This is a Standard Specifications document for Site Conditions issued by the Washington Suburban Sanitary Commission (WSSC) in Maryland for the 2026 construction season. The document establishes general requirements for contractors regarding existing utilities, structures, and facilities at project sites. Key requirements include mandatory notification to Miss Utility 48 hours in advance of work near existing utility structures, verification of utility locations through test pits or other means before construction begins, and protection of all existing utilities and structures throughout the project. Contractors must support and protect utility structures shown on drawings and those not shown at no additional cost to WSSC. The specification requires contractors to immediately notify the utility owner and engineer upon discovery of previously unknown underground utilities and to coordinate with utilities regarding any requested adjustments to public utility structures. Contractors must also permit free access to existing utility structures for inspection, maintenance, and new utility construction by utility owners and operators at all times.
The document further specifies that contractors are responsible for locating, protecting, and maintaining or removing and restoring existing improvements, structures, and facilities within and adjacent to the construction area, including trees, shrubberies, property survey monuments, fences, curbs, gutters, walkways, driveways, and flagstone. Damage to any existing structures must be repaired and restored to original condition at no additional cost to WSSC. Any costs resulting from damage to incorrectly marked utilities are the responsibility of the utility owner, not WSSC. The specification clarifies that all costs and time extensions incurred due to lack of coordination with utilities or from contractor-arranged relocations are at no additional cost to WSSC. Notably, providing for and complying with requirements outlined in this section will not be measured for payment but will be considered incidental to the overall contract cost.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01150-1 2026
STANDARD SPECIFICATIONS
SECTION 01150
SITE CONDITIONS
GENERAL
DESCRIPTION
Section includes general requirements relating to site conditions and responsibility for existing utilities, structures, and facilities.
EXISTING UTILITIES
General.
Existing utility structures and appurtenances are shown following best available information.
The Commission will not be responsible for completeness or accuracy thereof nor for any deductions, interpretations, or conclusions drawn there from.
Notify Miss Utility 48 hours in advance of work in vicinity of existing utility structures and appurtenances and verify by test pit or other means actual locations of existing utility structures and appurtenances before construction in their vicinity.
Support and protect utility structures and appurtenances following Drawings and Owner's requirements and take other steps necessary to protect structures from disturbance or damage.
Support and protect utility structures and appurtenances known, but not shown on Drawings, which occupy same space as facility to be constructed at no additional cost to the Commission.
Notify Utility Owner and Engineer immediately when previously unknown or different underground utility structures or appurtenances are encountered, and take necessary precautions to support and protect utility.
Relocations or temporary protection arranged by or for convenience of Contractor will be at no additional cost to the Commission.
Removal or relocation of existing utility structures and appurtenances that physically occupy same space as facility, structure, or pipeline to be constructed are at no cost to Contractor.
Cost will be paid for as set forth in General Conditions, Article 14.
Fulfill requests from public utility corporations, jurisdictional agencies, or other owners to adjust public utility structures and appurtenances within or adjacent to limits of construction.
Furnish copies of requests and replies thereto to Engineer, and coordinate activities with utility.
Additional cost or time extension incurred resulting from lack of coordination with utilities will be at no additional cost to the Commission.
01150-2 2026
Any costs incurred as result of damage to incorrectly marked existing utility structure or appurtenances are to be resolved with Owner of damaged utility and not the responsibility of the Commission.
Repair damage to utility structures or appurtenances shown on Drawings or otherwise known.
Restore damaged utility structures and appurtenances as near as practicable to their original condition to the Engineer's or utilities' approval, at no additional cost to the Commission.
Relocations by Others: Coordinated with construction schedules of others performing relocations of existing utilities to avoid delay in Work.
Access to Utilities: Permit free and clear access to existing utility structures and appurtenances, including Commission sites, by personnel of Utility Owners or Operators, for inspection, maintenance, providing additional service, and construction of new utilities.
Maintain and protect utility structures and appurtenances at all times.
OTHER EXISTING IMPROVEMENTS, STRUCTURES, AND FACILITIES
Locate, protect and maintain, or remove and restore, existing improvements, structures, and facilities within and adjacent to Construction area whether or not shown on drawings, unless Engineer directs otherwise.
Trees and Shrubberies: Protect from damage.
If damaged, replace or repair damage, under Engineer's direction, at no cost to the Commission.
Property Survey Pipes, Stones, and Monuments: Protect and if required, replace using
Professional Surveyor licensed to practice in State of Maryland, at no cost to the Commission.
Fences, Curbs, Gutters, Walkways, Driveways, Driveway Aprons and Flagstone: Remove and replace in original position or at Engineer's direction.
Replace, in kind, those damaged, at no cost to the Commission.
PRODUCTS
NOT USED
EXECUTION
NOT USED
MEASUREMENT AND PAYMENT
01150-3 2026
Except as otherwise noted herein, providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.