This solicitation seeks a contractor to provide construction services for a gravesite expansion project at Fort McPherson National Cemetery in Maxwell, Nebraska. The Department of Veterans Affairs National Cemetery Administration requires the contractor to perform all site preparation work including demolition and removal of existing structures. The contractor must also complete all construction activities in accordance with the drawings, specifications, and statement of work. The key qualification is experience performing similar work at national cemeteries. The contractor will be evaluated based on technical qualifications and past performance. Proposals are due by May 12, 2023 and the period of performance is 365 calendar days from notice to proceed.

The solicitation is set aside for small businesses. The primary NAICS code is 237110 and PSC code R499. The place of performance is Fort McPherson National Cemetery. The contractor will be responsible for preparing the site, demolishing structures, and expanding the number of gravesites available within the 365-day performance period. The solicitation does not specify an estimated value but the work includes tasks such as excavation, utilities installation, landscaping, and construction of a memorial wall and maintenance yard.

Notice text

4 versions

Update #4 · Latest ·

CONTINUATION PAGE

AMENDMENT 0003

Solicitation Number: 36C78623B0001

Project Description: Gravesite Expansion, Ft McPherson National Cemetery

The following changes are hereby incorporated into the referenced solicitation requirement:

Change the Bid Opening/Due date from May 4, 2023, to May 12, 2023, the IFB bid submission / due time remains unchanged at 3:00 p.m., CST.

Due to interested bidders inquiry and statement that they cannot gain access to the Government s Vendor Portal, Note and be advised that All bids shall be submitted electronically via email to the attention of the Contracting Officer at his/her respective Government s email address.

The following Request for Information (RFI) questions have been submitted to the Contracting Officer regarding this solicitation. The following questions and responses are provided for bidder s information and use.

RFI 1. Is this solicitation a Small Business (SB)Set-aside or a Service-Disabled Veteran Owned Small Business (SDVOSB) Set-aside?

Response: This re-bid solicitation requirement is a Small Business Set-aside, as stated on page 1 of the SF 1442, section 10 This Invitations for Bids (IFB) procurement opportunity is 100% Set-Aside for Small-Business, firms in accordance with FAR 19.502-2, Competition is restricted to Small Business Construction Firms.

RFI 2. Please verify the Vendor Portal access information.

Response: The Microsoft Teams call-in information is as follows:

Join on your computer or mobile app

Call in (audio only)

+1 872-701-0185, Phone Conference ID: 153 995 408#

or

Click here to join the meeting

Meeting ID: 281 625 574 862 / Passcode: 9Le78q

Download Teams | Join on the web

RFI 3. The criteria that is provided in the specifications appears to be a loessial silt and/or sandy material, that may not stand up well during excavation and does not seem to make sense given the application.

A. Fills: Materials approved from onsite and off-site sources.

Response: The NCA has No objections to an Alternate fill criteria conditional upon bidder's and awarded Contractor s testing laboratory service provides certification that the material is suitable for the intended purpose except for compaction standards. Recommend compaction to minimum 95% of maximum density per ASTM D698 as required in specification 31 20 11 Paragraph 3.3.D.

RFI 4. Dry Density: 1760 kg/m3 (110 pcf) minimum. 2. Plasticity Index: 6 maximum. Liquid Limit: 30 maximum. Based on the off-site samples retrieved and the onsite boring logs, below would be the fill specification found more fitting for this project.

Response: See RFI Response #1.

RFI 5. Cohesive soil with sufficient plasticity to provide an unconfined compressive strength of at least 1.5 tsf when compacted to spec, but not of an expansive nature.

1. Plasticity Index less than 30%.

2. Liquid Limit less than 45%.

Add additional lines, pages, sheets etc., as necessary

3. Acceptable materials per Unified Classification System ASTM D-2487 CL, ML, CL-ML

4. Compaction: Minimum dry density of 90% Modified Proctor and with a moisture content greater than optimum M.C. minus 1%, to be field verified by density-moisture content testing.

Please advise whether or not the above recommendation would be approved in place of what is currently in the specifications.

Response: See RFI Response #1.

RFI 6. There are two (2) Buy American Act clauses included in specifications, which one is to be used?

Response: The reference Buy American Act found in Section 32 84 00 (1.4.3).

RFI 7. There are no Asphalt Plants within a reasonable proximity to Fort McPherson National Cemetery; there are a couple of Ready-mix Concrete Plants nearby.

Will the Government consider it to be acceptable to replace the proposed asphalt paving with concrete?

If so, please provide Detail for the concrete paving.

Response: See attached Concrete Pavement Detail, drawing DT501R.

RFI 8. RE - DT502.

BITUMINOUS TACK COAT, 0.04 GAL./SY is available but should read 0.4 GA./SY

BITUMINOUS PRIME COAT, 0.04 GAL./SY is available but should be 0.15 GAL./SY

Please advise.

Response: For Asphaltic Material Application Rates:

The rate of application for bituminous tack coat shall be adequate to bond the new bituminous layer to the existing surface. This shall be from 0.05 to 0.10 Gal/SY when applied to the freshly laid asphaltic concrete.  (Per NDOT Spec 504)

The rate of application for bituminous prime coat shall be a uniform rate of 0.30 Gal/SY. (Per NDOT Spec 517)

RFI 9. Mix specified (PG 58V-34) is not available in this area.

PG64-22 is the standard.

This mix design comes out of the North Platte Plant (Croell).

Please advise if this would be acceptable.

Response: PG 58V-34 (per AASHTO M332) is the binder grade indicated in the Nebraska DOT Design Manual for use in hot mix asphalt throughout the state. Locally available binder with closest performance standard to PG58V-34 shall be provided for review and approval during the project submittal process for use in project asphalt mix.

END OF AMENDMENT 0003

Update #3 ·

CONTINUATION PAGE

AMENDMENT 0002

Solicitation Number: 36C78623B0001

Project Description: Gravesite Expansion, Ft McPherson National Cemetery

END OF AMENDMENT 0002

Update #2 ·

CONTINUATION PAGE

AMENDMENT 0001

Solicitation Number: 36C78623B0001

Project Description: Gravesite Expansion, Ft McPherson National Cemetery

The following Request for Information (RFI) questions have been submitted to the Contracting Officer regarding this solicitation. The questions and responses represent all questions submitted to the Contracting Officer prior to the deadline established in the Solicitation. The following questions and responses are provided for bidder s information and use.

RFI 1. Is the NCA willing to share CAD files with interested bidders, needed to determine excavation and fill quantities?

Response: No, CAD files will be supplied to the successful bidder, after award of the contract.

RFI 2. If the CAD files are not available or shareable, can the NCA provide estimates for excavation and fill quantities for bidding purposes?

Response: No, Prospective bidders are responsible for their own material takeoffs.

RFI 3. Have the plans been run through the State of Nebraska Department of Environment and Energy?

Response: No. NPDES permit will need to be processed.

RFI 4. Has Lincoln County and the State of Nebraska Department of Transportation been consulted regarding the drainage plans and road access?

Response: Lincoln County and NDOT were not part of the plan review.

RFI 5. Would the Government deem it acceptable to replace the proposed asphalt paving with concrete paving; considering that all existing roads are concreate paved?

Response: No, it would not be acceptable to change the specification requirements.

END OF AMENDMENT 0001

Update #1 ·

A.5 STATEMENT OF WORK

Contractor shall provide all Management, Supervision, Labor, Equipment, Materials, Parts, Tools, etc., required and necessary to completely prepare the site for building operations, including demolition and removal of existing structures, and perform and complete all work for Gravesite Expansion at Fort McPherson National Cemetery, Maxwell, Nebraska, as required by the attached and associated drawings and specification.

All work must be done strictly according to the contract requirements in accordance with the attached Drawings and Specifications:

SITE INVESTIGATION INSPECTION

Per FAR 52.236-3, Contractor should survey / inspect the site prior to submitting a bid in order to be fully aware of the scope of services required and to adequately gather existing unit s product information, model numbers and all necessary and matching standards and requirements. Failure to do so shall not relieve the successful offeror from performing in accordance with the strict intent and meaning of the specifications without additional cost to the Government.

Contractor shall perform a Site Investigation to verify and assess all dimensions/measurements and site conditions before start of the work and the ordering of any equipment, parts and or materials. Failure to do so shall not relieve the successful offeror from performing in accordance with the strict intent and meaning of the specifications without additional cost to the Government. The Contractor shall submit an After Inspection Report of Contractor s findings, listing any deficiencies found and recommended repair/work solutions to the PM and Contracting Officer for review and approval prior to commencing the work.

The Contractor must acquire the Department of Veterans Affairs (VA), National Cemetery Administration (NCA) Lead Project Manager & Technical Engineer in Charge (PM)s approval once materials has been approved to start the work.

All work shall be performed in a professional workmanship like manner, adhere to NCA standards, be done in strict accordance with the requirements set forth herein, manufacturer s requirements, installation guidelines; and be in accordance with applicable Federal, State and Local codes and regulations; inclusive of applicable OSHA Construction Safety Guidelines. All electrical work shall be in accordance with the latest edition of the National Electrical Code (NEC) and local building codes. Failure to do so shall not relieve the Contractor from performing in accordance with the strict intent and meaning of the specifications without additional cost to the Government.

Upon completion of the work the Contractor s On-site Superintendent, along with the PM, shall inspect the completed work for satisfactory acceptability prior to Contractor de-mobilizing from the site.

PERIOD OF PERFORMANCE

The Contractor shall complete all work including submittals, reviews, quality control, construction services, punch list corrections, clean up, invoicing and closeouts documentation submittal within three hundred sixty-five (365) calendar days from issuance of the Government s Notice Award Notification letter.

The Contractor shall develop and provide the Contracting Officer with a Project Schedule and Cost Schedule within ten (10) calendar days of Government issuance of the Notice to Proceed.

WORK HOURS

Normal construction services work hours for this project shall be 7:30 a.m. to 4:00 p.m., Monday through Friday, excluding Saturday, Sunday and Federal Holidays. Contractor work hours may be modified only by written approval of the Contracting Officer, at no additional cost to the Government.

The Contractor may request authorization in advance from the Contracting Officer to work outside of normal service hours at no additional cost to the Government. Written Authorization must be pre-approved in advance and prior to working and is at the sole discretion of the Contracting Officer.

Contractor, Contractor s employees and sub-contractors must check-in with the PM, daily, upon arrival at the Fort McPherson National Cemetery prior to beginning any work and prior to departing the facility/property after the day s work is completed.

HOLIDAYS

The following federal holidays are observed:

New Year's Day - January 1

Inauguration Day (DC Metropolitan Area Only) - January 20 every 4 years

Martin Luther King's Birthday - 3rd Monday in January

President's Day - 3rd Monday in February

Memorial Day - Last Monday in May

Juneteenth- June 19

Independence Day - July 4

Labor Day - 1st Monday in September

Columbus Day - 2nd Monday in October

Veterans Day - November 11

Thanksgiving Day - 4th Thursday in November

Christmas Day - December 25

And any other holiday proclaimed by the President as a Federal Holiday. When a holiday falls on a Sunday, the following Monday will be observed as a legal holiday. When a holiday falls on a Saturday, the preceding Friday shall be observed as a holiday.

CONTRACTOR QUALITY CONTROL

The Contractor s Site Superintendent will:

be on site, at all times, whenever work is being performed by Contractor or subcontractors employees, to ensure adequately supervision and communication;

review and approve submittals;

inspect the quality of work performed; and

certify the completed work for payment and other purposes.

Note that there may be infrequent stoppages in work at the order of the PM due to burial services being conducted in the area. Contractor will meet with PM at the start of each workday to ensure that no construction activities will interfere with burials on that specific day.

CONTRACTOR'S RESPONSIBILITIES

The Contractor will be responsible for ensuring that all work is done in a manner that safeguards NCA visitors, employees, and the public. Contractor shall obtain all necessary licenses and/or permits required to perform this work. Contractor shall take all precautions necessary to protect persons and property from injury or damage during the performance of this contract. Contractor shall be responsible for any injury to himself/herself, his/her employees, or others, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by him/her or his/her employees' fault or negligence. Contractor shall maintain personal liability and property damage insurance prescribed by the laws of the State of Nebraska.

NATIONAL CEMETERY ADMINISTRATION DIGNITY STANDARDS

Every action by contractor personnel at a National Cemetery must be performed with the special care, reverence, dignity, and respect that acknowledge the cemetery as the final resting place that commemorates the service and sacrifice those service members, Veterans, and their families made for our Nation. Critically important is the awareness, required of the contractor employees, of the remains buried in the grounds where the work is performed. The utmost care must be given to these remains and the headstones and flat grave markers that mark those gravesites and memorialize the service of individuals.

Contractors cannot walk, stand, lean, sit or jump on headstones or markers. Nor can they drive over them. Contractor personnel should use tools approved by the PM, such as shovels, pry bars or pinch bars to lift flat markers out of the ground; pickaxes are not an acceptable tool.

No tools, equipment or other items will be placed or leaned on headstones or markers. Once headstones/markers are removed from the socket, do not place on dirt piles or mud; they should be carefully placed on each associated gravesite and protected in such a way as to prevent any soiling and be out of the way of any other work.

Headstones shall be removed from their sockets using wooden and/or metal clamps. If metal clamps are used, the area that contacts the headstone must be protected with a rigid fabric that will prevent damage to and marking of the headstone. Clamps may be attached to a skid steer loader (i.e., Bobcat®) or similar machine to extract the headstone from the socket. When headstones are removed from their sockets, they shall be carefully stored on each associated gravesite; do not lean headstones against each other. Use care not to scratch or damage headstones in any manner. The headstones shall be laid with front inscription side up while the headstone is lying horizontally on the ground. The headstone shall be protected from direct ground contact while lying horizontally. The protection method shall be as approved by the PM and shall be free of deterioration in weather. An approved method is to support each headstone with two wood 4X4 s. Alternate methods can be approved. Cardboard shall not be used.

Wood or other suitable appropriate and attractive material shall be used to keep the headstones from contact with the soil while lying horizontally during the construction period. This also shows respect towards the families visiting the gravesites and the remains that are buried.

Contractor shall be responsible for replacing damaged headstones and markers and for restoring turf damaged during performance of this work.

Additionally, should any activity result in the exposure and/or damage to any remains, container for remains (i.e., casket or urn), or outer burial container, the Contractor must contact the PM, Director/Assistant Director, and Contracting Officer (CO) for guidance.

Any doubts as to proper procedures shall be brought to the attention of the PM, Director/Assistant Director, and CO for guidance or resolution.

The Contractor is required to discuss the guidance with their employees and have each employee sign a statement of compliance and deliver the signed statement to the PM before work may begin.

STANDARDS OF EMPLOYEE CONDUCT

The National Cemetery Administration (NCA) are national shrines that honors Veterans with a final resting place and lasting memorials that commemorate their service to our Nation. The standards of work, appearance, and procedures performed by Contractors at National Cemeteries shall reflect this nation s concern for those interred there. Due to the sensitive mission of the cemetery, Contractor s personnel must exercise and exhibit absolute decorum, composure, and stability at all times.

As the work being performed is at a National Cemetery all Contractor s employee must always look professional and neat in appearance; and be fully clothed to include upper garment to cover the body from the waist to neck and long pants or slacks. The Contractor shall require its employees, including subcontractors, to wear distinctive visible identification at all times for easy identification while on NCA premises. Contractor and Contractor s personnel (including subcontractor and their employees) shall be required to adhere to the standards of dress and conduct while performing work on the National Cemetery. These standards and regulations are enforceable under Title 38, U.S.C. Section 218.

Contractor s personnel shall:

be fully clothed at all times, to include long slacks or pants and shirt, buttoned up from neck to waist. Clothing will be clean each day. Any soiled clothing should be Cemetery work-related that day. Tank tops as outer garments are prohibited. Tee-shirts will have the company logo visibly displayed. Shoes/boots will have no holes or loose soles. Steel-toed shoes shall be required in accordance with OSHA. Contractor employees shall maintain personal hygiene.

not engage in loud or boisterous behavior or use profane or abusive language. Shall show proper reverence during committal service.

not eat or drink beverages except water or non-alcoholic drinks while in work area or in sight of committal service area during a service. Use of intoxicating beverages and/or drugs is strictly prohibited.

not lean, sit or stand on or against headstones, markers, or monuments. No tools, equipment or other items will be placed or leaned on headstones or monuments at any time. Contractor personnel shall not drive over headstones, markers, or monuments.

only smoke in smoking areas, as designated by the PM. All other areas are designated as NO SMOKING.

Contractor shall discuss the guidance in this paragraph with its employees and all subcontractors. Any doubts as to proper procedures shall be brought to the attention of the PM and Contracting Officer for guidance or resolution. Contractor and subcontractor employee shall sign a Statement of Compliance (if applicable); and shall deliver the signed statements to the PM before work may begin or before any new employee is allowed to work on Cemetery grounds.

Contractor shall be responsible for maintaining satisfactory standards of personnel conduct and work performance and shall administer disciplinary action as required. Contractor is expected to remove any employees from the Cemetery for cause, to include, but not limited to, safety violations, other misconduct in performance of duty under these specifications and/or conduct contrary to the best interests of the Government. If the Contractor fails to act in this regard, or the reason for a removal is immediately required to protect the interests of the Government, the PM may direct the removal of an employee from the premises. Contractor s objections to any such action will be referred to the Contacting Officer for final resolution; however, the Contractor will first immediately comply with the PM s direction pending the Contacting Officer final resolution at a later time or date. The Contractor will not be due any type of compensation for their costs incurred as a result of an employee being removed for cause; unless the removal is directed by the PM and is later found invalid and/or unreasonable by the Contracting Officer.

USE OF CEMETERY FACILITIES

The Government will not be responsible for any loss, damage, or theft of Contractor items, nor will free telephone service be provided. Contractor shall be responsible for acceptable standards of housekeeping and custodial maintenance of both National Cemetery Administration facilities and Contractor-installed facilities used by the Contractor's employees.

The Government will NOT furnish a storage building or area at the Cemetery site for use by the Contractor to store supplies and equipment. Contractor shall be responsible and required to provide and remove the material, equipment, tools and supplies to perform operations daily.

The Government will NOT furnish a rest room facility to include temporary port-o-pots and will not be allowed on the grounds.

Any hazardous substance that is used and which is a standard practice within the cemetery industry must be handled, stored, and transferred in accordance with all Occupational Safety and Health Administration (OSHA), Environment Protection Agency (EPA), and Department of Transportation (DOT) laws, regulations, and recommendations.

The Contractor will be responsible for safely storing any chemicals, pesticides, herbicides, cleaning solutions, etc. in accordance with manufacturers recommendations. SDS (Safety Data Sheet) is required for any/all chemicals, pesticides, herbicides and cleaning solutions.

Electricity, water and phone services will NOT be furnished by the Government for the Contractor s.

CONSTRUCTION DURING CEMETERY FUNCTIONS

The burial activities at a National Cemetery will take precedence over other contract activities. Contractor shall cooperate and coordinate with the PM or authorized designee, in arranging schedule to cause the least possible interference with cemetery activities in actual burial areas. The PM or a representative shall furnish the Contractor with a schedule of all interments and/or ceremonies no later than the close of business of the day prior to the scheduled event.

Work noise during the interment services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period. Contractor personnel shall not operate motorized equipment or conduct other commercial activities during interment services.

Execute work in such a manner as to interfere as little as possible with work being done by others. To minimize contract activity interference with flow of cemetery traffic, keep roads, walks and entrances to grounds, parking and occupied areas of buildings clear of materials, debris and standing equipment/vehicles at all times. At least one (1) lane must be open to traffic at all times.

Due to the sensitive mission of the Cemetery, the work could occasionally involve contact with and/or exposure to grieving individuals. Contractor personnel shall exercise and exhibit absolute decorum, composure and stability at all times and refer such individuals to Cemetery staff.

HISTORIC PRESERVATION

When the Contractor or any of the Contractor's employees, prior to, or during the service work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the PM verbally, and then with a written follow up.

AUTHORITIES OF GOVERNMENT PERSONNEL

Notwithstanding the Contractor s responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The Government will provide, at the time of contract award, a list of Government personnel authorized to act as PMs.

EXPOSURE OR ACCIDENTAL DISCOVERY OF REMAINS

Should any on-site activity, incident, emergency, or disaster result in exposure and/or damage to any remains, container for remains (i.e., casket or urn), or outer burial container, the Contractor shall IMMEDIATELY notify the Cemetery Director, the PM and/or the CO; take immediate steps to protect and render safe any exposed remains; and stop any further work that could affect those remains or grave site until the Cemetery Director provides the Contractor guidance regarding disposition of the remains and permission to proceed.

GENERAL

Contractor shall NOT mobilize on site until all Kick-Off meeting, Documentation and Submittals have been submitted, reviewed and accepted by the NCA. The PM shall provide written notification approval to mobilize.

WORK ENVIRONMENT AND WEATHER CONDITIONS

All work under this Contract will be performed outdoors and personnel performing the WORK will be exposed to wind, heat, sun, cold, dampness, frost, fog, and rain. These conditions, may, at times, be extreme. The Contractor shall take all necessary precautions to protect his/her employees from the elements to the maximum practicable extent. Weather will not be considered an excusable delay in meeting specifications or project schedule.

The Contractor understands that it may be necessary to work throughout all weather conditions and to apply additional labor and equipment as necessary to meet deadlines, at no additional cost to the Government.

If weather conditions are such that the work performed may cause more damage to the Cemetery grounds than good, the PM has the authority to stop work until conditions improve and the PM directs continuation of performance.

If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

OPERATIONS

It is understood the Government will not be held responsible for any damage to or loss of the Contractor s equipment, materials, supplies or the like which may result from vandalism, theft etc. while on site. The Contractor shall be responsible for maintaining fire extinguishers and other safety equipment.

The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

All utilities to this area are the responsibility of the Contractor. Electrical power is to be supplied by either a Contractor-owned generator or by the local power company. Secondary service runs and the cost of power are the Contractor s responsibility.

The Contractor would then be responsible for delivering and removing all necessary equipment and supplies daily.

DISPOSAL AND RETENTION

The Contractor shall be responsible for cleaning cemetery structures, headstones/flat makers, monuments, and roadways that are soiled or stained as a result of Contractor s performance.

The Contractor shall wash-down with water all soiled or stained structures headstones/flat markers, and monuments at the end of each workday Any such washing/cleaning shall be brought to the immediate attention of the PM prior to washing/cleaning.

At the end of each workday the Contractor shall properly remove and dispose all debris from the Cemetery site resulting from the work. The Contractor shall always ensure that rubbish and trash generated by the Contractor is kept clear of vehicular and pedestrian traffic throughout the site.

The Government will not provide receptacle(s) for disposal of debris related to this contract. The Contractor shall provide its own means of removing debris.

The Contractor shall dispose of all debris and other waste materials at a licensed off-site landfill unless otherwise directed by the PM.

The Contractor shall haul away and dispose of all hazardous waste in accordance with the Resource Conservation and Recovery Act (RCRA) and all other applicable Federal, State, and Local law and regulations. On-installation storage or disposal of hazardous waste is NOT allowed.

At the completion of the project the Contractors shall be responsible for properly removing and disposing of all debris from Government property. All debris and packaging shall be properly removed and disposed of by the Contractor to an approved offsite disposal site or recycling center in compliance with State and Local ordinances.

PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

Restore any areas disturbed in performance of this contract which may require restoration (as deemed appropriate by the PM); and will be deemed incidental to the contract.

All adjacent disturbed surfaces shall be repaired to the same quality standards of the existing work and shall also match the adjacent areas. Contractor hereby agrees to repair or replace deficiencies within the specified time frame by the direction of the Contracting Officer at Contractor's own expense and shall be corrected to the satisfaction of the Government.

Areas outside of the construction limits impacted by operations of the contract shall be returned to the state it was found prior to the construction services. All adjacent disturbed surfaces shall be repaired to the same quality standards of the existing work and shall also match the adjacent areas.

Damage to Government property: The Contractor (including Contractor s employees, subcontractors, consultants or the like) shall be responsible for repair or replacement of any Contractor damaged cemetery structure, to include: turf, curb, road pavement, headstones or markers, valve boxes, grid monument control markers, trees, plant beds, etc., which are chipped, marred, damaged and/or ruined at the fault of the Contractor. The Contractor shall bear all costs associated with replacement and reinstallation. All adjacent disturbed surfaces shall be repaired to the same quality standards of the existing work and shall also match the adjacent areas. Any such damage shall be brought to the immediate attention of the PM prior to repair, replacement, or installation.

The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site that are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so by the PM and shall avoid damaging vegetation that will remain in place.

If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and remove and properly dispose of from the site as defined herein.

The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall immediately notify the PM of any such occurrence and repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.

If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

Protection of Existing Utilities: Contractor shall be responsible for damages to utilities, above and below ground.

RESTORATION

Contractor shall remove, cut, alter, replace, patch and repair existing work as necessary. Except as otherwise shown or specified, do not disturb any water, steam, gas, or electric services without prior approval of the PM or Contracting Officer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the PM before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original construction, except as otherwise shown or specified.

Upon completion of the contract work any existing cemetery features (lawns, paving, roads, and walks) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work. All restoration work shall be accomplished without undue delay.

At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen/subcontractors to existing cemetery infrastructure.

USE OF ROADWAYS

The Contractor will be responsible for traffic control and shall obtain, erect, maintain and remove all signs, barricades, flagmen and other traffic control devices as may be necessary for the purpose of regulating, warning or guiding traffic. All traffic control protection will be considered incidental to the cost of the contract. The Contractor shall, under regulations prescribed by the Contracting Officer or PM, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the PM or Contracting Officer. The route of construction traffic to and from the project site shall be clear of debris at all times as well as the required safety signage and barricades for the safe passage of visitors. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, or similar construction the Contractor shall protect them from damage by well-constructed bridges. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

AVAILABILITY AND USE OF UTILITY SERVICES

Water: A water system is not available. The Contractor shall provide and utilize portable water when needed.

Electricity: In case the Contractor requires electricity while in performance of this Contract, the Contractor shall provide and utilize portable generators as necessary to complete the work.

WORK PERFORMED ON SITE BY OTHERS

The Government may undertake or award other contracts for additional work at or near the site of work for this contract. The Contractor shall fully cooperate with any other contractors and with Government employees and shall carefully adapt scheduling and performance of work, and needing any direction, it shall be provided by the PM.

The Contractor Supervisor shall be responsible for reporting to the PM any problems or questions that may arise with any other personnel on site during the period of performance of this contract. The Contractor Supervisor shall not take it upon him or herself to resolve any problems or issues with other on-site Contractors or employees, but rather will leave it to the PM to resolve the issue.

REPORTING AND RECORD KEEPING

Contractor s Superintendent shall report on a daily basis to the PM at the Cemetery and log in. This DAILY check-in is mandatory and shall be at a time agreed upon by the PM and the Contractor s Superintendent within the requirements of paragraph b below.

A list of scheduled ceremonies will be provided to the Contractor s Superintendent the week prior to the scheduled events, and a list of scheduled committal services will be provided daily. Contractor s Superintendent shall be solely responsible for ensuring that no contract work causes any committal service, ceremony, procession or visitation to be delayed, altered, or otherwise impacted in such a way that the dignity or security of the event is compromised.

The Contractor shall be solely responsible for staying abreast of all such upcoming events and when in doubt, Contractor must ask the PM.

CONTRACTOR-FURNISHED ITEMS

Contractor shall be responsible for supplying all equipment, personnel, tools, supplies and materials necessary to perform the services required by this contract.

Contractor-furnished items necessary to perform work as required under this contract shall be furnished, maintained and operated by the contractor and shall be consistent and fully compliant with all applicable OSHA, Federal, State, County, City laws, ordinances and regulations.

Contractor shall be responsible for the supply, maintenance and repair of all Contractor-owned equipment. This includes minor maintenance/repair and minor operating parts for equipment such as lubrication, oil changes, spark plugs, gaskets, cotter pins/keys, electric extension cords, etc., to keep all equipment in good operational condition throughout the period of performance of this contract. No Contractor equipment maintenance repairs of any kind can be done on Cemetery property without the PM(s) approval.

Contractor shall be responsible for ensuring that all his/her motor vehicles and equipment meet State inspection, safety, licensing, registration, and insurance requirements.

Only Contractor equipment and supplies (property) required to perform work under this contract shall be used on cemetery property. No personal property, equipment, or vehicles shall be staged on the cemetery premises.

GOVERNMENT S RESPONSIBILITIES

Upon award of the contract, the Government will inform the Contractor prior to commencing the work, of any known damages to the cemetery grounds, headstones/markers or any other areas that the Contractor is unaware of and not responsible for.

In addition, upon award of the contract, a walk-through of the cemetery grounds will be scheduled by mutual agreement of the Government and Contractor, and will be attended by the PM, appropriate contractor personnel (to include the Supervisor/Project Manager). The Contracting Officer is an optional attendee.

The Government will not provide the Contractor with any equipment and materials storage, furnishings, fuel storage, equipment, materials, restrooms, or telephones. Utilities will be provided as defined in AVAILABILITY AND USE OF UTILITY SERVICES .

Notification of Non-Compliance: The PM will notify the Contractor of any detected non-compliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification.

If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order ceasing all or part of the work until satisfactory corrective action has been taken.

No part of the time lost due to such cessation direction shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.

CLEANUP

Contractor shall thoroughly clean up the work area at the end of each day s work and at the completion of the project. Contractor must remove and properly dispose of all debris, materials, equipment, and substances daily, at the end/completion of the work/job. Contractor shall leave the premises clean and free of waste, scrap, equipment or other material delivered to the site by the Contractor or contractor s personnel.

Contractor shall request authorization from the PM prior to disposing of any Government owned materials, equipment or property.

Contractor shall properly remove and dispose all debris from government property. Disposal of debris, materials, equipment, and substances shall be in accordance with applicable Federal/State/local and environmental laws, rules and/or regulations.

Contractor shall provide, if requested, shipping manifest and documentation of proper disposal of any debris, materials, equipment, and substances prior to final payment. Contractor shall ensure and provide appropriate documentation to the PM that all applicable hazardous waste, haulers, and disposal facilities are properly certified or licensed.

The project site shall be protected and/or restored to a condition equal to that existing prior to the commencement of work.

PERSONAL PROTECTIVE EQUIPMENT

Contractor shall provide Personal Protective Equipment (PPE), proper safety signage; and must provide and have in place: fire extinguishers, cones, barricades etc., to protect the safety of visitors, patients, employees and tenants. The Contractor shall not be permitted to work if the proper safety equipment/items are missing; and shall be asked to leave the area/facility.

SAFETY DATA SHEETS

Contractor shall provide the PM with a copy of the Label of any product, material and/or chemical that is potential hazardous, as well as the Safety Data Sheets (SDS), before any such product, material and/or chemical is used.

MATERIAL STORAGE

There will be No on-site office or on-site storage/office container allowed. The contractor shall provide just in time delivery and pickup . The Contractor shall coordinate with the PM for material storage/staging within the work area. The storage/staging of equipment, materials or supplies must have prior PM approval.

Tools/Staging: Contractor shall provide its own required tools, ladders and equipment to complete the work.

Operating vehicles/equipment: Contractors shall not leave operating vehicles/equipment unattended at any time and all shall ensure that vehicle/equipment keys are removed when not in operation.

SMOKING

Is not prohibited inside any facility buildings. Smoking is prohibited within twenty-five feet from Entrances, Exits, Operable Windows, and Ventilation intakes that serve an enclosed area where smoking is prohibited.

NOISE

The Contractor / Contractor personnel shall not engage in loud or boisterous behavior, angry outbursts or use profane or abusive language at any time on Government property. The playing of loud music radios and/or electronic games/devices is not permitted. Two-way communications radios shall be allowed where broadcast frequency is approved by the PM. Contractor shall coordinate and schedule any noise making activities with the PM. For any noise making work activities, the Contractor must provide written notification to the PM and the PM will schedule and provide written authorization to proceed within three (3) business days in advance of the proposed activity.

FIRE-SEAL

If applicable, Contractor shall fire-seal all penetrations through any wall or floor with UL-Listed fire rated assemblies or materials.

FUMES

Any fume producing activities shall be scheduled after regular business hours unless written permission has been granted by the PM. The Contractor shall be responsible for all ventilation necessary to evacuate and prevent fumes from entering the building(s).

HOT WORK PERMIT

Any work or operation involving open flame or producing heat and/or sparks, (burning, welding or similar operation) that is capable of initiating fires or explosions will require a Hot Work Permit . The Contractor shall request a Hot Work Permit from the PM, a minimum of one (1) business day prior to the work activity.

This work shall include, but shall not be limited to, processes such as arc welding, oxy-fuel gas welding, open- flame soldering, brazing, thermal spraying, oxygen cutting, arc cutting, chipping, grinding, heat treating, sand blasting, torch-applied roofing, chemical welding and light horizontal welding.

PHOTOGRAPHY

Photography of employees, visitors, volunteers, and others on NCA premises is strictly prohibited. Photography of NCA premises (buildings, grounds, property, site) is allowed ONLY with written permission from the PM.

CONSTRUCTION SAFETY

Contractor shall ensure that all onsite construction workers (including subcontractors) have completed the OSHA 10-hour Construction Safety training or the 30-hour Construction Safety training, and other relevant competency training. Contractor shall provide verification of such training to the Contracting Officer and the PM prior to mobilizing and at anytime requested during the course of the work, until the contract is completed.

WARRANTY

Contractor shall Guarantee that all work done under this contract shall be free from defaults and no faulty materials or workmanship with no less than a One (1) Year Warranty .

SECURITY & SAFETY

Contractor, Contractor s employees and sub-contractors shall follow all VA Policies, Standard Operating Procedures, applicable Laws and Regulations while on VA property. Violations of VA Policies, Standard Operating Procedures, applicable Laws and Regulations may result in citation and disciplinary measures for persons violating the VA Policies, Standard Operating Procedures, applicable Laws and Regulations.

Contractor, Contractor s employees and sub-contractors shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of this contract.

Contractor, Contractor s employees and sub-contractors shall comply with VA Security Management program.

Contractor shall not employ any person who is an employee of the United States Government if that employment would appear to cause a Conflict of Interest.

Possession of weapons of any kind is prohibited on VA property; violators will be subject to fines or imprisonment under 18 U.S. Code § 930 - Possession of firearms and dangerous weapons in Federal facilities.

Any provision or partial provision of this notice that is not consistent with the contract specifications shall be null and void only to the extent of the inconsistency; all other provisions or partial provisions of this notice shall remain in full force and effect.

Contractor, Contractor s employees and sub-contractors shall comply with all site-specific requirements and Standard Operating Procedures (SOP s) including but not limited to: Rules of Behavior, and Smoking Policy.

Contractor, Contractor s employees and sub-contractors shall follow all VA policies, standard operating procedures, applicable laws and regulations while on VA property. Violations of VA regulations and policies may result in citation and disciplinary measures for persons violating the law.

NOTE: In the event of any inconsistency between the Statement of Work and the drawing and / or specification of this requirement, the requirement drawing, and specifications will prevail.

(End of Statement of Work)

Files

File Type Posted
36C78623B0001 0003.pdf PDF
Concrete Pavement Detail.pdf PDF
36C78623B0001 0003.docx DOCX document
36C78623B0001 0002.docx DOCX document
36C78623B0001 0001.docx DOCX document
Cost Estimate Worksheet.pdf PDF
DOL Wage Determination Lincoln County NE.pdf PDF
Past Performance.pdf PDF
Plans Part 2.pdf PDF
Plans Part 1.pdf PDF
Specifications.pdf PDF
RFI Form.pdf PDF
WAGE-RATES.pdf PDF
IFB _ 36C78623B0001.pdf PDF
Show all 14

Notice history

Notice Type Posted
Y1PZ--890CM3014: Gravesite Expansion Ft McPherson National Cemetery Award Award Notice
This notice Latest solicitation Solicitation
Y1PZ--890CM3014: Gravesite Expansion, Ft McPherson National Cemetery Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Y1PZ--Fort Sill NC Gravesite Expansion and FCA Deficiencies 920CM3006 Elgin, Oklahoma 73538, United States · NAICS 237990 National Cemetery Administration Service-Disabled Veteran-Owned Small Business
Fort Bliss National Cemetery, Gravesite Expansion and FCA Deficiencies El Paso, Texas 79906, United States · NAICS 237990 National Cemetery Administration Service-Disabled Veteran-Owned Small Business
Gravesite Expansion Florence National Cemetery 943CM3023 Florence, South Carolina 29506, United States · NAICS 237990 National Cemetery Administration Service-Disabled Veteran-Owned Small Business
Y1JZ--926CM3010 Cemetery Expansion and FCA Improvements Project Washington Crossing National Cemetery Newton PA 18940, United States · NAICS 237990 National Cemetery Administration Service-Disabled Veteran-Owned Small Business
Camp nelson national cemetery, KY 833CM3030 – correct FCA deficiencies Nicholasville, Kentucky 40356, United States · NAICS 237990 National Cemetery Administration Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors