This statement of work describes requirements for a construction services contract to expand gravesites at Fort McPherson National Cemetery in Nebraska. The contractor shall provide all management, supervision, labor, equipment, materials and tools to complete site preparation including demolition and removal of existing structures. The contractor must perform a site investigation and submit an after-inspection report before starting work. The performance period is 365 calendar days from notice to proceed. The contractor must follow National Cemetery Administration standards and comply with all safety, conduct, operations and reporting requirements detailed in the statement of work.

View the file

Other files

File Type Posted
36C78623B0001 0003.pdf PDF
Concrete Pavement Detail.pdf PDF
36C78623B0001 0003.docx DOCX document
36C78623B0001 0002.docx DOCX document
36C78623B0001 0001.docx DOCX document
DOL Wage Determination Lincoln County NE.pdf PDF
Past Performance.pdf PDF
Plans Part 2.pdf PDF
Plans Part 1.pdf PDF
Specifications.pdf PDF
WAGE-RATES.pdf PDF
RFI Form.pdf PDF
IFB _ 36C78623B0001.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number:

Solicitation Number:

Project Title:

Division Unit of Measure # of Units Unit Cost $ Extended/Total

Cost $ Comments / Remarks Division 0 - Special Sections

General Conditions and Administration

JB 1

Division 01 - General Requirements

Mobilization JB 1

Division 02 - Existing Conditions

Site Investigation JB 1

Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastic, and Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings (Doors, Windows, etc...)

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12- Furnishings

Division 13 - Special Construction

Division 14 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 25 - Integrated Automation

Division 26 - Electrical

Gravesite Expansion

Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number.

If a Division is not being used put N/A in that field.

Additional lines/items can be added if needed or appropriate.

IFB Contractor Cost Estimate Worksheet

890CM3014

36C78623B0001

Offeror shall use and edit to fit Task Order Project

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Mechanical, Electrical, Plumbing Subtotal

General Construction Subtotal

Total Base Construction Cost

Insurance (if applicable)

Bonding (if applicable)

Overhead ________ % $0.00

Profit ________ % $0.00

GRAND TOTALS $