01 74 00 Cleaning and Waste Management.pdf
PDF 161 KB Posted
- Attached to
- Vaults 60, 87 & ET Structural Repair and Grating Replacement State and local contract opportunity
- Solicitation number
- 3930
- Issued by
- Knox County, Tennessee
About this file
This document is a technical specification section (Section 01 74 00) for Cleaning and Waste Management related to the Vaults 60, 87 & ET Structural Repair and Grating Replacement project by KUB (Knoxville Utilities Board). The specification outlines comprehensive requirements for maintaining a clean and orderly construction site during project activities. Contractors are mandated to remove waste materials and debris daily, with a mandatory weekly cleaning schedule that includes sweeping floors, entry drives, roadways, and walkways, and restoring all affected areas to their original condition.
The specification establishes strict cleaning protocols with potential financial consequences for non-compliance. If the contractor fails to meet the cleaning requirements, the Owner may withhold payments equivalent to Liquidated Damages, exercise the right to correct defective work, or refuse to make monthly progress payments. The contractor must provide approved waste containers, dispose of materials offsite weekly, and ensure all work areas are left in a condition satisfactory to the Owner. Weekly inspections will be conducted, with the contractor required to notify the Owner every Thursday about work areas that have been active during the week.
View the file
Other files for this state and local contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vaults 60, 87 & ET Structural Repair and Grating Replacement
3930 CLEANING AND WASTE MANAGMENT
REVISED 07/24/24 01 74 00 - 1
SECTION 01 74 00
CLEANING AND WASTE MANAGMENT
PART 1 – GENERAL
1.01 SUMMARY
A. Section Includes: Requirements for maintaining Site in clean and neat condition during construction.
B. Related Requirements:
1. Document 00 72 13, General Conditions – Construction Contract.
2. Document 00 73 13, Supplementary Conditions – Construction Contract.
3. Section 01 77 00, Closeout Procedures.
1.02 GENERAL
A. Contractor shall not unreasonably encumber the Work area with construction equipment or materials.
Work area shall be kept clean during construction activities and promptly restored to original condition after moving to next Work area.
1.03 SCHEDULING
A. Daily: Remove and dispose of waste materials, rubbish, and other debris.
B. Weekly: Each Friday, at the latest, remove and dispose of debris generated by construction activities and construction personnel, restore areas to original condition (such as, lawns, beds, sidewalks, driveways, and streets) with temporary or permanent surfaces as specified in these Specifications.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.01 CLEANING
A. In accordance with General Conditions, as may be specified in other specification sections, and as required herein.
B. Wet down exterior surfaces prior to sweeping to prevent blowing of dust and debris. At least weekly, sweep floors (including, basins, tunnels, platforms, walkways, and roof surfaces), and pick up and dispose of debris.
C. Weekly, brush sweep entry drive, roadways, and other streets and walkways affected by the Work and where adjacent to the Work.
Vaults 60, 87 & ET Structural Repair and Grating Replacement
CLEANING AND WASTE MANAGMENT 3930
01 74 00 - 2 REVISED 07/24/24
D. Provide approved containers for collection and disposal of waste materials, debris, and rubbish. Weekly, dispose of such waste materials, debris, and rubbish offsite.
E. Leave the Work and adjacent areas affected in a cleaned condition satisfactory to Owner.
1. Remove and dispose of debris generated by construction activities and construction personnel.
2. Repair and patch adjacent surfaces to original condition.
3. Clean sidewalks, driveways, and other areas to original or better condition.
4. Rake clean all other surfaces.
5. Leave water courses, gutters, and ditches open and clean.
3.02 INSPECTION
A. Contractor shall notify Owner on a weekly basis, on Thursday, of Work areas that construction crews have worked on during the week.
B. The Owner, with the Contractor, will make an inspection to verify the status of completion.
C. Owner will notify Contractor in writing when surface conditions do not meet the Contract Documents.
3.03 EVALUATION
A. Failure to perform, as determined by the Owner may result in all or one of the following:
1. Withholding payments in an amount equal to Liquidated Damages on a daily basis as designated in the Agreement for each day surface conditions do not meet requirements of the Contract Documents.
2. Owner exercising right to correct defective Work in accordance with the General Conditions.
3. Refusal of Owner to make monthly progress payments as requested by the Contractor.
3.04 FINAL CLEANING
A. In accordance with Section 01 77 00, Closeout Procedures.
END OF SECTION
| 1 PART 1 – GENERAL |
| 1.01 SUMMARY |
| A. Section Includes: Requirements for maintaining Site in clean and neat condition during construction. |
| B. Related Requirements: |
| 1. Document 00 72 13, General Conditions – Construction Contract. |
| 2. Document 00 73 13, Supplementary Conditions – Construction Contract. |
| 3. Section 01 77 00, Closeout Procedures. |
| 1.02 general |
| A. Contractor shall not unreasonably encumber the Work area with construction equipment or materials. Work area shall be kept clean during construction activities and promptly restored to original condition after moving to next Work area. |
| 1.03 SCHEDULING |
| A. Daily: Remove and dispose of waste materials, rubbish, and other debris. |
| B. Weekly: Each Friday, at the latest, remove and dispose of debris generated by construction activities and construction personnel, restore areas to original condition (such as, lawns, beds, sidewalks, driveways, and streets) with temporary or perman... |
| 2 PART 2 - PRODUCTS (Not Used) |
| 3 PART 3 - EXECUTION |
| 3.01 CLEANING |
| A. In accordance with General Conditions, as may be specified in other specification sections, and as required herein. |
| B. Wet down exterior surfaces prior to sweeping to prevent blowing of dust and debris. At least weekly, sweep floors (including, basins, tunnels, platforms, walkways, and roof surfaces), and pick up and dispose of debris. |
| C. Weekly, brush sweep entry drive, roadways, and other streets and walkways affected by the Work and where adjacent to the Work. |
| D. Provide approved containers for collection and disposal of waste materials, debris, and rubbish. Weekly, dispose of such waste materials, debris, and rubbish offsite. |
| E. Leave the Work and adjacent areas affected in a cleaned condition satisfactory to Owner. |
| 1. Remove and dispose of debris generated by construction activities and construction personnel. |
| 2. Repair and patch adjacent surfaces to original condition. |
| 3. Clean sidewalks, driveways, and other areas to original or better condition. |
| 4. Rake clean all other surfaces. |
| 5. Leave water courses, gutters, and ditches open and clean. |
| 3.02 INSPECTION |
| A. Contractor shall notify Owner on a weekly basis, on Thursday, of Work areas that construction crews have worked on during the week. |
| B. The Owner, with the Contractor, will make an inspection to verify the status of completion. |
| C. Owner will notify Contractor in writing when surface conditions do not meet the Contract Documents. |
| 3.03 EVALUATION |
| A. Failure to perform, as determined by the Owner may result in all or one of the following: |
| 1. Withholding payments in an amount equal to Liquidated Damages on a daily basis as designated in the Agreement for each day surface conditions do not meet requirements of the Contract Documents. |
| 2. Owner exercising right to correct defective Work in accordance with the General Conditions. |
| 3. Refusal of Owner to make monthly progress payments as requested by the Contractor. |
| 3.04 final cleaning |
| A. In accordance with Section 01 77 00, Closeout Procedures. |
File details come from the government source that posted it. Updated .