Steam Plant Upgrades - Projects B260 at Hill AFB
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9123822R0007
- Agency
-
ENDIST Sacramento
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Hill AFB, Utah 84056, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This two-phase Design-Build solicitation issued by the Department of the Army Corps of Engineers Engineering District Sacramento seeks to award a firm-fixed price construction contract to replace eight existing boilers and upgrade supporting equipment at Building 260 Steam Plant at Hill Air Force Base in Utah. The selected contractor will replace the boilers with five new dual-fuel boilers rated at 50 MMBtu/hr each achieving ultra-low NOx emissions of 9 ppm, remove underground fuel oil storage tanks and replace with aboveground tanks sized for seven days of peak storage, conduct seismic retrofitting of existing buildings, and upgrade deaerators, pumps and other supporting equipment. Proposals are due by July 11, 2022 with evaluation based on design approach, past performance, and price.
This is a 100% small business set-aside with a NAICS code of 238990 and size standard of $16.5 million. The estimated value of construction is between $25-100 million to be completed within 730 calendar days at Hill Air Force Base in Utah. Potential contractors include six companies listed on the interested vendor list. The main PSC code is Z2NB.
Notice text
3 versions
Update #3 · Latest ·
Building 260 Steam Plant Upgrades at Hill AFB Solicitation # W9123822R0007
This requirement is a two-phase Design-Build Request for Proposal (RFP) with the intent of awarding a Firm-Fixed Price construction contract for Building 260 Steam Plant Upgrades at Hill AFB.
Competition in this procurement is only for the selected Offerors, that were invited to participate in Phase Two.
Project Description:
The Contractor shall perform improvements and repair of boilers in Building 260 (B260) Hill AFB project. This project will include the replacement of eight existing boilers in B260 with new dual-fuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants.
The boilers in B260 will be replaced with five new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. This will be a DB contract.
In accordance with DFARS 236.204(ii) the estimated magnitude of construction is expected to be Between $25,000,000.00 and $100,000,000.00. The NAICS Code is 236220 - Commercial and Institutional Building Construction. The size standard is $39.5M. The Product Service Code is Z2NB – Repair or Alteration of Heating and Cooling Plants. This solicitation will proceed as a 100% Small Business Set Aside.
Update #2 ·
Building 260 Steam Plant Upgrades at Hill AFB Solicitation # W9123822R0007
This requirement is a two-phase Design-Build Request for Proposal (RFP) with the intent of awarding a Firm-Fixed Price construction contract for Building 260 Steam Plant Upgrades at Hill AFB.
Project Description:
The Contractor shall perform improvements and repair of boilers in Building 260 (B260) Hill AFB project. This project will include the replacement of eight existing boilers in B260 with new dual-fuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants.
The boilers in B260 will be replaced with five new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. This will be a DB contract.
In accordance with DFARS 236.204(ii) the estimated magnitude of construction is expected to be Between $25,000,000.00 and $100,000,000.00. The NAICS Code is 236220 - Commercial and Institutional Building Construction. The size standard is $39.5M. The Product Service Code is Z2NB – Repair or Alteration of Heating and Cooling Plants. This solicitation will proceed as a 100% Small Business Set Aside.
Update #1 ·
Building 260 Steam Plant Upgrades at Hill AFB Solicitation # W9123822R0007
This requirement is a two-phase Design-Build Request for Proposal (RFP) with the intent of awarding a Firm-Fixed Price construction contract for Building 260 Steam Plant Upgrades at Hill AFB.
Project Description:
The Contractor shall perform improvements and repair of boilers in Building 260 (B260) Hill AFB project. This project will include the replacement of eight existing boilers in B260 with new dual-fuel (natural gas/fuel oil) boilers that meet BACT. This option will require phasing the boiler replacement in the existing plants to maintain steam production for the existing load. The existing buildings will require new wall openings and an emergency boiler to maintain “N+1” boiler redundancy in the plants.
The boilers in B260 will be replaced with five new 50 million Btu/hour (MMBH) boilers. The boilers will achieve ultra-low oxides of nitrogen (NOx) emissions of 9 parts per million (ppm). The existing boiler fuel oil underground storage tanks (USTs) in both buildings will be removed and replaced with aboveground storage tanks (AST), which are sized for seven days of storage during peak heating season. The existing buildings will have seismic retrofitting and supporting equipment (deaerator, pumps, etc.) upgraded. This will be a DB contract.
In accordance with DFARS 236.204(ii) the estimated magnitude of construction is expected to be Between $25,000,000.00 and $100,000,000.00. The NAICS Code is 238990 - All Other specialty Trade Contractor. The size standard is $16.5M. The Product Service Code is Z2NB – Repair or Alteration of Heating and Cooling Plants. This solicitation will proceed as a 100% Small Business Set Aside.
Files
Show all 31
Notice history
| Notice | Type | Posted |
|---|---|---|
| Steam Plant Upgrades - Projects B260 at Hill AFB | Award Notice | |
| This notice | Solicitation | |
| Steam Plant Upgrades - Projects B260 at Hill AFB | Pre-Solicitation | |
| Steam Plant Upgrades - Projects B260 at Hill AFB | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| 16292 Steam Boiler Replacement | Air Force Sustainment Center | Total Small Business | |
| Z1DA--FY27 NRM - Replace B98 and B88 Boiler and Sump Pumps | Veterans Integrated Service Network 21 | No set-aside | |
| HAFB Multiple Award Construction Contract V (MACC V) | Air Force Sustainment Center | Total Small Business | |
| F-35 Composite Repair and Training Facility / F-35 Maintenance Facility, Hill Air Force Base, Utah | ENDIST Sacramento | No set-aside | |
| SABER V Hill AFB | Air Force Sustainment Center | Competitive 8(a) |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity