Submittal Procedures Document Summary

This is a Standard Specifications section detailing submittal procedures for the Washington Suburban Sanitary Commission (WSSC) in Maryland for construction projects. The document establishes comprehensive requirements for contractors to prepare and submit various documentation including schedules, shop drawings, catalog data, working drawings, method of construction statements, samples, and record drawings to demonstrate compliance with contract requirements. All submittals must be made electronically through E-Builder, WSSC's online construction management tool, with hard copies provided only in specific circumstances such as drawings exceeding 11"x17" or containing more than 50 pages. Within three days of the preconstruction conference, contractors must submit a list of materials and equipment suppliers with contact information, and within 30 days of the Notice to Proceed, a complete submittal schedule organized by specification section with approximate submission dates.

The approval process includes four classifications: Approved, Approved as Noted (requiring minor corrections), Revise and Resubmit (requiring major corrections), and Rejected, with the Engineer returning submittals within 30 days. Construction schedules must be submitted within 15 days of the Notice to Proceed in either Critical Path Method (CPM) format using Primavera P6 or MS Project, or as an approved Bar Chart schedule, with detailed network analysis due within 45 days including activity descriptions, durations in working days (minimum one day, maximum 30 calendar days), and identification of critical materials such as pipe and fittings. Record drawings must be submitted within 10 working days of substantial completion using green-line markings for water as-built conditions and red-line markings for sewer as-built conditions, including fire hydrant summary sheets and grade notes. Operation and Maintenance Manuals must be submitted as preliminary electronic indexed PDFs prior to equipment shipment, with five final hard copies and a PDF version provided before any required testing begins. All costs associated with submittal preparation and compliance are considered incidental to the contract and are not separately measured for payment.

View the file

Other files

File Type Posted
Water_and_Wastewater_Engineering_Services_Basic_Ordering_Agreement_(Addendum_#3_Revision).pdf PDF
Water_and_Wastewater_Engineering_Services_Basic_Ordering_Agreement.pdf PDF
Sample_Invoice_Template_4.20.2026.xls XLS spreadsheet
WSSC_Pipeline_Design_Manual_2017_(1).pdf PDF
101624_SAMPLE_BOA_Water_Wastewater_Eng_Serv_4.20.26.pdf PDF
01150_Site_Conditions_2026.pdf PDF
02070_Geosynthetics_2026.pdf PDF
03300_Cast-in-Place_Concrete_2026.pdf PDF
Section_IV_-_Water_Details.pdf PDF
Section_VI_-_Corrosion_Details.pdf PDF
02955_Sewer_Mains_Lateral_Rehabilitation_by_Lining_2026.pdf PDF
02370_Slope-Watercourse_Protection_2026.pdf PDF
02315_Earthwork_for_Pipeline_Construction_2026.pdf PDF
02930_Exterior_Plants_2026.pdf PDF
02441_Microtunneling_2026.pdf PDF
Section_VIII_-_Sediment_Control_Details.pdf PDF
Section_III_-_Sewer_Details.pdf PDF
01630_Substitution_Procedures_2026.pdf PDF
02959_Sewer_Main_and_Lateral_Connection_Sealing_2026.pdf PDF
02230_Site_Clearing_2026.pdf PDF
02446_Horiz_Directional_Drilling_2026.pdf PDF
02512_Cleaning-Lining_Water_Mains_2026.pdf PDF
02530_Sanitary_Sewage_System_2026.pdf PDF
05500_Metal_Fabrications_2026_(1).pdf PDF
02533_Pressure_Sewer_System_2026.pdf PDF
02960_Temporary_Bypass_Pumping_System_2026.pdf PDF
02958_Pipe_Bursting_2026.pdf PDF
02950_Paving_Requirements_2026_(1).pdf PDF
Section_I_-_General_Notes_0.pdf PDF
01110_Summary_of_Work_2026.pdf PDF
Section_II_-_Miscellaneous_Details.pdf PDF
01500_Temp_Facilities_Controls_2026.pdf PDF
02445_Boring-Jacking_2026.pdf PDF
02511_Chlorination_and_Dechlorination_2026.pdf PDF
02957_Sewer_Manhole_Rehabilitation_2026.pdf PDF
02920_Lawns-Grasses_2026.pdf PDF
02510_Water_Distribution_System_Contractor_Furnishes_All_Materials_2026.pdf PDF
Section_IX_-_Procurment_and_Manufacturing_Details_(1)_(1).pdf PDF
01570_Temp_Erosion-Sediment_Control_2026.pdf PDF
02510_Water_Distribution_System_2026.pdf PDF
04200_Masonry_2026.pdf PDF
13110_Cathodic_Protection_2026.pdf PDF
02820_Fences-Gates_2026.pdf PDF
01450_Quality_Control_2026.pdf PDF
13112_Impressed_Current_Cathodic_Protection_for_Water_Sewer_Pipelines_2026.pdf PDF
01770_Project_Cleanup_2026.pdf PDF
02956_CCTV_Inspection_of_Sewer_Mains,_Manholes_and_Laterals_2026.pdf PDF
03400_Precast_Concrete_Underground_Structures_2026.pdf PDF
00600_TOC_Specs_2026.pdf PDF
WSSC_Pipeline_Design_Manual_2017.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01330-1 2026

STANDARD SPECIFICATIONS

SECTION 01330

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 DESCRIPTION

A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to include Schedules, Contractor's Drawings, Samples, Manuals, Methods of Construction, and Record Drawings to Engineer demonstrating performance of Work.

1. Other requirements for submittals are specified under applicable sections of Standard Specifications and Special Provisions.

1.2 SUBMITTAL REQUIREMENTS

A. General.

1. Submit each under separate cover or transmittal.

2. Furnish neat, legible, and sufficiently explicit detail to enable proper review for Contract compliance. Illegible submittals shall be considered incomplete or defective and will be returned.

3. Show complete and detailed fabrication; assembly and installation details;

wiring and control diagrams; catalog data; pamphlets; descriptive literature; and performance and test data.

4. Include calculations or other information sufficient to show comprehensive description of structure, machine, or system provided and its intended manner of use.

a. With each submission, furnish Engineer specific written notation and justification of each variation in Contractor's Submittals from requirements of Contract Documents.

b. Fabrication, purchase or delivery of materials to the site, and installation of materials or Work performed before approval, or not conforming to approved submittals, shall be at Contractor's risk.

5. Engineer’s review and approval of submittals shall not relieve Contractor from responsibility for fulfillment of terms of Contract, unless Engineer has received specific written notice of each variation and has given specific written approval.

6. Contractor assumes all risks of error and omission.

7. Contract Work, Materials, Fabrication, and Installation: Following approved submittals.

8. Submittals shall be made electronically through the Commission’s online construction management tool, currently E-Builder. Hard copies shall be provided only as noted herein. When a hard copy is submitted, a transmittal of those items shall be made through E-Builder noting how the hard copy or sample was submitted to the Engineer.

01330-2 2026

B. Process and Requirements.

1. Not later than 3 days after preconstruction conference, submit written list of materials and equipment to be purchased, giving name, address, and telephone number of Supplier, Manufacturer, or processor.

a. Submit updated material and equipment list when changes are made.

2. Coordinate and schedule submittals with construction schedule and

Engineer.

3. With the first submittal, but not later than 30 days after Notice to Proceed, submit a complete submittal schedule, listing as near as practicable and by Specification Section number, submittals required and approximate date submittal will be forwarded.

a. Arrange submittals schedule so that related equipment items are submitted concurrently.

b. Engineer may require changes to submittal schedule to permit concurrent review of related equipment.

4. To each submittal affix the following signed Certification Statement.

a. "Certification Statement: By this submittal, we hereby represent that we have determined and verified all field measurements, field construction criteria, materials, dimensions, catalog numbers and pertinent data and we have checked and coordinated each item with other applicable approved drawings and all Contract requirements.”

5. Identification.

a. Submit identification data, as applicable, contained thereon or permanently adhered thereto:

1) The Commission Contract Number.

2) Project name and location.

3) Submittal Numbers:

a) Number sequentially as submitted.

b) Resubmittals shall bear original submittal number and be sequentially lettered.

4) Product identification.

5) Drawing title, drawing number, revision number, and date of drawing and revision.

6) Applicable Contract Drawing Numbers and Specification

Section and Paragraph Numbers.

7) Subcontractor's, Vendor's and/or Manufacturer's name, address and phone number.

8) Contractor's Certification Statement.

b. Identify on exterior, catalog product data or brochures submitted in packages of multiple items. Include page and catalog item numbers for items submitted.

1) Highlight catalog, product data, or brochures containing various products, sizes, and materials to show particular item submitted.

2) Mark items not applicable to Contract "not applicable" or cross out.

3) If one or more items in catalog submittal are not approved, resubmit only unapproved items.

01330-3 2026

6. Number of Copies: See requirements in Submittals specified herein.

7. Approval Process.

a. Follow submittal schedule provided to Engineer. Engineer will return submittal within 30 days.

b. Submittals will be returned, marked with one of following classifications:

1) APPROVED: Requires no corrections, no marks.

2) APPROVED AS NOTED: Requires minor corrections. Items may be fabricated as marked without further resubmission.

Resubmit 2 corrected copies to the Engineer.

3) REVISE AND RESUBMIT: Requires corrections. No items may be fabricated. Resubmit entire submittal following original submission with corrections noted. Allow 30 days for checking and Engineer’s appropriate action.

4) REJECTED: Requires major corrections or is otherwise not following Contract Documents. No items shall be fabricated.

Resubmit entire submittal following original submission with corrections noted. Allow 30 days for checking and Engineer’s appropriate action.

5) INFORMATION ONLY: Items specified by Contract Documents.

C. Electronic Submittals: PDF Format, as approved by Engineer.

1.3 SUBMITTALS

A. Schedules. (Excluding Area service connection contracts AC, LC)

1. Material Supply Availability

a. Within 10 days of the Notice to Proceed, submit a list of all critical materials to be supplied on the Contract. Include the name of the supplier, the quantity of material, the lead time for the materials, and the expected delivery date for the materials. Should the material availability impact the ability to begin work, provide a written request to delay the start of on-site activities to accommodate material deliveries. Reflect material availability and delivery in the project schedule.

2. Schedule of Breakdown for Each or Lump Sum Items:

a. Before first application for payment, submit to Engineer schedule of breakdown for lump sum items, aggregating total amount bid for each. Include with each breakdown its proper share of overhead, profit, and applied General Conditions. Subdivide Work into activities on Construction Schedule in sufficient detail. Coordinate with breakdowns submitted herein, to serve as basis for progress payments during construction.

b. Prepare schedule of breakdown in form acceptable to Engineer and furnish with data to substantiate its correctness as Engineer may require.

3. Construction Schedule - Critical Path Method.

a. Within 15 days after construction start date in Notice to Proceed, prepare and submit a preliminary schedule in time-scale format, indicating planned operations during first 60 days. Include cost of activities expected to be completed or partially completed before submission and mutual acceptance of entire schedule. Acceptable schedule formats include the latest version of

01330-4 2026

Primavera P6 and MS Project.

b. Submit original schedules and updates in the original program native format, including all calendars and resource files. In addition to the native format, submit a PDF version of the schedule formatted as a Gantt chart and scaled to fit on 11x17 sheets. If the time scale extends to multiple sheets, include the columns identifying the activities on each sheet.

c. When the base schedule has been approved, submit a full copy of the schedule with an accepted baseline.

d. Within 45 days after construction start date in Notice to Proceed, submit 5 copies of a complete network analysis system, showing usage of entire Contract Time, consisting of detailed network, mathematical analysis, and network diagram. Present schedule in the form of an Arrow Diagramming Method (ADM) CPM Network Diagram.

1) Show order and interdependence of activities and sequence in which Work will be accomplished. Show how the start of a given activity is dependent on completion of preceding activities and how its completion restricts start of following activities.

2) Show following detailed network activities on network diagram, in addition to construction activities;

a) Submittal and approval of samples and submittals.

b) Procurement of critical materials and equipment.

c) Identify when critical materials (pipe, fittings, valves) are to be on site and available for the next phase of work.

d) When supply chain is critical to ongoing water and sewer main work, divide work into appropriate phases. Demonstrate that materials will be on site for each phase of the work.

e) When work includes water main bypass, include a task for installation and removal of all bypass. Schedule shall reflect the requirement to remove bypass by November 15.

f) When work includes sewer bypass, indicate the set-up and removal of the bypass system.

g) Fabrication of materials and equipment, their installation and testing.

h) Specified intermediate milestone or completion dates.

i) Show duration of each activity in working days, with minimum of 1 working day and maximum of 30 Calendar days for any on site activity. Material and equipment related delivery activities are exempt from the maximum duration requirement.

j) For projects affecting greater than approximately 1 mile of water main, the construction schedule shall reflect Sequence of Construction requirements provided in Section 01110 and as modified elsewhere in contract documents. Deviations from these requirements shall be noted in the schedule narrative and are subject to approval by the ENGINEER. Work on subsequent phases shall not begin until all main in the previous phase is complete and at least 50% of the connections are complete.

3) Group related activities on network and highlight activities on critical path. Time-scale network using units of approximately 1/2-inch equals 1 week or other suitable scale approved by Engineer. Indicate weekends

01330-5 2026 and holidays. Where slack exists, show activities at earliest time they are scheduled to be accomplished. Use sheet size 22 inch by 34 inch minimum, or per Engineer’s approval. Place title and revision block in lower right-hand corner. Give dummies duration of zero.

4) Include tabulation of each activity shown on detailed network diagram in the mathematical analysis. Furnish following information as minimum for each activity:

a) Activity node numbers (I/J).

b) Activity description.

c) Duration of activity in units of working days.

d) Earliest start date (by calendar date).

e) Earliest finish date (by calendar date).

f) Scheduled or actual start date (by calendar date).

g) Scheduled or actual finish date (by calendar date).

h) Latest start date (by calendar date).

i) Latest finish date (by calendar date).

j) Slack or Float (working days).

k) Activity percent complete and remaining duration.

l) Monetary value of activity.

m) Responsibility code for each activity (Prime Contractor, subcontractors, suppliers, the Commission).

n) Manpower required by trade and by total.

o) Equipment required.

5) List activities in sorts or groups in mathematical analysis:

a) Ascending activity node number (I/J).

b) Amount of total float, then in order of activity number.

c) Latest start date, then in order of activity number.

d) Responsibility in order of earliest start date.

6) To facilitate review of payment requests, submit separate sort consisting of activities to which monetary values are assigned. Organize by node number from lowest to highest and then in order of following node number. As minimum for each monetary activity furnish:

a) Activity node numbers (I/J).

b) Activity description.

c) Monetary value of activity.

d) Previous amount.

e) Current amount.

7) Furnish initial submittal and revisions in 3 copies.

e. Review of system:

1) Participate in Engineer’s review and evaluation of proposed network diagrams and analysis. Resubmit revisions necessary as a result of this review to Engineer within 10 days after conference. Allow 20 days for Engineer’s checking and further action.

2) Progress payments will be withheld pending attainment of mutually acceptable schedule. Engineer’s review and mutual acceptance of Contractor’s schedule is for conformance to requirements of the Contract Document. Review and mutual acceptance by Engineer of Contractor’s schedule does not relieve Contractor of any of its Contract Document

01330-6 2026 responsibilities for accuracy or feasibility of schedule, or of Contractor’s ability to meet interim project milestone dates and Contract completion date, nor does such review and mutual acceptance expressly or impliedly warrant, acknowledge or admit the reasonableness of the logic, durations, manpower, or equipment loading of Contractor’s schedule.

3) Contractor shall use mutually accepted schedule for planning, organizing, directing, and executing Work and for reporting progress.

4) To make subsequent changes to method of operating and scheduling, submit written request separately to Engineer for review, stating reasons for change(s). For major changes, Engineer may require Contractor to revise and submit, without additional cost to the Commission, all affected portions of network diagram and mathematical analysis to show effect on entire project. Change may be considered major if time estimated or actually used for an activity or logic of sequence of activities is so varied from original plan that there is reasonable doubt about effect on Contract completion date or dates. Changes affecting activities with adequate slack time shall be considered minor, except that accumulation of minor changes may be considered major when their cumulative effect might affect Contract completion date. Incorporate mutually accepted changes into next monthly update.

f. Submit at 30-day intervals, a report of actual construction progress by updating mathematical analysis sorts and graphically generating and reproducing a copy of current network diagram. Include issued change orders in updated schedule.

Revise network diagram as described above and as necessary for clarity.

g. Show activities or portions of activities completed during reporting period and their total value as basis for Contractor's periodic request for payment.

Coordinate these activities or portions of activities with breakdown for lump sum items herein. State percentage of Work actually completed and scheduled as of report date and progress along critical path in terms of days ahead or behind mutually accepted schedule dates.

1) If project is behind schedule, report progress along other paths with negative slack. Engineer will review percentage of work actually completed following procedures set forth in General Conditions Article 22.

2) If Contractor fails to submit required monthly reports and updates within time prescribed, Engineer may withhold approval of progress payment estimates until Contractor submits acceptable required reports and updates. Submit 3 copies of report for each update.

h. Simultaneously submit a narrative report with updated analysis, which shall include but not be limited to description of problem areas, current and anticipated delaying factors, their impact, and an explanation of corrective actions taken or proposed.

i. Float or slack is defined as difference in working days between earliest start date and latest start date, or difference between earliest finish date and latest finish date of any activity of mathematical analysis of 2., c., 4) herein. Float or slack is not for exclusive use of Contractor or the Commission.

j. Requests for Contract Time extension:

1) Accompanied by revised schedule, or portion thereof, and mathematical

01330-7 2026 analysis.

2) Based on affect of controlling delays to the Work as a whole.

4. Construction Schedule – Bar Chart Form.

a. With written approval of the engineer, the Contractor may substitute the CPM schedule with a Bar-Chart Schedule. Should the bar-chart be inadequate for the work, the COMMISION may direct the use of a Critical Path Schedule.

When approved by the Engineer, provide the bar-chart schedule within 15 days after construction start date in Notice to Proceed, prepare and submit to Engineer for review, feasible and reasonable schedule showing Order of Work and start and finish dates of salient milestones, referencing work by street name. Submit in Microsoft Project 2007 (or later) compatible format by digital delivery (email or CD) and 2 copies of printed format to Contract Manager.

Show usage of entire Contract Time and include dates for submittals, approval of samples and submittals, and procurement of materials, plant, and equipment. Using sufficient detail, subdivide Work into activities on Construction Schedule, coordinate with breakdowns for lump sum items herein, to serve as basis for progress payments during construction.

b. When the base schedule has been approved, submit a full copy of the schedule with an accepted baseline.

c. For projects affecting greater than approximately 1 mile of water main, the construction schedule shall reflect Sequence of Construction requirements provided in Section 01110 and as modified elsewhere in contract documents.

Deviations from these requirements shall be noted in the schedule narrative and are subject to approval by the Engineer.

d. In addition to pipe installation, the schedule must include, but not be limited, to information on submittals, test pits, bypass installation, contract and permit restrictions, and material delivery. Bypass construction cannot begin without a schedule for material delivery that meets all contract requirements including but not limited to winter bypass restrictions.

e. Furnish such additional information and data required by Engineer to justify basis of schedule precedent to mutual acceptance. Engineer’s review and mutual acceptance of Contractor’s schedule is for conformance to requirements of the Contract Document. Review and mutual acceptance by Engineer of Contractor’s schedule does not relieve Contractor of any of its Contract Document responsibilities for accuracy or feasibility of schedule, or of Contractor’s responsibility to meet interim project milestone dates and Contract completion date.

f. Submit with each request for payment, in same format specified above, actual performance against scheduled performance on the mutually accepted construction schedule, including work added by change order. If Contractor fails to submit required updated schedule within time prescribed, Engineer may withhold approval of progress payment estimates until Contractor submits required current updated schedule.

g. Use mutually accepted schedule for planning, organizing, directing, and executing Work and for reporting progress. Engineer may order and authorize minor changes to this schedule whenever they are of definite advantage to or necessary for operations of the Commission.

01330-8 2026

B. Shop Drawings.

1. For original submittal and each subsequent re-submittal required, submit electronic versions via the Commission’s web based construction management tool (currently E-Builder). Submit 3 hard copies of shop drawings with pages larger than 11”x17” or that exceed 50 pages in length unless otherwise approved by the Engineer.

2. Show types, sizes, accessories, and layouts, including plans, elevations, and sectional views; component, assembly, and installation details; and all other information required to illustrate how applicable portions of Contract requirements will be fabricated and/or installed.

3. In case of fixed mechanical and electrical equipment, submit layout drawings drawn to scale, to show required clearances for operation, maintenance, and replacement of parts. Include manufacturer's certified performance curves, catalog cuts, pamphlets, descriptive literature, installation, and application recommendations, as required.

Submit together shop drawings for closely related items such as a pump and its motor. Additional shop drawings and information required for electrical and mechanical equipment are listed in appropriate Specification Sections.

4. Shop drawings for continually furnished items such as pipe, fittings, valves, precast structures and metal work will be waived provided Contractor submits a letter naming manufacturer who will furnish these items. Manufacturer shall have on file certified drawing(s) containing above information approved by the Commission, and items furnished shall be as described on certified drawing(s). If Standard Details or Specifications change after certified drawings are approved, new submittals are required.

C. Catalog Data.

1. For original submittal and each subsequent resubmittal required, submit electronic versions of catalog data via E-Builder. Submit 3 hard copies of catalog data that contain drawings larger than 11”x17” or that exceed 50 pages in length unless otherwise approved by the Engineer.

2. Manufacturer's Catalog, Product, and Equipment Data: Certified and include material type, performance characteristics, voltage, phase, capacity, and similar data.

3. Furnish wiring diagrams when applicable.

4. Indicate catalog, model, and serial numbers representing specified equipment.

5. Submit complete component information to verify specified required items.

D. Working Drawings.

electronic versions of all working drawings via E-Builder. Submit 3 hard copies of working drawings that contain drawings larger than 11”x17” or that exceed 50 pages in length unless otherwise approved by the Engineer.

2. Submit working drawings as required for changes, substitutions, Contractor design items, and Contractor designed methods of construction. Requirements for working drawings are listed in appropriate Specification Sections or in Special Provisions.

3. Include with drawings calculations or other information to completely explain structure, machine, or system described and its intended use.

01330-9 2026

Review or approval of drawings by Engineer shall not relieve Contractor from responsibility for fulfillment of terms of Contract. Contractor assumes risks of error, and Engineer shall have no responsibility.

4. Submit working drawings and calculations sealed, dated, and signed by Professional Engineer registered in State of Maryland and experienced in the work or discipline involved.

E. Method of Construction.

electronic versions of data detailing method of construction via E-Builder.

2. When Engineer specifies or directs, submit proposed method of construction for specific portions of Work.

a. Include detailed written description of phases of construction operation to fully explain to Engineer proposed method of construction.

b. If required by Specifications, submit working drawings to supplement description.

3. Engineer review will follow the process herein and shall not relieve Contractor from responsibility for fulfillment of terms of Contract.

Contractor assumes risks associated with proposed method.

4. After review, submit requests for modifications in detail, including justification for them. Do not implement modifications prior to Engineer’s review.

F. Manufacturer's Installation Recommendations and Installer Qualification.

electronic version of manufacturer’s installation recommendations via E- Builder.

2. Furnish written detail for step-by-step preparation and installation of the materials and products, including recommended tolerances and space for maintenance and operation.

3. When technical specifications outline the qualifications of the installer, whether the contractor/subcontractor or contractor personnel, submit documentation to demonstrate compliance with the qualification requirements for that specific application.

G. Samples.

1. General: As soon as practicable after Notice to Proceed, submit samples required by Specifications or at Engineer’s request. Unless otherwise specified, submit 3 samples of each item as original submittal.

2. Obtain approval before delivery of material to Contract site.

3. Samples: Representative of actual material proposed for use in project and of sufficient size to demonstrate design, color, texture, and finish when these attributes will be exposed to view.

a. If samples deviate from Contract Documents, advise Engineer in writing with submittal and state reason.

4. Identification.

a. Permanently attach to each sample:

1) The Commission Contract Number.

01330-10 2026

2) Project Name and Location.

3) Product Identification.

4) Applicable Contract Drawing and Specification Section Number.

5) Subcontractor's, Vendor's and/or Manufacturer's Name, Address and

Phone Number.

b. Mail under separate cover a letter submitting each shipment of samples containing identification information listed herein. Enclose copy of this letter with shipment.

5. Approval Process.

a. Allow 30 days for Engineer’s checking and appropriate action. Certain samples may be tested for specified requirements by the Commission before approval. Failure of sample to pass tests will be sufficient cause for refusal to consider further samples of same brand and make of that material.

b. Rejected samples will be returned upon request, and resubmittals required shall consist of 3 new samples and an additional 30 days for review.

Only 1 test of each sample proposed for use will be made at expense of the Commission. When originally submitted sample fails, retesting of additional samples will be made by the Commission at expense of Contractor. Upon approval, 1 sample so noted will be returned, and remainder will be retained by Engineer until completion of Work.

c. Samples of various material or equipment delivered to site or during placement may be taken by Engineer for testing. Samples failing to meet Contract requirements will automatically void previous approvals, and resubmittal of samples will be required.

H. Record Drawings (As-builts).

1. The Contractor will be responsible for preparation and maintenance of record drawings. Coordinate and cooperate with Commission personnel in preparation. Do not permanently seal or bolt manhole covers until after as-built surveys have been made.

2. Submit record drawings within 10 working days of substantial completion using the Commission’s electronic as-built submittal tool or other method approved by the Engineer. Record drawings shall be neat and legible using appropriate markings and colors to reflect the as-built conditions.

Submittals shall be made via the COMMISSION’s online-construction management tool as a PDF unless another format is approved by the Engineer (e.g. DWG may be acceptable). The final submittal shall include but not be limited to:

a. Water As-built Drawings, showing all built modifications and annotations in green (“Green-Line Drawings”), including the most current revisions to the Drawings and Profile, and connections permit numbers when applicable.

b. Sewer As-built Drawing showing all as-built modifications and annotations in red (“Red-Line Drawings”), including the most current revisions to the Drawings and Profile, and connections permit numbers when applicable. When modified from plan, include sewer invert elevations. Sewer as-built that include lining should indicate

01330-11 2026 the liner thickness and type of curing used.

c. Fire Hydrant Summary Sheet.

d. Sewer As-built Data Work Sheet.

e. Copy of the water and sewer grade notes sheets, including field notes.

3. Maintain at least 1 record copy of Contract Documents at site in good order and annotated to show revisions made during construction. Keep annotations current for possible monthly inspection. The Commission may inspect as-built documents prior to processing of monthly pay estimates.

a. Make record drawings available to Engineer at all times during life of Contract. The Commission will make digital versions of the Contract Drawings available to the Contractor.

b. Drawings: Made part of record drawings and to include:

1) Contract Drawings: Annotate or redraft, as required, to show revisions, substitutions, variations, omissions, and discrepancies made or discovered during construction concerning location and depth of utilities, piping, duct banks, conduits, manholes, pumps, valves, vaults, and other equipment. Make revisions and show on all drawing views with actual dimensions established to permanent points.

2) Modifications or annotations to the drawings shall be clearly marked using the revision block, a number within a triangle to identify the change and the change shall be clouded on the drawing.

3) As-Built drawings shall identify the type and manufacturer of all valves used on the project.

4) Working/Layout Drawings: When required as submittals, record actual layouts of conduit runs between various items of electrical equipment for power, control, and instrumentation; wire sizes, numbers, and functions; configuration of conduits; piping layouts;

and duct layouts. Add sections and details as required, for clarity.

Revise drawings of switchgear, motors, control centers and other equipment to show actual installations.

I. Operation and Maintenance Manuals.

1. Furnish Operation and Maintenance Manuals for various types of equipment and systems, as required by Contract Documents. Unless otherwise indicated, furnish separate manual for each piece of equipment and system. If manual contains other items or equipment, indicate where specified items are located in manual. Include in manual complete information necessary to operate, maintain, and repair specific equipment and system furnished under this Contract, and include the following specific requirements;

a. Contents:

1) Table of Contents and Index.

2) Brief description of equipment/system and principal components.

3) Starting and stopping procedures, both normal and emergency.

4) Installation, maintenance, and overhaul instructions including detailed assembly drawings with parts list and numbers, and recommended spare parts list with recommended quantity, manufacturer's price, supplier's

01330-12 2026 address, and telephone number.

5) Recommended schedule for servicing, including technical data sheets that indicate weights and types of oil, grease, or other lubricants recommended for use and their application procedures.

6) One copy of each component wiring diagram and system wiring diagram showing wire size and identification.

7) One approved copy of each submittal with changes made during construction properly noted, including test certificates, characteristic curves, factory and field test results.

8) For electrical systems, include dimensioned installation drawings, single line diagrams, control diagrams, wiring and connection diagrams, list of material for contactors, relays and controls, outline drawings showing relays, meters, controls and indication equipment mounted on equipment or inside cubicles, control and protective schematics, and recommended relay settings.

b. Material:

1) Covers: Oil, moisture, and wear resistant 9 inches by 11-1/2 inches size.

2) Pages: 60-pound paper 8-1/2 inches by 11 inches size with minimum of 2 punched holes 8-1/2 inches apart reinforced with plastic, cloth, or metal.

3) Fasteners: Metal screw post or Acco metal strap type.

4) Diagrams and Illustrations: Attach foldouts, as required.

5) Legible Original Quality: Reproduced by dry copy method.

2. Copies:

a. Submit preliminary electronic copies of each manual for review and approval no later than date of shipment of equipment. The electronic version shall be an indexed PDF. Installation shall not begin until manuals are accepted by Engineer. Include in preliminary copies all items required under “Contents” above.

b. Unless otherwise specified, provide five (5) hard copies of final approved manuals to the engineer prior to any required testing and submit an indexed PDF version via E-Builder.

J. Substitutions: See Section 01630.

K. Construction Videotape and Photographs Submittal:

1. The Contractor shall provide digital video and photographic records of pre-construction conditions, construction progress and post-construction conditions as follows:

a. Before commencing the Work, the Contractor shall provide a video record of the pre-construction conditions of the site, roadways, or property that might be affected by the Contractor's operations both directly and indirectly during the Work. Two copies of the video record of pre-construction conditions shall be submitted prior to the commencement of the Work. All video and photographs shall be taken by a professional photographer, or by an employee of the Contractor who can demonstrate proficiency at professional quality photography.

b. Starting when the Work commences and continuing for as long as the Work is

01330-13 2026 in progress, not less than 10 photographs, consisting of different subjects or angles of view each time, shall be taken from different locations in the project area at intervals not exceeding one week apart. All photographs shall be furnished to the Engineer within one week after each exposure.

c. The Contractor shall upload photographs to the designated folders in e-Builder.

The file name shall include the date and brief description of the photo. Provide additional information on the photo or as a caption associated with the photo that includes but is not limited to the date and the job title, photograph identification, and direction the camera was facing.

d. Prior to commencing the Work, preconstruction photos shall be taken at the Project site and shall be identified by job title, date, and direction the camera was facing. Four exposures shall be taken at each 100-foot property line interval with one each upstream, downstream, and perpendicular to the property line in both directions. This shall be done to provide a 360-degree view of preconstruction conditions at each interval.

e. Upon completion of the Work, the Contractor shall provide a digital video record of the post-construction conditions showing the conditions of roadways, ditches, culverts, driveways, buildings, fences, utilities, and other facilities or property which were within 200 yards or were affected by the contractor's operations during the Work. Two copies of the video record post-construction conditions shall be furnished prior to project close-out.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

PART 4 MEASUREMENT AND PAYMENT

1.1 Providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.