This statement of work outlines the technical requirements for the demolition of two buildings located within the Sierra Ancha Experimental Forest for the Department of Agriculture Forest Service solicitation numbered 1240LT23Q0096. The base scope of work includes the demolition and disposal of all elements above the foundation for the Shop building, as well as the removal and disposal of asbestos materials in the Mess Hall comprising 300 square feet of flooring and 3 linear feet of pipe. Optional work items include the full demolition and disposal of the Mess Hall down to its concrete pier foundations, removal of the concrete pier foundations, demolition and disposal of the Shop's concrete slab foundation and site regrading. All work must be completed within fifteen consecutive days of commencement. No explosives are permitted for the demolitions.
View the file
Other files for this federal contract opportunity
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachment
Project Sierra Ancha Building Demolition
General Information
1.0 Scope of Work
The work includes the demolition of two buildings, haul off, and disposal of demolished materials. The Shop is a 960 sq.
ft building with a wood frame and corrugated metal siding. The Mess Hall (Building #5) is an 834 sq. ft wood building.
Both buildings must be demolished without the use of explosives. The Mess Hall must have water and sewer lines capped and, at minimum, everything above the foundation must be removed and disposed of properly. The foundation of the Mess Hall consists of concrete piers. The foundation of the Shop is a concrete slab on grade.
2.0 Background
The Shop and the Mess Hall are both located within the Sierra Ancha Experimental Forest. From Apache Junction, take State Highway 88 northeast to Roosevelt on Lake Roosevelt and then southeast to Highway 288. Turn on to Highway 288 and follow it north until the pavement ends, and then continue on the dirt road until you pass the Arizona DOT workstation. Just past it is a Sierra Ancha Experimental Forest sign on the right, and you will find an access road with a gate to enter the site.
Contractor Requirements
3.0 Technical Requirements / Tasks
The base scope of work includes two bid items:
- Demolition and disposal of all building elements above the foundation of the Shop. Under no circumstances will the use of explosives be permitted. This includes, but is not limited to, the removal of:
o Walls o Windows o Roofs o Support Beams o Both water and sewer lines must be capped. All demolition materials must be removed from the site and disposed of properly, the contractor shall be responsible for all permits and fees.
- Removal and disposal of all asbestos-containing materials (ACMs) from the Mess Hall, comprising approximately
300 SF of vinyl sheet flooring and 3 LF of asbestos-cement pipe, by an EPA-certified asbestos abatement contractor. See Specification Section 024230.
Option work items include:
- Demolition and disposal of all building elements above the concrete foundation piers of the Mess Hall, as described for the Shop in the base scope above
- Complete removal and disposal of the concrete pier foundations of the Mess Hall
- Complete removal and disposal of the concrete slab foundation of the Shop and regrading of the site to match surrounding landscape and natural slope
- Backfill of voids left by piers with material found on site and regrading of the site to match surrounding landscape and natural slope
4.0 Government Furnished
N/A
5.0 Deliverables / Schedule
All work must be completed within fifteen consecutive days after work begins.
6.0 Travel
N/A
7.0 Contractor’s Key Personnel
8.0 Security Requirements
N/A
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards
Attachment
Mess Hall
Mess Hall Back Porch
Mess Hall Supports
Shop Exterior
Shop Interior
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |