02960_Temporary_Bypass_Pumping_System_2026.pdf

PDF 103 KB Posted

Attached to
Urgent Repairs, Rehabilitation, and/or Replacement of Water and Wastewater Assets
Solicitation number
115581
Issued by
Prince George's County, Maryland

About this file

This is a Standard Specifications document for Temporary Bypass Pumping Systems issued by the Washington Suburban Sanitary Commission (WSSC Water) in Maryland, applicable to urgent repairs and rehabilitation of water and wastewater assets throughout Prince George's and Montgomery Counties. The specifications establish comprehensive requirements for implementing temporary sewage diversion systems around work areas during sewer main repairs, rehabilitation, or replacement projects. Contractors must submit detailed plans describing proposed pumping system configurations, including suction and discharge piping specifications, pump sizes and capacities, site access points, and expected flow rates. The bypass pumping systems must be capable of handling peak flows of 15 million gallons per day (mgd) or greater as approved by the Engineer, operate continuously for 24 hours per day, and include backup pumps and emergency response procedures. All temporary piping installations must utilize high-density polyethylene (HDPE) pipes joined through butt-fusion methods performed by certified technicians, with flexible hoses and associated equipment rated for anticipated external and internal loads.

The specifications require contractors to maintain spare parts on site, perform leakage and pressure tests before operation, and conduct bi-hourly inspections with an on-site responsible operator present during all pumping operations. All costs associated with providing and maintaining the temporary bypass pumping system, including pipe installation, removal, property restoration, and utility relocation, are considered incidental to the contract and will not be separately measured for payment. Contractors bear full responsibility for preventing sewage overflows, releases, or spills and must develop comprehensive emergency plans detailing procedures for pump failures and service backup incidents. Installation locations must minimize disturbance to existing utilities and require Engineer approval prior to construction. Upon project completion and written Engineer approval, contractors must remove all temporary piping and restore properties to pre-construction conditions.

View the file

Other files

File Type Posted
Urgent_Repairs,_Rehabilitation,_and_or_Replacement_of_Water_and_Wastewater_Assets_(Addendum_#7_Revision).pdf PDF
Prince_George's_County_Wage_Determinatio.pdf PDF
Montgomery_County_Wage_Determination_8.25.26.pdf PDF
Exhibit_A_-_Company_Experience_Statement.pdf PDF
Section_VI_-_Corrosion_Details.pdf PDF
Section_VIII_-_Sediment_Control_Details.pdf PDF
WSSC_Construction_IDIQ_Terms_and_Conditions.pdf PDF
OSHA_Recordkeeping_Forms_(PDF_Fillable).pdf PDF
Section_IV_-_Water_Details.pdf PDF
Section_III_-_Sewer_Details.pdf PDF
Section_II_-_Miscellaneous_Details.pdf PDF
SCENARIO_2_Watermain_Replacement_Pkg_R.pdf PDF
SCENARIO_1_Valve_Replacement_Pkg_R.pdf PDF
SCENARIO_3_Sewer_Replacement_and_SHC_Pkg_R.pdf PDF
Section_I_-_General_Notes_0.pdf PDF
03300_Cast-in-Place_Concrete_2026.pdf PDF
02958_Pipe_Bursting_2026.pdf PDF
13110_Cathodic_Protection_2026.pdf PDF
04200_Masonry_2026.pdf PDF
02510_Water_Distribution_System_2026.pdf PDF
05500_Metal_Fabrications_2026.pdf PDF
Section_VII_-_Pressure_Sewer.pdf PDF
03400_Precast_Concrete_Underground_Structures_2026.pdf PDF
Section_IX_-_Procurment_and_Manufacturing_Details_(1).pdf PDF
02315_Earthwork_for_Pipeline_Construction_2026.pdf PDF
02955_Sewer_Mains_Lateral_Rehabilitation_by_Lining_2026.pdf PDF
13112_Impressed_Current_Cathodic_Protection_for_Water_Sewer_Pipelines_2026.pdf PDF
02957_Sewer_Manhole_Rehabilitation_2026.pdf PDF
02530_Sanitary_Sewage_System_2026.pdf PDF
02920_Lawns-Grasses_2026.pdf PDF
02370_Slope-Watercourse_Protection_2026.pdf PDF
02441_Microtunneling_2026.pdf PDF
Sol_Urgent_Repairs_Exmaple_Invoice.xlsx XLSX spreadsheet
01330_Submittal_Procedures_2026.pdf PDF
02820_Fences-Gates_2026.pdf PDF
02930_Exterior_Plants_2026.pdf PDF
02950_Paving_Requirements_2026.pdf PDF
02533_Pressure_Sewer_System_2026.pdf PDF
02956_CCTV_Inspection_of_Sewer_Mains,_Manholes_and_Laterals_2026.pdf PDF
02959_Sewer_Main_and_Lateral_Connection_Sealing_2026.pdf PDF
02230_Site_Clearing_2026.pdf PDF
02512_Cleaning-Lining_Water_Mains_2026.pdf PDF
ESC_Minor_Utility_Permit,_Health_and_Safety_Qualification_Questionaire,_and_Example_Health_and_Safety_Plan_outline.pdf PDF
02510_Water_Distribution_System_Contractor_Furnishes_All_Materials_2026.pdf PDF
02511_Chlorination_and_Dechlorination_2026.pdf PDF
02446_Horiz_Directional_Drilling_2026.pdf PDF
01500_Temp_Facilities_Controls_2026.pdf PDF
02445_Boring-Jacking_2026.pdf PDF
01110_Summary_of_Work_2026.pdf PDF
00600_TOC_Specs_2026.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

02960-1 2026

STANDARD SPECIFICATIONS

SECTION 02960

TEMPORARY BYPASS PUMPING SYSTEMS

PART 1 GENERAL

1.1 DESCRIPTION

A. Section includes requirements for implementing a temporary pumping system for the purpose of diverting existing sewage flow around work area for duration of the project.

1.2 QUALITY ASSURANCE

A. Follow national standards and as specified herein.

B. Perform leakage and pressure tests on discharge piping using clean water, before operation. Notify Engineer 24 hours prior to testing.

C. Maintain and inspect temporary pumping system every two hours. Responsible operator: On site when pumps are operating.

D. Keep and maintain spare parts for pumps and piping on site, as required.

E. Maintain adequate hoisting equipment and accessories on site for each pump.

1.3 SUBMITTALS

A. Submit following Section 01330.

1. Detailed plan and description of proposed pumping system. Indicate number, size, material, location and method of installation of suction and discharge piping, size of pipeline or conveyance system to be bypassed, staging area for pumps, site access point, and expected flow.

a. Size and location of manhole or access points for suction and discharge hose or piping.

b. Sections showing suction and discharge pipe depth, embedment, select fill and special backfill, if buried.

c. Temporary pipe supports and anchoring required.

d. Thrust and restraint block sizes and locations.

e. Sewer plugging method and type of plugs.

f. Bypass pump sizes, capacity, number of each size to be on site and power requirements.

g. Backup pump, power and piping equipment.

h. Calculations of static lift, friction losses, and flow velocity. Pump curves showing pump operating range.

02960-2 2026

i. Design plans and computation for access to bypass pumping locations indicated on drawings.

j. Calculations for selection of bypass pumping pipe size.

k. Method of noise control for each pump and/or generator.

l. Method of protecting discharge manholes or structures from erosion and damage.

m. Schedule for installation and maintenance of bypass pumping lines.

n. Procedures to monitor upstream mains for backup impacts.

o. Procedures for setup and breakdown of pumping operations.

p. Emergency plan detailing procedures to be followed in event of pump failures, sewer overflows, service backups, and sewage spillage.

1) Maintain copy of emergency plan on site for duration of project.

B. Submit following Section 01450.

1. Certify bypass system will meet requirements of codes, and regulatory agencies having jurisdiction.

1.4 CONTRACTORS RESPONSIBILITY FOR OVERFLOWS AND SPILLS

A. Schedule and perform work in manner that does not cause or contribute to incidence of overflows, releases or spills of sewage from sanitary sewer system or bypass operation.

1.5 DELIVERY AND STORAGE

A. Transport, deliver, handle, and store pipe, fittings, pumps, ancillary equipment and materials to prevent damage and following manufacturer’s recommendations.

1. Inspect all material and equipment for proper operation before initiating work.

B. Material found to be defective or damaged due to manufacturer or shipment.

1. When Engineer deems repairable: Repair as recommended by manufacturer.

2. When Engineer deems not repairable: Replace as directed by Engineer before initiating work.

3. Repair or replacement of defective or damaged material and equipment will be at no cost to Commission.

PART 2 PRODUCTS

2.1 MATERIALS

A. Discharge and Suction Pipes: Approved by Engineer.

1. Discharge piping: Determined according to flow calculations and system operating calculations.

2. Suction piping: Determined according to pump size, flow calculations, and manhole depth following manufacturer’s specifications and recommendations.

02960-3 2026

B. Polyethylene Plastic Pipe:

1. High density solid wall and following ASTM F714 Polyethylene (PE) Plastic Pipe

(SDR-DR) based on Outside Diameter, ASTM D1248 and ASTM D3550

2. Homogenous throughout, free of visible cracks, discoloration, pitting, varying wall thickness, holes, foreign material, blisters, or other deleterious faults.

C. High-Density Polyethylene (HDPE).

1. Homogenous throughout, free of visible cracks, discoloration, pitting, varying wall thickness, holes, foreign material, blisters, or other deleterious faults.

a. Defective areas of pipe: Cut out and joint fused as stated herein.

2. Assembled and joined at site using couplings, flanges or butt-fusion method to provide leak proof joint. Follow manufacturer’s instructions and ASTM D 2657.

a. Threaded or solvent joints and connections are not permitted.

3. Fusing: By personnel certified as fusion technicians by manufacturer of HDPE pipe and/or fusing equipment.

4. Butt-fused joint: True alignment and uniform roll-back beads resulting from use of proper temperature and pressure.

a. Allow adequate cooling time before removal of pressure.

b. Watertight and have tensile strength equal to that of pipe.

c. Acceptance by Engineer before insertion.

5. Use in streams, storm water culverts and environmentally sensitive areas.

D. Flexible Hoses and Associated Couplings and Connectors.

1. Abrasion resistant.

2. Suitable for intended service.

3. Rated for external and internal loads anticipated, including test pressure.

a. External loading design: Incorporate anticipated traffic loadings, including traffic impact loading.

4. When subject to traffic loading, compose system, such as traffic ramps or covers.

a. Install system and maintain H-20 loading requirements while in use, or as directed by the Engineer.

E. Valves and Fittings: Determined according to flow calculations, pump sizes previously determined, and system operating pressures.

F. Plugs: Selected and installed according to size of line to be plugged, pipe and manhole configurations, and based on specific site.

1. Additional plugs: Available in the event a plug fails. Plugs will be inspected before use for defects which may lead to failure.

G. Aluminum “irrigation type” piping or glued PVC piping will not be permitted.

H. When approved by Engineer, discharge hose will be allowed in short sections.

2.2 EQUIPMENT

02960-4 2026

A. Pumps.

1. Fully automatic self-priming units that do not require the use of foot-valves or vacuum pumps in priming system.

2. Electric or diesel powered.

3. Constructed to allow dry running for long periods of time to accommodate cyclical nature of effluent flows.

4. Provide.

a. Necessary stop/start controls for each pump.

b. One standby pump of each size maintained on site.

1) On-line, isolated from primary system by a valve.

c. Quiet flow pumps at request of Engineer.

2.3 DESIGN REQUIREMENTS

A. Bypass pumping systems:

1. Sufficient capacity to pump peak flow of 15 mgd.

a. Peak flows greater than 15 mgd as approved by Engineer.

b. Commission will provide flow data for bypass system.

2. Operate 24 hours per day.

B. Provide pipeline plugs and pumps of adequate size to handle peak flow, and temporary discharge piping to ensure total flow of main can be safely diverted around section to be repaired.

PART 3 EXECUTION

3.1 PUBLIC NOTIFICATION

A. Follow Section 01110.

3.2 PREPARATION

A. Determining location of bypass pipelines.

1. Minimal disturbance to existing utilities.

a. Field locate existing utilities in proposed bypass area.

2. Obtain approvals for placement within public or private property.

3. Obtain Engineer’s approval of location.

4. Costs associated with relocation of utilities and obtaining approvals at no cost to the Commission.

3.3 INSTALLATION AND REMOVAL

A. Provisions and requirements must be reviewed by Engineer before starting construction.

02960-5 2026

B. Remove manhole sections or make connections to existing sewer and construct temporary bypass pumping structures at access location indicated on Drawings and as required to provide adequate suction conduit.

C. Plugging or blocking of sewage flows shall incorporate a primary and secondary plugging device. When plugging or blocking is no longer needed for performance and acceptance of work, remove in a manner that permits the sewage flow to slowly return to normal without surge, to prevent surcharging or causing other major disturbances downstream.

D. When working inside manhole or force main, exercise caution. Follow OSHA, Local, State and Federal requirements. Take required measures to protect workforce against sewer gases and/or combustible or oxygen-deficient atmosphere.

E. Installation of Bypass Pipelines:

1. Pipeline may be placed along shoulder of roads.

a. Do not place in streets or sidewalks.

2. When bypass pipeline crosses local streets and private driveways, place in roadway ramps.

a. When roadway ramps cannot be used, place bypass in trenches and cover with temporary pavement as approved by Engineer.

b. Follow Section 02510.

F. During bypass pumping operation, protect sewer lines from damage inflicted by equipment.

G. Upon completion of bypass pumping operations, and after the receipt of written permission from Engineer, remove piping, restore property to pre-construction condition and restore pavement.

PART 4 MEASUREMENT AND PAYMENT

4.1 Except as otherwise specified herein, providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.

**WSSC**

1.1 DESCRIPTION
1.2 QUALITY ASSURANCE
1.3 SUBMITTALS
1.4 CONTRACTORS RESPONSIBILITY FOR OVERFLOWS AND SPILLS
1.5 DELIVERY AND STORAGE
2.1 MATERIALS
2.2 EQUIPMENT
2.3 DESIGN REQUIREMENTS
3.1 PUBLIC NOTIFICATION
3.2 PREPARATION
3.3 INSTALLATION AND REMOVAL
4.1 Except as otherwise specified herein, providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.