About this file

This is a Schedule of Unit Prices for the City of Umatilla, Florida's N/S Golden Gem Utility Improvements project. The project encompasses construction of new water lines, new sewer lines, pavement reconstruction, and general restoration along North/South Golden Gem Drive from Cayman Circle to East/West Golden Gem Drive. The scope of work includes 36 line items organized into four categories: general construction (mobilization, permits, surveys, testing, traffic maintenance, demolition, and sodding), roadway improvements (asphalt and base course installation), water infrastructure (10" and 12" PVC/HDPE water mains, gate valves, tees, reducers, wet taps, and pressure testing), and sewer infrastructure (6" PVC force main, plug valves, tees, flushing ports, and pressure testing). A mandatory pre-bid conference was held on January 16, 2025, with sealed bids due February 13, 2025, at 2:00 p.m. The City Council will review bids on March 4, 2025, approve the contract on March 18, 2025, and issue a Notice to Proceed prior to March 31, 2025.

Unit prices submitted by bidders shall represent the exact net amount per unit with no additional adjustments permitted for overhead, profit, insurance, or indirect expenses. Bidders must perform all necessary calculations and tests to determine required quantities, with the understanding that any authorized changes to quantities will be based on these unit prices. A 110% Payment & Performance Bond is required, and contractors must comply with the General Wage Decision (GWD FL20250119 HEAVY 01.03.25) for applicable labor rates. The project is locally funded with approximately $900,000 in grant funding available, though the total contract sum will be determined through the bidding process. Bidders must submit two physical copies and one digital copy of their bid and demonstrate technical qualifications including AWWA standards compliance, directional drilling capabilities, and adherence to utility installation specifications. The City reserves the right to waive informalities, reject any or all bids, and select the bid most favorable to the City's interests, with subcontractors requiring comprehensive listing on the Section 00301-A form.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item # Description Quantity Unit Unit Price Amount

GENERAL

1 Mobilization LS 2 NPDES Permit & Compliance LS 3 Construction Layout Survey LS 4 As-built Survey LS 5 Testing LS 6 Maintenance of Traffic LS 7 Silt Fence LF 8 Demo Asphalt & Driveway LS 9 Sod SY 10 Concrete Driveway SY

SUB-TOTAL

ROADWAY

11 2" SP 9.5 Asphalt SY 12 8" Limerock SY 13 12" Stabilized Subgrade SY 14 Thermo Stop Bar LS

SUB-TOTAL

WATER

15 10" PVC Watermain LF

16 10" DIP LF

17 12" HDPE Directional Bore LF 18 10" PVC to 12" HDPE Transition EA 19 Temporary Jumper EA 20 10" Gate Valve EA 21 10" 45° Bend EA 22 10" x 10" Tee EA 23 8" Wet Tap w/ Tapping Sleeve & Valve EA

24 12" x 10" Wet Tap w/ Tapping Sleeve & Valve EA

25 8" x 10" Reducer EA 26 8" Gate Valve EA 27 Thrust Restraints EA 28 Bactees LS 29 Pressure Test LS

SUB-TOTAL

3. The Unit Prices shall represent the exact net amount per unit to be paid by the Contractor (in the case of additions or increases) or to be refunded by the Owner (in the case of decrease). No additional adjustments will be allowed for overhead, profit, insurance, or to other direct or indirect expenses of the Contractor or Subcontractors, and no additional adjustments will be allowed.

City of Umatilla N/S Golden Gem Utility Improvements

Schedule of Unit Prices

1. It shall be the responsibility of the BIDDER to perform whatever tests and/or calculations as are necessary to determine quantities required for the performance of the work described herein.

2. Should certain additional work be required, or should the quantities submitted by the Contractor of certain classes of work be increased or decreased from those required by the Contract Documents, by authorization of the Owner, the unit prices contained in the following Schedule of Unit Prices shall, at the option of the Owner, be the basis of payment to the Contractor credit to the Owner, for such increase or decrease in the work.

SEWER

30 6" PVC Force Main LF

31 Tie Into Existing 6" Force Main (Requires City Coordination) LS

32 6" Plug Valve EA 33 6" x 6" Tee EA 34 6" Flushing Port EA 35 6" Plug EA 36 Thrust Restraints EA 37 Pressure Test LS

Subtotal 110% Payment & Performance Bond Total Price

TOTAL BASE BID PRICE for the contract sum (Sum of items 1-36 and Bond)