This is a Statement of Work (Exhibit 5) issued by the Oregon Department of Transportation (ODOT) for the Enterprise Maintenance Station Roof Replacement Project located at 715 Golf Course Road, Enterprise, Oregon 97828. The project involves the complete replacement of the original 1992 building roof with Insulated Metal Panels (IMPs), including removal and disposal of existing rain gutters, downspouts, gable trim, eave trim, ridge cap, roof metal, and roof insulation. The contractor shall provide all necessary materials, tools, equipment, supervision, permits, and transportation to complete the work. The project specifications call for All Weather Insulated Panels Standing Seam SR2 with 5-inch panel thickness, 40-inch panel width, R41 minimum insulation value, and white Silicone Modified Polyester Two-Coat System paint finish, along with commercial-grade gutters compatible with the IMP roof system. The contractor must schedule work at least ten business days prior to commencement and coordinate all efforts with subcontractors and suppliers. Substantial completion is due no later than August 31, 2026, with final completion by September 30, 2026. The ODOT Project Manager is Shelby Stout, contactable at shelby.stout@odot.oregon.gov or (541) 952-1165.
The statement of work requires contractors to complete a pre-bid site visit to examine existing conditions and submit any discrepancies or clarifications in writing prior to installation. Work shall be performed on weekdays between 7 a.m. and 5 p.m., excluding weekends and state holidays unless approved by the ODOT Project Manager. ODOT has obtained the structural permit; however, the contractor is responsible for all additional required permits and building department inspections. The project is subject to BOLI Prevailing Wage Rates, requiring weekly Certified Payroll Reports from the general contractor and all subcontractors as a prerequisite for progress payment approval. The contractor must provide one-year installation warranty on all workmanship and all applicable equipment warranties. Submittals required prior to construction commencement include Insulated Metal Panel Product Data and Gutter and Downspout Product Data. Final closeout requirements include marked-up record drawings indicating utility locations and changes, digital copies of all operations and maintenance information, equipment details, signed certification that all subcontractors and suppliers have been paid in full, and full instruction of ODOT's operating and maintenance personnel on equipment operation and maintenance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00015915 Intent To Award.xlsx | XLSX spreadsheet | |
| 00015915 Exhibit 6 Plans Revised.pdf | ||
| 00015915 Exhibit 9 2013 As Builts.pdf | ||
| 00015915 Exhibit 6 Plans.pdf | ||
| 00015915 Prebid Meeting Agenda.doc | DOC document | |
| 00015915 Prebid Sign In Sheet.docx | DOCX document | |
| 00015915 Kingspan KingSeam Product Data.pdf | ||
| 00015915 PI Invitation To Bid.docx | DOCX document | |
| 00015915 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00015915 Sample Contract.docx | DOCX document | |
| 00015915 Exhibit 8 1992 As Builts.pdf | ||
| 00015915 Exhibit 7 Photos.docx | DOCX document | |
| 00015915 Addendum1.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 5
STATEMENT OF WORK
1/22/26 Oregon Department of Transportation
Enterprise Maintenance Station Roof Replacement Project Location:
715 Golf Course Road
Enterprise, OR 97828
ODOT Contact:
The ODOT Project Manager for this project is Shelby Stout.
· E-mail: shelby.stout@odot.oregon.gov
· Cell: (541) 952-1165
· Address: 3012 Island Ave
La Grande, OR 97850 The ODOT Project Manager may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Project Background The Enterprise Maintenance Station building footprint is approximately 50’x128’. The original 1992 building is a pre-engineered steel building that currently has blanket insulation draped over purlins and covered with metal roofing. The 2013 wash bay addition is a CMU structure with glulam roof beams and a snap lock standing seam metal roof. See attached as-builts and pictures for additional information.
Project Description
The project shall consist of the replacement of the original 1992 building roof. The 2013 wash bay addition roof is to remain as is.
This includes the removal and disposal of all existing rain gutters, downspouts, gable trim, eve trim, ridge cap, roof metal, and roof insulation. Replace with Insulated Metal Panels, associated trim, and gutters. Contractor shall provide all necessary materials, tools, equipment, supervision, permits, and transportation necessary to complete work.
Current roof penetrations include three actuated louver exhausts, three radiant tube heater exhausts, one vehicle exhaust system vent, one radio antenna, one bathroom vent, and one furnace vent.
Detailed Project Specifications
1. Material list:
· Insulated Metal Panel Roofing
· Basis of design is All Weather Insulated Panels Standing Seam SR2
· 5” panel thickness
· 40” panel width
· Exterior standing seam 26ga or heavier
· Interior metal 26ga or heavier
· R41 minimum
· Concealed fastening per manufacturer’s recommendations
· Exterior and interior panel color to be white, Silicone Modified Polyester Two-Coat System paint finish
· Inside and outside ridge cap, color to be white
· Request for substitutions will be considered
· Commercial Grade Gutters
· Compatible with IMP roof system
· 24ga or heavier
· Color to match existing exterior
· Downspout size and locations shall match existing, square to round adapters into existing 4” drainpipes.
2. Outline of work:
· Remove and dispose of existing metal trim, gutters, downspouts, fiberglass panels, roof metal, and insulation.
· Roof type shall be gable, match existing roof pitch and slope from the center ridge line equally to both sides.
· Provide and install insulated metal panels per manufacturer’s recommendations.
· Use two part closed cell foam insulation to seal void between panels at ridge and around any other penetrations through the roof.
· Provide and install white commercial grade gutters on both eaves with downspouts to pavement. Downspout location shall match exiting PVC drainpipes.
· Provide and install new square to round PVC adapters on existing PVC downspout drainpipes.
· Provide and install zee flashing or straight hemmed flashing behind and/or below new gutter to seal up and cover existing wall panels.
· Provide and install custom white gable trim at the north end of the building.
· Contractor shall ensure gable trim extends down enough to cover gap between the new roof and existing metal siding, as well as cover any existing holes in wall panels.
· Contractor shall ensure wall panels are sealed with outside form fit closure. Use mastic between roof metal and gable trim.
· If face of gable trim exceeds 5”, include stiffener or two separate pieces of trim to reduce oil canning.
· Provide and install custom white side wall flashing at the south end of the building where the new roof will step down approximately 5” to existing wash bay roof.
· Provide and install reverse ridge cap on the interior.
· Provide and install ridge cap system as per manufacturer's recommendations.
· Existing ABS plumbing vent will need to be cut off below the roof deck and a new ABS vent pipe will need to be installed 18” above finish roof.
· Existing GPS antenna white cap and cable will be removed by others prior to start of construction. The 3” galvanized pipe will remain in place. Once contractor installs IMPs and roof jack, ODOT will coordinate with others to re-install GPS components.
· Existing radio antenna and weather head will be removed from the galvanized pole prior to construction. The weather head and antenna pipe will remain in place; contractor is responsible to core drill IMPs and install roof jacks.
· The three roof top exhaust fans are no longer needed. Fans will be disconnected by ODOT electricians, Contractor shall remove and dispose of fans as part of this project.
· The three radiant tube heater exhaust vents will need to be removed and replaced. Contractor is responsible to work with a licensed HVAC contractor to remove existing B-vents and install new vents that extend approximately 24” above finish roof. Contractor is responsible for ensuring vents are mounted plumb, solid, and 100% sealed by properly sized rubber flashing boot.
· The furnace concentric PVC vent is to remain in place. Provide and install new roof jack once IMP and ridge cap are in place.
· Field verify all dimensions prior to ordering material.
· Prepare IMPs onsite; provide extra precautions to ensure IMPs are not damaged during prepping, flying, or setting.
· Verify all materials onsite prior to any demolition.
· Verify weather conditions will hold throughout IMP installation or have plan in place to temporarily dry-in any areas that have been torn off.
General Construction Notes
· The contractor shall make a site visit and examine existing conditions prior to providing a bid. Any discrepancies shall be brought to the attention of ODOT through a request for clarification as set forth in the bid documents.
· Clarifications shall be requested in writing prior to any installation. Incorrect installations shall be corrected at no additional cost to ODOT.
· All work shown is to be by the contractor unless specifically noted as being by ODOT or by others. All materials shown are to be provided by the contractor unless specifically noted as existing or provided by ODOT.
· Drawings are schematic in nature, major components and equipment are shown on the drawings. The contractor shall supply and install all minor components and materials necessary to provide a complete and functional project whether all such components are noted in the drawings and specifications.
· Plans and specifications call out specific make and models of equipment in some locations. Substitution requests shall be made during the bid process. ODOT shall at its sole discretion determine the acceptability of substitutions. No substitutions shall be installed without prior written approval from the ODOT Construction Project Manager.
· All equipment and materials shall be installed in accordance with the manufacturer’s published installation instructions and recommendations.
· Clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
Submittals
The Contractor shall provide the following submittals at a minimum to the ODOT Project Manager. Submittals shall be approved by the ODOT Project Manager prior to the start of on-site construction.
· Insulated Metal Panel Product Data
· Gutter and Downspout Produce Data Scheduling of Contract
· Substantial completion of the Work shall be no later than 8/31/26. Final completion shall be no later than 9/30/26.
· After award of contract, the Contractor shall contact the ODOT Project Manager to schedule the Work at least ten (10) business days prior to the start of any work/demolition.
· The Work shall be accomplished on weekdays between the hours of 7 a.m. and 5 p.m. Work hours shall exclude weekends and State Holidays, unless specifically requested by the Contractor and approved by the ODOT Project Managers.
· ODOT has obtained the structural permit. Contractor will be responsible for contacting the building department for required inspections.
· Any further permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Manager prior to the start of work. The Contractor shall be responsible for posting all permits on site in accordance with local jurisdiction requirements.
· The Contractor shall submit to the ODOT Project Managers a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.
· The Contractor shall coordinate the efforts of all Suppliers and Subcontractors and shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.
Clean-Up/Conditions of Site
· The Contractor shall be responsible for keeping the ODOT Project Manager informed of all activity throughout the Work.
· The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the premises. The Contractor shall broom-clean their work area at the end of each workday and neatly stack materials and debris in an approved location. The contractor shall clean the entire work area at the conclusion of the project to the satisfaction of the ODOT Project Manager.
· The Contractor shall protect materials subject to damage by temperature or other weather conditions.
· The location for storage of materials, debris, or dumpsters on the Premises shall be approved in advance by the ODOT Project Manager. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.
· The Contractor shall notify the ODOT Project Manager at least two (2) days in advance of any major deliveries.
· Contractor shall immediately notify the ODOT Project Manager of any damage done by the Contractor to the Premises, grounds, or adjacent State properties. Damage done by the Contractor to the Premises or surrounding area shall be repaired to existing conditions as found prior to the commencement of the Work.
· ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Premises.
· It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.
· The Contractor shall immediately bring to the attention of the ODOT Project Manager any conflicts or issues between existing utilities and the Work.
BOLI
· BOLI Prevailing Wage Rates apply to this project. Provide weekly Certified Payroll Reports for General Contractor and all subcontractors as a prerequisite for progress payment approval.
Close Out
· All special inspections must be complete prior to Substantial Completion.
· Inspection of the work by the ODOT Project Manager for establishment of Substantial Completion shall be made within five (5) business days after receipt of the Contractor’s email request. At this time, the ODOT Project Manager and the Contractor shall develop a punch list document for any incomplete or deficient work.
· Prior to Final Completion, the Contractor shall complete all items on the punch list.
· The Contractor shall provide final inspection reports for all permits applicable to this Contract signed by authorities having jurisdiction
· The Contractor shall maintain one set of the approved drawings for recording as-built conditions. Mark (in red) the actual location of all underground utilities and any changes. At the time of Final Completion, the Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Manager.
· Prior to Final Completion, the Contractor shall provide one (1) digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Manager.
· Prior to Final Completion, provide ODOT Project Manager with information for all equipment provided by the project, including but not limited to: Manufacturer, model, serial number, consumables, installation date, purchase date.
· Prior to Final Completion, and as prerequisite for final payment, provide ODOT Project Manager with signed certification that all subcontractors and suppliers have been paid in full and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.
· Prior to Final Completion, the Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems.
· Inspection of the work by the ODOT Project Manager for establishment of Final Completion shall be made within five (5) business days after receipt of the Contractor’s email request.
Warranty
· Contractor shall provide a one-year Installation warranty on all workmanship.
· Contractor shall provide all warranties for equipment applicable to this Contract.