF
03300_Cast-in-Place_Concrete_2026.pdf PDF
02958_Pipe_Bursting_2026.pdf PDF
13110_Cathodic_Protection_2026.pdf PDF
04200_Masonry_2026.pdf PDF
02510_Water_Distribution_System_2026.pdf PDF
05500_Metal_Fabrications_2026.pdf PDF
Section_VII_-_Pressure_Sewer.pdf PDF
03400_Precast_Concrete_Underground_Structures_2026.pdf PDF
Section_IX_-_Procurment_and_Manufacturing_Details_(1).pdf PDF
02315_Earthwork_for_Pipeline_Construction_2026.pdf PDF
02955_Sewer_Mains_Lateral_Rehabilitation_by_Lining_2026.pdf PDF
13112_Impressed_Current_Cathodic_Protection_for_Water_Sewer_Pipelines_2026.pdf PDF
02957_Sewer_Manhole_Rehabilitation_2026.pdf PDF
02530_Sanitary_Sewage_System_2026.pdf PDF
02960_Temporary_Bypass_Pumping_System_2026.pdf PDF
02920_Lawns-Grasses_2026.pdf PDF
02370_Slope-Watercourse_Protection_2026.pdf PDF
02441_Microtunneling_2026.pdf PDF
Sol_Urgent_Repairs_Exmaple_Invoice.xlsx XLSX spreadsheet
01330_Submittal_Procedures_2026.pdf PDF
02820_Fences-Gates_2026.pdf PDF
02930_Exterior_Plants_2026.pdf PDF
02950_Paving_Requirements_2026.pdf PDF
02533_Pressure_Sewer_System_2026.pdf PDF
02956_CCTV_Inspection_of_Sewer_Mains,_Manholes_and_Laterals_2026.pdf PDF
02959_Sewer_Main_and_Lateral_Connection_Sealing_2026.pdf PDF
02230_Site_Clearing_2026.pdf PDF
02512_Cleaning-Lining_Water_Mains_2026.pdf PDF
ESC_Minor_Utility_Permit,_Health_and_Safety_Qualification_Questionaire,_and_Example_Health_and_Safety_Plan_outline.pdf PDF
02510_Water_Distribution_System_Contractor_Furnishes_All_Materials_2026.pdf PDF
02511_Chlorination_and_Dechlorination_2026.pdf PDF
02446_Horiz_Directional_Drilling_2026.pdf PDF
02445_Boring-Jacking_2026.pdf PDF
01110_Summary_of_Work_2026.pdf PDF
00600_TOC_Specs_2026.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01500-1 2026

STANDARD SPECIFICATIONS

SECTION 01500

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 DESCRIPTION

A. Section includes general requirements relating to responsibilities for temporary construction facilities, controls, and environmental protection, except temporary erosion and sediment control included in Section 01570.

1.2 CONSTRUCTION FACILITIES

A. General: Temporary facilities and protective devices include, but are not limited to, temporary barricades, fences, bridges, guards, temporary utilities, steel plates over trenches, maintenance of traffic, project identification signs, and construction of haul roads.

1. Use materials of size, shape, and strength suitable for intended use, in construction of the above.

2. Conduct construction operations to cause least inconvenience possible to general public, the Commission, and its employees.

3. Where required, erect and maintain signs, fences, barricades, pedestrian bridges, supply guards and flagmen for protection of public.

4. Take positive measures to prevent entry of children, animals, and unauthorized adults to work site and storage areas at all times.

5. Obtain Engineer's approval before transporting or locating temporary facilities within construction site.

B. Furnish and construct temporary fencing required to fence off excavation, storage, and operating areas.

1. Erect suitably constructed temporary fences, neat in appearance, and meeting

Engineer’s approval.

2. Unless otherwise indicated, erect fences 6 feet high.

C. Barricade or close all openings in roadways, floors, walls, or other parts of structures or walkways while openings are not in regular use.

1. Use barricades substantial in character, neat in appearance, and of size and arrangement with Engineer’s approval.

01500-2 2026

D. In areas where removal of existing sidewalk is necessary, construct pedestrian bridges of suitable materials, with handrails or sides tightly boarded, following local or State requirements.

1. Construct bridges with minimum width of 6 feet, or greater width to accommodate normal traffic flow at the particular location.

1.3 TEMPORARY UTILITIES

A. Water.

1. Unless otherwise specified, the Commission will furnish water required during construction period at no cost to Contractor.

2. Make arrangements for, piping, backflow devices, appurtenances, and hookup required.

3. Assure availability of drinking water for work force.

4. Install temporary pumps, tanks, and compressors to produce required pressures.

B. Electricity.

1. Make necessary arrangements and pay for all temporary electric service and lighting required during construction period.

2. Pay costs for permanent power authorized by Engineer and used during construction period through date of Contract substantial completion

3. Ensure electric service of sufficient capacity and characteristics to supply proper current for various types of construction tools, motors, welding machines, light, heating plant, pumps, testing, and other work required.

4. Install necessary temporary wiring, panelboards, outlets, switches, lamps, fuses, controls and accessories.

C. Toilets.

1. Locate toilets where directed.

2. Maintain adequate number of temporary prefabricated chemical type toilets, unless otherwise indicated, with proper enclosures for use of workers during construction.

3. Keep clean and comply with local and State health requirements and sanitary regulations.

4. Keep locked during non-working hours.

D. Temporary Heating.

1. Provide temporary heating, including costs of equipment and installation, fuel and attendance, whenever and for such periods as heating may be required.

a. General weather conditions to prevent freezing.

b. Maintain suitable working conditions.

c. Ensure progress of operation within established scheduled time.

d. Curing of concrete.

01500-3 2026

1.4 PROJECT SIGNS

A. No Parking Signs.

1. Provide when work will require a street clear of vehicles.

2. Post signs 48-hours prior to performing work.

3. Weather-resistant poster board sign 11-inches x 17-inches, 6 ply, poly-coated (2 sides)

a. Image file for sign will be provided by Engineer.

4. Attach signs to wooden stakes, and/or traffic barrels/cones in public rights-of-way.

a. Do not attach signs to telephone poles, roadside trees, light poles, or mailbox posts.

5. Place signs along work area at 25-to-50-foot intervals to have at least one sign in front of each property to ensure residents will observe signage.

01500-4 2026

B. Water Main Replacements, Relocations, and Cleaning and Lining Contracts.

1. Provide metal signs.

a. Size: Approximately 24-inch by 36-inch.

b. Place 4-inch WSSC Water drop symbol top left corner approximately 3” from the left side and 1 ¾” from the top.

c. Place QR code at upper right corner of sign approximately 2” from the right side and 1 ¾” from the top.

d. White background with blue lettering centered on the 36-inch width of sign.

e. All titles/static text (“Project Number, Improvements by, Contract Manager and Contact Number” titles) is 115-point text, Helvetica Neue REGULAR centered on the 36-inch width.

f. 1st line of title/static text (“Project Number” title) is 8” from the top centered.

g. All text specific to the job is 160-point text, Helvetica Neue MEDIUM centered on the 36-inch width of sign.

h. 2 ¼” of space from bottom of job specific information to the title of the next line.

i. Center a 10-point blue rule between bottom of job specific information and the title.

j. BY PERMISSION GRANTED TO WSSC WATER THROUGH LOCAL

GOVERNMENT text is 42-point text, Helvetica Neue medium centered vertically between text above and box below and horizontally on the 36inch width.

k. 5” high box with a flat side on the left edge and an angle on right side of box in PMS 299, .5” from left edge and ¼” from the bottom.

l. 5” high box with a flat side on the right edge and an angle on left side of box in PMS 534, .5” from right edge and ¼” from the bottom.

m. 24-hour emergency number is reversed and centered in PMS 534 (darker blue) box.

See next page for Water Main Project Sign template

01500-5 2026

2. Install sign as directed by Contract Manager

a. 4-inch by 4-inch by 8-foot post set approximately 3 feet in ground with ¾- inch exterior plywood of same size as metal sign, firmly attached to top of post.

b. Approximately 12 stainless steel wood screws, minimum #10 - 5/8-inch long with washers, to attach sign and name plates to plywood.

3. Install signs within 7 days of start of construction in grass areas within road right of way.

4. Provide water resistant white brochure box labeled with "WSSC PROJECT INFO" in 3-inch blue lettering that holds at least 150 sheets of 8 ½-inch by 11- inch flyers attached to the bottom of the sign.

5. Provide at:

a. Add project specific locations here b.

c.

01500-6 2026

C. Sewer Main Rehabilitation Contracts. Repeat design of water main sign.

1. Provide portable “sandwich board” signs at each work site.

a. Locate the portable signs at each end of every work site for every crew used in the execution of the work.

b. Set signs in grass areas within road rights-of-way each day before beginning of work.

c. 24-inch x 36-inch white plastic A-frame, double-sided sign.

d. Use Water Main Replacements, Relocations, and Cleaning and Lining

Contracts specs above for this “sandwich board” sign.

D. MDE-Funded Sewer Projects (S3) signs

1. Provide portable “sandwich board” signs at each work site.

a. Locate the portable signs at each end of every work site for every crew used in the execution of the work.

01500-7 2026

b. Set signs in grass areas within road rights-of-way each day before beginning of work.

c. 24-inch x 36-inch white plastic A-frame, double-sided sign.

d. Use Water Main Replacements, Relocations, and Cleaning and Lining

Contracts specs above for this “sandwich board” sign.

e. See example on next page.

f. When posting S3 signage per Maryland Department of the Environment

(MDE) and the Environmental Protection Agency (EPA) it must be accompanied by their signage.

01500-8 2026

1.5 TRAFFIC CONTROL PLAN

A. If not included in Contract Documents, submit traffic control plan following 01330 to the Engineer for review and approval.

1. Maintain normal thru traffic flow following jurisdictional requirements, Manual on

Uniform Traffic Control Devices, and specific permit requirements.

2. Take safety measures following Maryland Department of Transportation, State

Highway Administration General Provisions GP-7.05 and GP-7.06 and applicable jurisdictional requirements.

B. Follow Appropriate Jurisdictional Permits; Absent Jurisdictional Requirements, Roads:

Considered secondary unless otherwise indicated on Drawings, and following criteria shall govern.

1. General: Assign flaggers certified in the State of Maryland whose only duty is to direct traffic when roadway lanes are blocked by construction equipment or operations.

a. Flaggers:

1) Dressed in attire following current MUTCD (Manual on Uniform Traffic Control Devices-OSHA).

2) Required to have photo I.D. and Flagger certification card on them at all times. Provide to Engineer upon request.

b. Equipment.

1) STOP/SLOW paddle.

(a) 24” x 24”, with minimum 8” high letters.

(b) Reflective sheeting following Maryland SHA’s Specification

950.03.

(c) Non-reflective paddles are not allowed.

2) Two-way radios or pilot vehicles: Used when flaggers are not within sight distance of each other, or when directed by Engineer.

2. Primary Roads where Shown on Drawings.

a. Do not store excavated material and other materials on roadways.

b. Close excavations at end of each workday by backfilling or by means of steel plates marked in advance with warning signs, or other accepted materials.

c. Leave work area clean and without obstacles during off-work hours.

3. Secondary Roads.

a. Maintain two-way traffic during working hours.

b. Clean up area of work site at end of each workday to allow maximum use of roadway during off-work hours.

C. Temporary Facilities: Required for pedestrian and vehicular access to properties adjacent to or contiguous with Project.

1. If necessary to temporarily interrupt access, after securing Engineer's approval, notify all affected parties of time, extent, and duration of interruption.

01500-9 2026

1.6 ENVIRONMENTAL PROTECTION

A. Furnish necessary items for fulfilling work described herein for environmental protection that results directly or indirectly from Work. For erosion and sediment control see Section 01570.

1. Take precautions in conduct of operations necessary to avoid contaminating water in adjacent watercourses or water storage areas, including wells, whether natural or man-made.

2. Conduct earthwork, moving of equipment, water control of excavations, and other operations likely to create silting to eliminate pollution of watercourses or water storage areas.

a. Dispose of water contaminated with oil, bitumen, harmful or objectionable chemicals, sewage, or other pollutants offsite: Federal Clean Water Act and Resource Conservation and Recovery Act.

b. Discharge of pollutants into any watercourse or water storage area prohibited:

State of Maryland National Pollutant Discharge Elimination System.

c. When water from adjacent natural sources is needed, use intake methods, which avoid contaminating source of supply or becoming source of erosion or sedimentation.

3. Noise and Air Pollution Control: As to not violate following applicable ordinances, regulations, rules and laws pertaining to noise and air pollution in effect. Conduct operations following provisions in effect and as set forth in:

a. Rules and Regulations Governing the Control of Air Quality in the State of

Maryland, COMAR 26.11., Maryland Department of the Environment.

b. Chapter 3, Montgomery County Code, 1972, Bill No. 42-73, Air Quality

Control.

c. Subtitle 19, Prince George's County Code, 1999 Edition, Pollution.

d. Rules and Regulations Governing the Control of Noise Pollution in the State of Maryland COMAR 26.02.03, Maryland Department of the Environment.

e. Chapter 31B, Montgomery County Code, 1972, Bill No. 64-73, Noise Control.

4. Plant Pest Control: By soil moving or handling equipment that has operated in or will operate in regulated areas following plant quarantine regulations.

a. In general, these regulations require thorough cleaning of soil from equipment before it is moved from regulated areas to uninfested areas.

b. Obtain complete information from regional office of Plant Pest Control

Division of United States Department of Agriculture.

5. Preservation of Natural Resources: In construction operations for Work, clean-up, and condition of adjacent terrain upon completion of Work, fully comply with all applicable regulations and laws concerning preservation of natural resources.

6. Dust Control: Throughout construction period, maintain dust control using water sprinklers or chemical dust control binder with Engineer’s approval.

01500-10 2026

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

PART 4 MEASUREMENT AND PAYMENT

4.1 Providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.

**WSSC**

STANDARD SPECIFICATIONS
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
1.1 DESCRIPTION
1.2 CONSTRUCTION FACILITIES
1.3 TEMPORARY UTILITIES
1.4 PROJECT SIGNS
1.5 TRAFFIC CONTROL PLAN
1.6 ENVIRONMENTAL PROTECTION
4.1 Providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.