About this opportunity
This solicitation seeks a firm fixed price construction contract to reconstruct sections of Taxiway Mike and Taxiway Delta at Cannon Air Force Base in New Mexico. The Department of the Air Force Special Operations Command is procuring these reconstruction services to improve the condition of the taxiways based on deterioration identified in a 2015 pavement assessment. The contractor will remove and replace asphalt with Portland cement concrete on 102,000 square feet of Taxiway Mike and 100,000 square feet of Taxiway Delta, along with slab replacement, joint seal repair, and material submittals. Proposals are due by June 14, 2021 and the period of performance is 471 calendar days from notice to proceed. Evaluation criteria include past performance, technical approach, and price.
This is a competitive 8(a) set-aside designated under NAICS 237310 and PSC Z1PB. The place of performance is Cannon Air Force Base in New Mexico. The estimated budget is not disclosed but includes reconstruction of over 200,000 square feet of taxiway pavement. The incumbent is unknown as this appears to be the first solicitation for this requirement.
Notice text
4 versions
Update #4 · Latest ·
**UPDATE**
8 Jun 21 - The following items have been uploaded to this amended posting:
Amended solicitation, extending the due date to 14 Jun 21.
Updated attachment 3.
Updated attachment 5.
Updated attachment 12.
Updated Questions and Answers.
**UPDATE**
4 Jun 21 - Questions and Answers has been posted under the attachments in regards to this solicitaiton.
**UPDATE**
The suspense for RFI's is 26 May 21, 1500 MDT. We cannot guarantee that RFIs submitted after this suspense will be answered before the proposal due date of 11 Jun 21.
This is a single construction project for the airfield at CAFB, NM with two phases. In phase one, the vendor will reconstruct sections T17A and T18A of Taxiway Mike. The reconstruction of Taxiway Mike includes the removal of 102,000 square feet of 3" Asphalt, to replace with 102,000 square feet of new Portland Cement Concrete (PCC). This will also include slab replacement of adjoining hot brake pad and joint seal repair. In phase two, the vendor will reconstruct sections T12A and T13A1 of Taxiway Delta. The reconstruction of Taxiway Delta includes the reconstruction of 25,000 square feet of PCC in section T13A1, slab replacement, and joint seal repair. Additionally, 75,000 square feet of 4" Asphalt shall be removed and replaced with PCC in section T12A.
Taxiways Mike and Delta are located on the same airfield of CAFB, NM. Taxiway Delta covers 100,000 square feet and Taxiway Mike covers 102,000 square feet. Stemming from a 2015 Pavement Condition Index (PCI) Report, it was determined that sections of Taxiways Mike and Delta are in need of repair.
Update #3 ·
**UPDATE**
4 Jun 21 - Questions and Answers has been posted under the attachments in regards to this solicitaiton.
**UPDATE**
The suspense for RFI's is 26 May 21, 1500 MDT. We cannot guarantee that RFIs submitted after this suspense will be answered before the proposal due date of 11 Jun 21.
This is a single construction project for the airfield at CAFB, NM with two phases. In phase one, the vendor will reconstruct sections T17A and T18A of Taxiway Mike. The reconstruction of Taxiway Mike includes the removal of 102,000 square feet of 3" Asphalt, to replace with 102,000 square feet of new Portland Cement Concrete (PCC). This will also include slab replacement of adjoining hot brake pad and joint seal repair. In phase two, the vendor will reconstruct sections T12A and T13A1 of Taxiway Delta. The reconstruction of Taxiway Delta includes the reconstruction of 25,000 square feet of PCC in section T13A1, slab replacement, and joint seal repair. Additionally, 75,000 square feet of 4" Asphalt shall be removed and replaced with PCC in section T12A.
Taxiways Mike and Delta are located on the same airfield of CAFB, NM. Taxiway Delta covers 100,000 square feet and Taxiway Mike covers 102,000 square feet. Stemming from a 2015 Pavement Condition Index (PCI) Report, it was determined that sections of Taxiways Mike and Delta are in need of repair.
Update #2 ·
**UPDATE**
The suspense for RFI's is 26 May 21, 1500 MDT. We cannot guarantee that RFIs submitted after this suspense will be answered before the proposal due date of 11 Jun 21.
This is a single construction project for the airfield at CAFB, NM with two phases. In phase one, the vendor will reconstruct sections T17A and T18A of Taxiway Mike. The reconstruction of Taxiway Mike includes the removal of 102,000 square feet of 3" Asphalt, to replace with 102,000 square feet of new Portland Cement Concrete (PCC). This will also include slab replacement of adjoining hot brake pad and joint seal repair. In phase two, the vendor will reconstruct sections T12A and T13A1 of Taxiway Delta. The reconstruction of Taxiway Delta includes the reconstruction of 25,000 square feet of PCC in section T13A1, slab replacement, and joint seal repair. Additionally, 75,000 square feet of 4" Asphalt shall be removed and replaced with PCC in section T12A.
Taxiways Mike and Delta are located on the same airfield of CAFB, NM. Taxiway Delta covers 100,000 square feet and Taxiway Mike covers 102,000 square feet. Stemming from a 2015 Pavement Condition Index (PCI) Report, it was determined that sections of Taxiways Mike and Delta are in need of repair.
Update #1 ·
This is a single construction project for the airfield at CAFB, NM with two phases. In phase one, the vendor will reconstruct sections T17A and T18A of Taxiway Mike. The reconstruction of Taxiway Mike includes the removal of 102,000 square feet of 3" Asphalt, to replace with 102,000 square feet of new Portland Cement Concrete (PCC). This will also include slab replacement of adjoining hot brake pad and joint seal repair. In phase two, the vendor will reconstruct sections T12A and T13A1 of Taxiway Delta. The reconstruction of Taxiway Delta includes the reconstruction of 25,000 square feet of PCC in section T13A1, slab replacement, and joint seal repair. Additionally, 75,000 square feet of 4" Asphalt shall be removed and replaced with PCC in section T12A.
Taxiways Mike and Delta are located on the same airfield of CAFB, NM. Taxiway Delta covers 100,000 square feet and Taxiway Mike covers 102,000 square feet. Stemming from a 2015 Pavement Condition Index (PCI) Report, it was determined that sections of Taxiways Mike and Delta are in need of repair.
Files
Show all 28
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Repair Taxiway Mike & Delta | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| FA8501-27-rapid-pave-OTA | Air Force Sustainment Center | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity