00012859 Preliminary Bid Results.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- S-73000-00012859
- Issued by
- Crook County, Gladstone City, Oregon
About this file
The file "00012859 Preliminary Bid Results.xlsx" appears to be a preliminary bid results spreadsheet for the Oregon Department of Transportation (ODOT) Hunter Creek Maintenance Station Sander Storage Building project. The invitation to bid (ITB) seeks a qualified contractor to construct a new Pre-engineered Metal Building (PEMB) at the Hunter Creek Maintenance Station. The project scope includes erecting the PEMB, installing below-grade utilities, performing utility trenching, conducting site grading, and completing other work as specified in the contract documents.
While the specific details of the preliminary bid results are not visible in the provided information, the contract opportunity indicates that ODOT will provide the pre-engineered metal building, and the selected contractor will be responsible for its construction and associated site work. The project appears to be a targeted infrastructure improvement for the maintenance station, focusing on creating a dedicated sander storage building to support ODOT's operational needs in the region.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 3/19/25 | |||||
| ITB No. | S-73000-00012859 | BIDDER | ||||
| NAME: | Vitus Construction Inc | Great Western Corp | ||||
| Bid Closing: | March 19, 2025 at 11:30 a.m. | CITY/STATE: | Gold Hill, Oregon | North Bend, Oregon | ||
| Description: | ODOT Hunter Creek Maintenance Station Sander Storage Building | CCB#: | 63643 | 137472 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | BASE BID includes all work, materials, equipment, labor to install foundations, erection of the pre-engineered building, below grade utilities, utility trenching and site grading and all work included in the construction documents NOTE: Base Bid does not include Add Alternate #1. | 1 | LS | $ 87,200.00 | $ 87,200.00 | $ 181,850.00 | $ 181,850.00 |
| TOTAL | $ 87,200.00 | $ 181,850.00 |
ADD ALTERNATE #1 includes: Furnish and install pre-finished metal siding and trim at south and west walls as detailed in the drawings. 1 LS $ 38,800.00 $ 38,800.00 $ 64,500.00 $ 64,500.00