00 52 13 Agreement - Construction Contract.pdf

PDF 232 KB Posted

Attached to
Vaults 60, 87 & ET Structural Repair and Grating Replacement State and local contract opportunity
Solicitation number
3930
Issued by
Knox County, Tennessee

About this file

This document is a Construction Contract Agreement between the Knoxville Utilities Board (KUB), a municipal utility, and an unspecified contractor for the Vaults 60, 87 & ET Structural Repair and Grating Replacement project. The project involves structural repairs and grating replacement, with a defined timeline for substantial completion by March 6, 2026, and final completion by April 5, 2026. The engineering design for the project will be handled by Aptim Environmental & Infrastructure, LLC. The contract emphasizes time-sensitive performance, with specific liquidated damages provisions of $500 per day for delays in substantial completion and $250 per day for delays in final completion.

The contract does not specify the total contract price, as the document shows a placeholder "[number]" for the total lump sum. The payment structure includes progress payments made NET 30 days, with 95% of completed work value being paid during the project and the remaining 5% held as retainage. The contract allows for unit price work, with actual quantities to be determined by the engineer. Funding for the project will be solely from the revenues of the Electric Division of the Knoxville Utilities Board. The contract includes provisions for potential additional costs related to delays, such as engineering and administrative services, and requires compliance with Title VI of the Civil Rights Act of 1964.

View the file

Other files for this state and local contract opportunity

Other files attached to Vaults 60, 87 & ET Structural Repair and Grating Replacement, newest first.
File Type Posted
00 01 01 Title Page.pdf PDF
01 14 33 Work In Rights-of-Way.pdf PDF
00 01 10 Table of Contents.pdf PDF
00 41 11 Bid Cover Sheet.pdf PDF
00 45 40 Verification of Business Status Minority and Women-Owned Business Certification.pdf PDF
01 14 13 Access to Site.pdf PDF
01 31 13 Project Coordination.pdf PDF
01 41 00 Regulatory Requirements.pdf PDF
00 41 13 Bid Form.pdf PDF
00 43 13 Bid Security Form.pdf PDF
00 45 48 Drug-Free Affidavit.pdf PDF
00 61 13.16 Payment Bond.pdf PDF
00 73 16 Insurance Requirements.pdf PDF
01 35 23 Owner Safety Requirements.pdf PDF
01 45 00 Quality Control.pdf PDF
01 54 23 Temporary Scaffolding and Platforms.pdf PDF
01 55 26 Traffic Control.pdf PDF
01 74 00 Cleaning and Waste Management.pdf PDF
01 77 00 Closeout Procedures.pdf PDF
01 78 23 Operation and Maintenance Data.pdf PDF
Drawings - Vaults 60, 87 & ET Structural Repair and Grating Replacement.pdf PDF
00 01 15 List of Drawing Sheets.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 45 13 Bidders Qualifications.pdf PDF
00 45 19 Non-Collusion Affidavit.pdf PDF
00 61 13.13 Performance Bond.pdf PDF
00 72 13 General Conditions - Construction Contract.pdf PDF
00 73 13 Supplementary Conditions - Construction Contract.pdf PDF
01 11 00 Summary of Work.pdf PDF
01 26 00 Contract Modification Procedures.pdf PDF
01 29 00 Payment Procedures.pdf PDF
01 57 13 Temporary Erosion and Sediment Control.pdf PDF
01 60 00 Common Product Requirements.pdf PDF
Appendix A - Structural Design Calculations.pdf PDF
Bid Invitation - 3930.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vaults 60, 87 & ET Structural Repair and Grating Replacement

3930 AGREEMENT – CONSTRUCTION CONTRACT

REVISED 05/02/25 00 52 13 - 1

DOCUMENT 00 52 13

AGREEMENT – CONSTRUCTION CONTRACT

This Agreement is by and between Knoxville Utilities Board, a municipal utility created by charter of the City of Knoxville, Tennessee, a municipal corporation (“Owner”) and [name of contracting entity] (“Contractor”).

Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary Conditions.

Owner and Contractor hereby agree as follows:

ARTICLE 1—WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: Vaults 60, 87 & ET Structural Repair and Grating Replacement.

ARTICLE 2—THE PROJECT

2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows:

Vaults 60, 87 & ET Structural Repair and Grating Replacement.

ARTICLE 3—ENGINEER

3.01 The part of the Project that pertains to the Work has been designed by Aptim Environmental & Infrastructure, LLC .

ARTICLE 4—CONTRACT TIMES

4.01 Time is of the Essence:

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.02 Contract Times: Dates.

A. The Work will be substantially complete on or before March 6, 2026, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before April 5, 2026.

4.03 Liquidated Damages:

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal or arbitration proceeding, the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $500.00 for each day that expires after the time

(as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.

AGREEMENT – CONSTRUCTION CONTRACT 3930

00 52 13 - 2 REVISED 05/02/25

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $250.00 for each day that expires after such time until the Work is completed and ready for final payment.

3. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.

B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, excess, or consequential, for such delay, except for special damages (if any) specified in this Agreement.

4.04 Special Damages:

A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain any Milestones and Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete.

B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment.

C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement.

ARTICLE 5—CONTRACT PRICE

5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:

A. Total lump sum of $[number].

B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item). The listing of all Unit Price Work is provided in Document 00 43 22, Unit Prices Form included as Exhibit A to this Document.

The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.

REVISED 05/02/25 00 52 13 - 3

ARTICLE 6—PAYMENT PROCEDURES

6.01 Submittal and Processing of Payments:

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions.

Applications for Payment will be processed by Engineer as provided in the General Conditions.

6.02 Progress Payments; Retainage:

A. Owner shall make progress payments NET 30 days from the date of receipt and approval of the Contractor’s Applications for Payment during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.

a. 95 percent of the value of the Work completed (with the balance being retainage).

b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 100 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

6.03 Final Payment:

A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.

6.04 Consent of Surety:

A. Owner will not make final payment or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.

6.05 Obligation of Funds:

A. The obligations of the Owner hereunder are payable solely from the revenues of the Electric Division(s) of the Knoxville Utilities Board.

ARTICLE 7—CONTRACT DOCUMENTS

7.01 Contents:

A. The Contract Documents consist of all documents and sections listed on the Table of Contents, which may include but is not limited to the following:

1. This Agreement.

00 52 13 - 4 REVISED 05/02/25

2. Bidding Requirements

3. Bonds and Insurance:

4. General Conditions.

5. Supplementary Conditions.

6. Technical Specifications.

7. Drawings listed on the attached sheet index.

8. Addenda if any.

9. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:

a. Notice to Proceed.

b. Work Change Directives.

c. Change Orders.

d. Field Orders.

e. Warranty Bond, if any.

B. There are no Contract Documents other than those listed above in this Article 7.

C. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.

ARTICLE 8—REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS

8.01 Contractor’s Representations:

A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:

1. Contractor has examined and carefully studied the Contract Documents, including Addenda.

2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and

(c) Contractor’s safety precautions and programs.

REVISED 05/02/25 00 52 13 - 5

7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.

12. The Contractor agrees that it will comply with Title VI of the Civil Rights Act of 1964 and all requirements imposed by Owner to the effect that no person shall, on the grounds of race, color, or national origin, be excluded from participating in, or denied the benefits of, or be subject to discrimination under any program or activities for which Owner received Federal Financial Assistance. The Contractor agrees to compile appropriate data, maintain records, and submit reports as required to permit effective enforcement of Title VI. If there are any violations of this assurance, Owner shall have the right to recommend corrective actions or to seek administrative enforcement of this assurance.

8.02 Contractor’s Certifications:

A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and,

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

8.03 Standard General Conditions:

A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018) (Document 00 72 13), published by the Engineers Joint Contract Documents Committee, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published

00 52 13 - 6 REVISED 05/02/25

document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions (Document 00 73 13).

REVISED 05/02/25 00 52 13 - 7

IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.

This Agreement will be effective on [indicate date on which Contract becomes effective] (which is the Effective Date of the Contract).

Owner: Contractor:

Knoxville Utilities Board

(typed or printed name of organization) (typed or printed name of organization) By: By:

(individual’s signature) (individual’s signature) Date: Date:

(date signed) (date signed) Name: Brian Day Name:

(typed or printed) (typed or printed) Title: Procurement Manager Title:

(typed or printed) (typed or printed) (If [Type of Entity] is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: Attest:

(individual’s signature) (individual’s signature) Title: Title:

(typed or printed) (typed or printed) Address for giving notices: Address for giving notices:

4505 Middlebrook Pike Knoxville, TN 37921

END OF DOCUMENT

Article 1— WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: Vaults 60, 87 & ET Structural Repair and Grating Replacement.
Article 2— THE PROJECT
2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: Vaults 60, 87 & ET Structural Repair and Grating Replacement.
Article 3— ENGINEER
3.01 The part of the Project that pertains to the Work has been designed by Aptim Environmental & Infrastructure, LLC .
Article 4— CONTRACT TIMES
4.01 Time is of the Essence:
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Contract Times: Dates.
A. The Work will be substantially complete on or before March 6, 2026, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before April 5, 2026.
4.03 Liquidated Damages:
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified....
1. Substantial Completion: Contractor shall pay Owner $500.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final pay...
3. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.

B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, exces...

4.04 Special Damages:
A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain any Milestones and Substantial Completion according to the Contract Times, and (2) for the actual costs reason...
B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineer...
C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement.
Article 5— CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:
A. Total lump sum of $[number].
B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item). The listing of all Unit Price Wor...
The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actu...
Article 6— PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments:
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage:
A. Owner shall make progress payments NET 30 days from the date of receipt and approval of the Contractor’s Applications for Payment during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment ha...
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not li...
a. 95 percent of the value of the Work completed (with the balance being retainage).
b. 95 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 10...

6.03 Final Payment:
A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.
6.04 Consent of Surety:
A. Owner will not make final payment or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.
6.05 Obligation of Funds:
A. The obligations of the Owner hereunder are payable solely from the revenues of the Electric Division(s) of the Knoxville Utilities Board.
Article 7— CONTRACT DOCUMENTS
7.01 Contents:
A. The Contract Documents consist of all documents and sections listed on the Table of Contents, which may include but is not limited to the following:
1. This Agreement.
2. Bidding Requirements
3. Bonds and Insurance:
4. General Conditions.
5. Supplementary Conditions.
6. Technical Specifications.
7. Drawings listed on the attached sheet index.
8. Addenda if any.
9. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:
a. Notice to Proceed.
b. Work Change Directives.
c. Change Orders.
d. Field Orders.
e. Warranty Bond, if any.
B. There are no Contract Documents other than those listed above in this Article 7.
C. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.
Article 8— REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS
8.01 Contractor’s Representations:
A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:
1. Contractor has examined and carefully studied the Contract Documents, including Addenda.
2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been iden...
5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports a...
6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and t...
7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Pr...
8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written ...
10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.
12. The Contractor agrees that it will comply with Title VI of the Civil Rights Act of 1964 and all requirements imposed by Owner to the effect that no person shall, on the grounds of race, color, or national origin, be excluded from participating in,...
8.02 Contractor’s Certifications:
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.02:
1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels...
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and,
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
8.03 Standard General Conditions:
A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018) (Document 00 72 13), published by the Engineers Joint Contract Documents Commit...