Turbine Rehabilitation & Generator Rewind, Norfork Powerhouse
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9127S21R0001
- Agency
-
ENDIST Little Rock
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Norfork, Arkansas 72658, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals for turbine rehabilitation and generator rewind services at the Norfork Powerhouse in Baxter County, Arkansas. The U.S. Army Corps of Engineers Little Rock District intends to award a contract to rehabilitate and rewind the turbines and generators of two generating units at the Norfork Lake Dam and Powerhouse. Proposals are to be evaluated based on past performance, technical approach, schedule, quality control, and price. The response deadline was extended to April 20, 2022. Bidders must meet experience requirements for projects of similar scope and magnitude involving Francis turbines and generators of comparable size to those specified.
The magnitude of construction is estimated between $25 million to $75 million. There is no set-aside designation, making this a full and open competition. The NAICS code is 237130 and PSC code is R499. The place of performance is Norfork, Arkansas. A site visit was held in October 2021 and questions were required to be submitted through ProjNet by October 21, 2021. The work must be completed within specified outage window timelines to avoid potential liquidated damages. At least 10% small business participation is required.
Notice text
3 versions
Update #3 · Latest ·
Turbine Rehabilitation and Generator Rewind, Norfork Lake, Dam and Powerhouse, White River Basin, Baxter County, Arkansas
Magnitude of Construction: Between $25,000,000 and $75,000,000
Set-Aside: Full and Open Competition
Site Visit: An organized Site Visit has been scheduled for October 12-14, 2021 and November 01-02, 2021, at the Norfork Powerhouse. Please see FAR 52.236-27 Alt 1 in section 00 21 00 for complete details.
Bidder Inquiry: A Request for Information (RFI) Review has been set up at www.projnet.org for this solicitation. The Projnet Inquiry Key is M3SKC3-9A73UQ. The review is open from September 30, 2021, until November 9, 2021.
ProjNet w ill be reopened from December 16, 2021, until January 28, 2022 for additional bidder inquiries.
Reference Drawings: This file is too large to post on SAM. Please email sarah.n.hagood@usace.army.mil if you would like a copy of this document sent to you via DoD SAFE.
Update #2 ·
Turbine Rehabilitation and Generator Rewind, Norfork Lake, Dam and Powerhouse, White River Basin, Baxter County, Arkansas
Magnitude of Construction: Between $25,000,000 and $75,000,000
Set-Aside: Full and Open Competition
Site Visit: An organized Site Visit has been scheduled for October 12-14, 2021 and November 01-02, 2021, at the Norfork Powerhouse. Please see FAR 52.236-27 Alt 1 in section 00 21 00 for complete details.
Bidder Inquiry: A Request for Information (RFI) Review has been set up at www.projnet.org for this solicitation. The Projnet Inquiry Key is M3SKC3-9A73UQ. The review is open from September 30, 2021, until November 9, 2021.
Reference Drawings: This file is too large to post on SAM. Please email sarah.n.hagood@usace.army.mil if you would like a copy of this document sent to you via DoD SAFE.
Update #1 ·
Turbine Rehabilitation and Generator Rewind, Norfork Lake, Dam and Powerhouse, White River Basin, Baxter County, Arkansas
Magnitude of Construction: Between $25,000,000 and $75,000,000
Set-Aside: Full and Open Competition
Site Visit: An organized Site Visit has been scheduled for October 12-14, 2021, at the Norfork Powerhouse. Please see FAR 52.236-27 Alt 1 in section 00 21 00 for complete details.
Bidder Inquiry: A Request for Information (RFI) Review has been set up at www.projnet.org for this solicitation. The Projnet Inquiry Key is M3SKC3-9A73UQ. The review is open from September 30, 2021, until October 21, 2021.
Reference Drawings: This file is too large to post on SAM. Please email sarah.n.hagood@usace.army.mil if you would like a copy of this document sent to you via DoD SAFE.
Files
Show all 18
Notice history
| Notice | Type | Posted |
|---|---|---|
| Turbine Rehabilitation & Generator Rewind, Norfork Powerhouse | Award Notice | |
| This notice | Solicitation | |
| Turbine Rehabilitation & Generator Rewind, Norfork Powerhouse | Pre-Solicitation | |
| INDUSTRY REVIEW: Turbine Rehabilitation & Generator Rewind, Norfork Powerhouse | Special Notice | |
| Turbine Replacement & Generator Rewind, Norfork Powerhouse | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Eufaula Powerhouse Hydroelectric Generator Rewind | ENDIST Tulsa | No set-aside | |
| Tenkiller Hydropower Excitation System Replacement | ENDIST Tulsa | No set-aside | |
| Webbers Falls U1 Speed Increaser Gearbox Replacement | ENDIST Tulsa | No set-aside | |
| Webbers Falls Excitation System Replacements | ENDIST Tulsa | No set-aside |