About this opportunity

The US Department of Agriculture (USDA) is seeking a contractor for the demolition of two buildings located within the Sierra Ancha Experimental Forest, including the removal and disposal of all building elements above the foundation, capping of water and sewer lines, and removal and disposal of asbestos-containing materials. The work must be completed within fifteen consecutive days after work begins. The magnitude of construction is between $25,000 and $100,000, and the offer due date is August 18th, 2023.

List of services to be provided by the contractor:

  1. Demolition of two buildings (The Shop and the Mess Hall)
  2. Removal and disposal of all building elements above the foundation
  3. Capping of water and sewer lines
  4. Removal and disposal of all asbestos-containing materials
  5. Complete removal and disposal of the concrete pier foundations of the Mess Hall (optional)
  6. Complete removal and disposal of the concrete slab foundation of the Shop and regrading of the site to match surrounding landscape and natural slope (optional)
  7. Backfill of voids left by piers with material found on site and regrading of the site to match surrounding landscape and natural slope (optional)

Notice text

4 versions

Update #4 · Latest ·

AMENDMENT 0003 - AUGUST 15TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO PROVIDE ANSWERS TO QUESTIONS RECEIVED ON 08/14/2023. NO OTHER CHANGES. DUE DATE REMAINS 08/18/2023 BY 1700 (MT).

AMENDMENT 0002 - AUGUST 7TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO EXTEND THE OFFER DUE DATE UNTIL AUGUST 18TH TO PROVIDE OFFERORS ADDITIONAL TIME TO SUBMIT PROPOSALS. NO OTHER CHANGES.

AMENDMENT 0001 - AUGUST 4TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO DOCUMENT THE SITE VISIT HELD ON AUGUST 1ST, 2023 AND PROVIDE ANSWERS TO QUESTIONS. THE SCHEDULE OF ITEMS HAS ALSO BEEN REVISED AND SITE VISIT ATTENDEE INFORMATION IS PROVIDED. OFFER DUE DATE IS NOT EXTENDED.

AMENDMENT ATTACHMENTS:

1240LT23Q0096.0001 - SIERRA ANCHA BUILDING DEMOLITION (3 PAGES)

AMENDMENT 0001 - (REV 2) SCHEDULE OF ITEMS - SIERRA ANCHA BUILDING DEMOLITION

AMENDMENT 0001 - SIERRA ANCHA DEMO - SITE VISIT ATTENDEE SIGN-IN SHEET

The Sierra Ancha Experimental Forest is seeking quotations for the Sierra Ancha Building Demolition project. 

Description of Work: Work includes, but is not limited to, the demolition of two buildings, haul off, and disposal of demolished materials. The Shop is a 960 sq. ft building with a wood frame and corrugated metal siding. The Mess Hall (Building #5) is an 834 sq. ft wood building. This solicitation has been revised to include required asbestos abatement. (Description of work on the SF-18 is actually the location, this will be amended after the site visit when we provide Q&As)

Location: The Shop and the Mess Hall are both located within the Sierra Ancha Experimental Forest. From Apache Junction, take State Highway 88 northeast to Roosevelt on Lake Roosevelt and then southeast to Highway 288. Turn on to Highway 288 and follow it north until the pavement ends, and then continue on the dirt road until you pass the Arizona DOT workstation. Just past it is a Sierra Ancha Experimental Forest sign on the right, and you will find an access road with a gate to enter the site. (GILA COUNTY, AZ)

Magnitude of construction is between $25,000 and $100,000.

This is a small business set-aside (NAICS: 238910 / $19.0M)

There is a site visit scheduled for August 1st, 2023 at 10 AM (Local Time, Arizona, MST), 11 AM (Mountain Time, Denver). See Section L for details.

Submit your proposals to Westley.Bisson@usda.gov. Do not mail your proposals.

Update #3 ·

AMENDMENT 0002 - AUGUST 7TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO EXTEND THE OFFER DUE DATE UNTIL AUGUST 18TH TO PROVIDE OFFERORS ADDITIONAL TIME TO SUBMIT PROPOSALS. NO OTHER CHANGES.

AMENDMENT 0001 - AUGUST 4TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO DOCUMENT THE SITE VISIT HELD ON AUGUST 1ST, 2023 AND PROVIDE ANSWERS TO QUESTIONS. THE SCHEDULE OF ITEMS HAS ALSO BEEN REVISED AND SITE VISIT ATTENDEE INFORMATION IS PROVIDED. OFFER DUE DATE IS NOT EXTENDED.

AMENDMENT ATTACHMENTS:

1240LT23Q0096.0001 - SIERRA ANCHA BUILDING DEMOLITION (3 PAGES)

AMENDMENT 0001 - (REV 2) SCHEDULE OF ITEMS - SIERRA ANCHA BUILDING DEMOLITION

AMENDMENT 0001 - SIERRA ANCHA DEMO - SITE VISIT ATTENDEE SIGN-IN SHEET

The Sierra Ancha Experimental Forest is seeking quotations for the Sierra Ancha Building Demolition project. 

Description of Work: Work includes, but is not limited to, the demolition of two buildings, haul off, and disposal of demolished materials. The Shop is a 960 sq. ft building with a wood frame and corrugated metal siding. The Mess Hall (Building #5) is an 834 sq. ft wood building. This solicitation has been revised to include required asbestos abatement. (Description of work on the SF-18 is actually the location, this will be amended after the site visit when we provide Q&As)

Location: The Shop and the Mess Hall are both located within the Sierra Ancha Experimental Forest. From Apache Junction, take State Highway 88 northeast to Roosevelt on Lake Roosevelt and then southeast to Highway 288. Turn on to Highway 288 and follow it north until the pavement ends, and then continue on the dirt road until you pass the Arizona DOT workstation. Just past it is a Sierra Ancha Experimental Forest sign on the right, and you will find an access road with a gate to enter the site. (GILA COUNTY, AZ)

Magnitude of construction is between $25,000 and $100,000.

This is a small business set-aside (NAICS: 238910 / $19.0M)

There is a site visit scheduled for August 1st, 2023 at 10 AM (Local Time, Arizona, MST), 11 AM (Mountain Time, Denver). See Section L for details.

Submit your proposals to Westley.Bisson@usda.gov. Do not mail your proposals.

Update #2 ·

AMENDMENT 0001 - AUGUST 4TH, 2023 - THE PURPOSE OF THIS AMENDMENT IS TO DOCUMENT THE SITE VISIT HELD ON AUGUST 1ST, 2023 AND PROVIDE ANSWERS TO QUESTIONS. THE SCHEDULE OF ITEMS HAS ALSO BEEN REVISED AND SITE VISIT ATTENDEE INFORMATION IS PROVIDED. OFFER DUE DATE IS NOT EXTENDED.

AMENDMENT ATTACHMENTS:

1240LT23Q0096.0001 - SIERRA ANCHA BUILDING DEMOLITION (3 PAGES)

AMENDMENT 0001 - (REV 2) SCHEDULE OF ITEMS - SIERRA ANCHA BUILDING DEMOLITION

AMENDMENT 0001 - SIERRA ANCHA DEMO - SITE VISIT ATTENDEE SIGN-IN SHEET

The Sierra Ancha Experimental Forest is seeking quotations for the Sierra Ancha Building Demolition project. 

Description of Work: Work includes, but is not limited to, the demolition of two buildings, haul off, and disposal of demolished materials. The Shop is a 960 sq. ft building with a wood frame and corrugated metal siding. The Mess Hall (Building #5) is an 834 sq. ft wood building. This solicitation has been revised to include required asbestos abatement. (Description of work on the SF-18 is actually the location, this will be amended after the site visit when we provide Q&As)

Location: The Shop and the Mess Hall are both located within the Sierra Ancha Experimental Forest. From Apache Junction, take State Highway 88 northeast to Roosevelt on Lake Roosevelt and then southeast to Highway 288. Turn on to Highway 288 and follow it north until the pavement ends, and then continue on the dirt road until you pass the Arizona DOT workstation. Just past it is a Sierra Ancha Experimental Forest sign on the right, and you will find an access road with a gate to enter the site. (GILA COUNTY, AZ)

Magnitude of construction is between $25,000 and $100,000.

This is a small business set-aside (NAICS: 238910 / $19.0M)

There is a site visit scheduled for August 1st, 2023 at 10 AM (Local Time, Arizona, MST), 11 AM (Mountain Time, Denver). See Section L for details.

Submit your proposals to Westley.Bisson@usda.gov. Do not mail your proposals.

Update #1 ·

The Sierra Ancha Experimental Forest is seeking quotations for the Sierra Ancha Building Demolition project. 

Description of Work: Work includes, but is not limited to, the demolition of two buildings, haul off, and disposal of demolished materials. The Shop is a 960 sq. ft building with a wood frame and corrugated metal siding. The Mess Hall (Building #5) is an 834 sq. ft wood building. This solicitation has been revised to include required asbestos abatement. (Description of work on the SF-18 is actually the location, this will be amended after the site visit when we provide Q&As)

Location: The Shop and the Mess Hall are both located within the Sierra Ancha Experimental Forest. From Apache Junction, take State Highway 88 northeast to Roosevelt on Lake Roosevelt and then southeast to Highway 288. Turn on to Highway 288 and follow it north until the pavement ends, and then continue on the dirt road until you pass the Arizona DOT workstation. Just past it is a Sierra Ancha Experimental Forest sign on the right, and you will find an access road with a gate to enter the site. (GILA COUNTY, AZ)

Magnitude of construction is between $25,000 and $100,000.

This is a small business set-aside (NAICS: 238910 / $19.0M)

There is a site visit scheduled for August 1st, 2023 at 10 AM (Local Time, Arizona, MST), 11 AM (Mountain Time, Denver). See Section L for details.

Submit your proposals to Westley.Bisson@usda.gov. Do not mail your proposals.

Attachments

Show all 11

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Sierra ancha building demolition Award Award Notice
Sierra ancha building demolition This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity