Attachment 2 - SOMs Twy Mike Delta Material Register 14 April 2021.xlsx
XLSX spreadsheet 409 KB Posted
- Attached to
- Repair Taxiway Mike & Delta
- Solicitation number
- FA4855-21-R-0008
About this file
This submittal register outlines 294 required submittals for the Repair Taxiway Mike & Delta project at Cannon Air Force Base in New Mexico. The project has two phases - phase one involves reconstructing 102,000 square feet of Taxiway Mike with new Portland cement concrete, including slab replacement and joint seal repair. Phase two reconstructs sections of Taxiway Delta, removing and replacing 75,000 square feet of asphalt with concrete and performing additional slab replacement and joint seal repair. The submittals cover preconstruction, product data, shop drawings, samples, design data, test reports, certificates, manufacturer instructions, and closeout documentation for construction activities including excavation, concrete, asphalt, lighting, signage, and erosion control. The Department of the Air Force Special Operations Command is the contracting agency.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
Prepared By:
Blair Remy Architects Mead & Hunt 7 S. Mickey Mantle Drive 2440 Deming Way JDM Place, Suite 350 Middleton, WI 53562 Oklahoma City, OK 73104
| 0 | |||||||||||||||||||
| TITLE: | SUBMITTAL REGISTER - 100% SUBMITTAL | SUBMITTAL REGISTER | |||||||||||||||||
| JOB NAME: | RECONSTRUCT TAXIWAY M | ||||||||||||||||||
| LOCATION: | CANNON AFB, NEW MEXICO | ||||||||||||||||||
| CONTRACT NO: | |||||||||||||||||||
| CONTRACTOR: | |||||||||||||||||||
| CONTRACTOR SCHEDULE | |||||||||||||||||||
| DATES | CONTRACTOR | ||||||||||||||||||
| ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
Line Acti vity # Trans mittal # Specification Section SD # Submittal Description Item Submitted Paragraph # Classification: GOVT or A/E Reviewer Submit Approval Needed By Material Needed By Action Code Date Of Action Date FWD to APPR / Auth Date RCD From CONTR Date FWD To Other Revwr Date RCD From Other Reviewer Action Code Date Of Action Mailed To CONTR/ Date RCD
| From APPR Authority | Remarks | |||||||
| 1 | 01 11 00 | 1 | Preconstruction Submittals | Salvage Plan | 1.6 | G | ||
| 2 | 01 14 00 | 1 | Preconstruction Submittals | List of Contact Personnel | 1.4.1.1 | G | ||
| 3 | 01 14 00 | 1 | Preconstruction Submittals | Personnel List | 1.4.1.1 | G | ||
| 4 | 01 14 00 | 1 | Preconstruction Submittals | Vehicle List | 1.4.1.1 | |||
| 5 | 01 30 00 | 1 | Preconstruction Submittals | View Location Map | 1.3 | G | ||
| 6 | 01 30 00 | 1 | Preconstruction Submittals | Progress and Completion Pictures | 1.4 | G | ||
| 7 | 01 30 00 | 1 | Preconstruction Submittals | AF 833 | 1.4 | G | ||
| 8 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Project Scheduler Qualifications | 1.3 | G | ||
| 9 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Preliminary Project Schedule | 3.4.1 | G | ||
| 10 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Initial Project Schedule | 3.4.2 | G | ||
| 11 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Periodic Schedule Update | 3.6.2 | G | ||
| 12 | 01 33 00 | 1 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||
| 13 | 01 35 13 | 1 | Preconstruction Submittals | Heavy Equipment and Vehicle List | 3.1.2 | |||
| 14 | 01 35 13 | 1 | Preconstruction Submittals | Existing Conditions Survey | 3.1.2 | |||
| 15 | 01 35 13 | 1 | Preconstruction Submittals | Construction Operations Plan | 3.1.2 | |||
| 16 | 01 35 13 | 1 | Preconstruction Submittals | Safety Plan | 3.1.2 | |||
| 17 | 01 35 13 | 1 | Preconstruction Submittals | Schedule of Work | 3.1.2 | |||
| 18 | 01 35 13 | 1 | Preconstruction Submittals | Form Faa 7460-1 Notice Of Proposed Construction Or Alteration | 3.1.1 | G | ||
| 19 | 01 35 13 | 1 | Preconstruction Submittals | Form Faa 7460-1 Notice Of Proposed Construction Or Alteration | 3.1.2 | G | ||
| 20 | 01 35 26 | 1 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7 | G | ||
| 21 | 01 35 26 | 6 | Test Reports | Monthly Exposure Reports | 1.4 | |||
| 22 | 01 35 26 | 6 | Test Reports | Notifications and Reports | 1.12 | |||
| 23 | 01 35 26 | 6 | Test Reports | Accident Reports | 1.12.2 | G | ||
| 24 | 01 35 26 | 6 | Test Reports | LHE Inspection Reports | 1.12.3 | |||
| 25 | 01 35 26 | 7 | Certificates | Crane Operators/Riggers | 1.6.1.4 | |||
| 26 | 01 35 26 | 7 | Certificates | Standard Lift Plan | 1.7.2.2 | G | ||
| 27 | 01 35 26 | 7 | Certificates | Critical Lift Plan | 1.7.2.3 | G | ||
| 28 | 01 35 26 | 7 | Certificates | Activity Hazard Analysis (AHA) | 1.8 | |||
| 29 | 01 35 26 | 7 | Certificates | Confined Space Entry Permit | 1.9.1 | |||
| 30 | 01 35 26 | 7 | Certificates | Hot Work Permit | 1.9.1 | |||
| 31 | 01 35 26 | 7 | Certificates | Certificate of Compliance | 1.12.4 | |||
| 32 | 01 35 26 | 7 | Certificates | License Certificates | 1.14 | |||
| 33 | 01 35 26 | 7 | Certificates | Radiography Operation Planning Work | ||||
| Sheet | 1.14.1 | G | ||||||
| 34 | 01 35 26 | 7 | Certificates | Portable Gauge Operations Planning | ||||
| Worksheet | 1.14.1 | G | ||||||
| 35 | 01 45 00.00 10 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||
| 36 | 01 45 00.00 10 | 1 | Preconstruction Submittals | CQC System Manager And Alternate | ||||
| Qualifications | 3.4.2 | G | ||||||
| 37 | 01 45 00.00 10 | 6 | Test Reports | Verification Statement | 3.9.2 | |||
| 38 | 01 50 00 | 1 | Preconstruction Submittals | Construction Site Plan | 1.3 | G | ||
| 39 | 01 50 00 | 1 | Preconstruction Submittals | Traffic Control Plan | 3.4.1 | G | ||
| 40 | 01 50 00 | 1 | Preconstruction Submittals | Haul Road Plan | 2.2.1 | G | ||
| 41 | 01 50 00 | 1 | Preconstruction Submittals | Contractor Computer Cybersecurity Compliance Statements | 1.6.1.4 | G | ||
| 42 | 01 50 00 | 1 | Preconstruction Submittals | Contractor Temporary Network Cybersecurity Compliance Statements | 1.6.6 | G | ||
| 43 | 01 50 00 | 6 | Test Reports | Backflow Preventer Tests | 2.4 | |||
| 44 | 01 50 00 | 7 | Certificates | Backflow Tester | 1.4.1 | |||
| 45 | 01 50 00 | 7 | Certificates | Backflow Preventers | 1.4 | |||
| 46 | 01 57 19 | 1 | Preconstruction Submittals | Preconstruction Survey | 1.7.3 | |||
| 47 | 01 57 19 | 1 | Preconstruction Submittals | Preconstruction Survey | 1.8.1 | |||
| 48 | 01 57 19 | 1 | Preconstruction Submittals | Environmental Protection Plan | 1.9 | G | ||
| 49 | 01 57 19 | 1 | Preconstruction Submittals | Regulatory Notifications and Permits | 1.7.2 | |||
| 50 | 01 57 19 | 6 | Test Reports | Inspection Reports | 3.4.1 | G | ||
| 51 | 01 57 19 | 6 | Test Reports | Solid Waste Management Report | 1.9.3.6.1 | G | ||
| 52 | 01 57 19 | 6 | Test Reports | Waste Determination For All Waste | ||||
| Streams | 1.9.3.6.3 | G CEIE | ||||||
| 53 | 01 57 19 | 7 | Certificates | Employee Training Records | 1.6 | G | ||
| 54 | 01 57 19 | 7 | Certificates | Employee Training Records | 1.8.2 | G | ||
| 55 | 01 57 19 | 7 | Certificates | Erosion and Sediment Control | ||||
| Inspector | 1.8.2 | |||||||
| 56 | 01 57 19 | 7 | Certificates | Erosion and Sediment Control | ||||
| Inspector | 3.4.1 | |||||||
| 57 | 01 57 19 | 7 | Certificates | Contractor Certification | 1.9.3.6 | G CEIE | ||
| 58 | 01 57 19 | 7 | Certificates | Certificates Of Competency | 1.9.2 | G | ||
| 59 | 01 57 19 | 11 | Closeout Submittals | Regulatory Notifications/Permits | 1.7.2 | G CEIE | ||
| 60 | 01 57 19 | 11 | Closeout Submittals | Erosion Control Plan Compliance Notebook | 3.4.5 | G CEIE | ||
| 61 | 01 57 19 | 11 | Closeout Submittals | Assembled Employee Training | ||||
| Records | 1.8.2 | G | ||||||
| 62 | 01 57 19 | 11 | Closeout Submittals | Monthly Hazardous Material Usage | ||||
| Totals | 3.6 | G CEIE | ||||||
| 63 | 01 57 19 | 11 | Closeout Submittals | Solid Waste Management Report | 1.9.3.6.1 | G CEIE | ||
| 64 | 01 57 19 | 11 | Closeout Submittals | As-Built Topographic Survey | 3.4.5 | G CEIE | ||
| 65 | 01 74 19 | 1 | Preconstruction Submittals | Construction Waste Management Plan | 1.7 | G | ||
| 66 | 01 74 19 | 6 | Test Reports | Quarterly Reports | 1.9.2 | |||
| 67 | 01 74 19 | 6 | Test Reports | Annual Report | 1.9.3 | |||
| 68 | 01 74 19 | 11 | Closeout Submittals | Final Construction Waste Diversion | ||||
| Report | 1.1 | S | ||||||
| 69 | 01 78 00 | 3 | Product Data | Warranty Management Plan | 1.7.1 | |||
| 70 | 01 78 00 | 3 | Product Data | Warranty Tags | 1.7.4 | |||
| 71 | 01 78 00 | 3 | Product Data | Spare Parts Data | 1.6 | |||
| 72 | 01 78 00 | 8 | Manufacturer’s Instructions | Instructions | 1.7.1 | |||
| 73 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.3 | G | ||
| 74 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||
| 75 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.2 | G | ||
| 76 | 01 78 00 | 11 | Closeout Submittals | As-Built Record of Equipment and | ||||
| Materials | 1.7.1 | |||||||
| 77 | 01 78 00 | 11 | Closeout Submittals | Final Approved Shop Drawings | 3.2.4 | |||
| 78 | 01 78 00 | 11 | Closeout Submittals | Construction Contract Specifications | 3.2.5 | |||
| 79 | 01 78 00 | 11 | Closeout Submittals | Certification Of USDA Designated | ||||
| Items | 2.2 | G | ||||||
| 80 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.4 | G | ||
| 81 | 02 41 00 | 1 | Preconstruction Submittals | Demolition Plan | 1.2.1 | G | ||
| 82 | 02 41 00 | 1 | Preconstruction Submittals | Existing Conditions | 1.11 | |||
| 83 | 02 41 00 | 7 | Certificates | Notification | 1.7 | G | ||
| 84 | 03 30 53 | 2 | Shop Drawings | Installation Drawings | 1.4 | G | ||
| 85 | 03 30 53 | 3 | Product Data | Air-Entraining Admixture | 2.2.3.1 | |||
| 86 | 03 30 53 | 3 | Product Data | Water-Reducing or Retarding | ||||
| Admixture | 2.2.3.2 | |||||||
| 87 | 03 30 53 | 3 | Product Data | Curing Materials | 2.2.10 | |||
| 88 | 03 30 53 | 3 | Product Data | Expansion Joint Filler Strips, | ||||
| Premolded | 2.2.6 | |||||||
| 89 | 03 30 53 | 3 | Product Data | Joint Sealants - Field Molded Sealants | 2.2.7 | |||
| 90 | 03 30 53 | 3 | Product Data | Waterstops | 2.4.1 | |||
| 91 | 03 30 53 | 3 | Product Data | Batching and Mixing Equipment | 3.1.3.3 | |||
| 92 | 03 30 53 | 3 | Product Data | Conveying and Placing Concrete | 3.2 | |||
| 93 | 03 30 53 | 3 | Product Data | Formwork | 2.2.8 | |||
| 94 | 03 30 53 | 3 | Product Data | Mix Design Data | 2.3 | G | ||
| 95 | 03 30 53 | 3 | Product Data | Ready-Mix Concrete | 2.3 | |||
| 96 | 03 30 53 | 3 | Product Data | Curing Compound | 2.4.2 | |||
| 97 | 03 30 53 | 3 | Product Data | Mechanical Reinforcing Bar | ||||
| Connectors | 2.2.5 | |||||||
| 98 | 03 30 53 | 6 | Test Reports | Aggregates | 2.2.2 | |||
| 99 | 03 30 53 | 6 | Test Reports | Concrete Mixture Proportions | 2.1.3 | G | ||
| 100 | 03 30 53 | 6 | Test Reports | Compressive Strength Testing | 3.8.3 | G | ||
| 101 | 03 30 53 | 6 | Test Reports | Slump | 3.8.3 | G | ||
| 102 | 03 30 53 | 6 | Test Reports | Air Content | 3.8.3 | |||
| 103 | 03 30 53 | 6 | Test Reports | Water | 2.2.4 | |||
| 104 | 03 30 53 | 7 | Certificates | Cementitious Materials | 2.2.1 | |||
| 105 | 03 30 53 | 7 | Certificates | Pozzolan | 2.2.1.2 | |||
| 106 | 03 30 53 | 7 | Certificates | Aggregates | 2.2.2 | |||
| 107 | 03 30 53 | 7 | Certificates | Delivery Tickets | 2.3 | |||
| 108 | 03 30 53 | 8 | Manufacturer’s Instructions | Curing Compound | 2.4.2 | |||
| 109 | 26 56 20 | 1 | Preconstruction Submittals | Protection plan | 1.5.4 | G | ||
| 110 | 26 56 20 | 1 | Preconstruction Submittals | Training | 3.10.2 | G | ||
| 111 | 26 56 20 | 2 | Shop Drawings | Lighting and visual navigation aids | 2.1 | G | ||
| 112 | 26 56 20 | 2 | Shop Drawings | Posted instructions | 3.10.4 | G | ||
| 113 | 26 56 20 | 3 | Product Data | Type L-823 | 2.8.1.5 | G | ||
| 114 | 26 56 20 | 3 | Product Data | Runway edge lights | 2.2.1 | G | ||
| 115 | 26 56 20 | 3 | Product Data | Runway threshold and end lights | 2.2.2 | G | ||
| 116 | 26 56 20 | 3 | Product Data | Taxiway edge lights | 2.3.1 | G | ||
| 117 | 26 56 20 | 3 | Product Data | Runway hold position lights | 2.3.2 | G | ||
| 118 | 26 56 20 | 3 | Product Data | Light bases | 2.4 | G | ||
| 119 | 26 56 20 | 3 | Product Data | Isolation transformers | 2.7 | G | ||
| 120 | 26 56 20 | 3 | Product Data | Frangible couplings | 2.8.2.4 | G | ||
| 121 | 26 56 20 | 3 | Product Data | Materials and equipment | 1.5.2 | G | ||
| 122 | 26 56 20 | 6 | Test Reports | Visual inspection | 3.8 | G | ||
| 123 | 26 56 20 | 6 | Test Reports | Visual inspection | 3.8.1 | G | ||
| 124 | 26 56 20 | 6 | Test Reports | Progress testing for series lighting | ||||
| circuits | 3.8.4 | G | ||||||
| 125 | 26 56 20 | 6 | Test Reports | Counterpoise system test and | ||||
| inspection | 3.8.3 | G | ||||||
| 126 | 26 56 20 | 6 | Test Reports | Operating test | 3.8.2 | G | ||
| 127 | 26 56 20 | 6 | Test Reports | Electrical acceptance tests | 3.8.5 | G | ||
| 128 | 26 56 20 | 7 | Certificates | Qualifications of contractor | 1.5.3 | G | ||
| 129 | 26 56 20 | 7 | Certificates | Special tools | 2.9.1 | G | ||
| 130 | 26 56 20 | 7 | Certificates | Special tools | 3.10.2 | G | ||
| 131 | 26 56 20 | 7 | Certificates | 4-Jack positioning jig | 3.1.6 | G | ||
| 132 | 26 56 20 | 7 | Certificates | Elevated light level | 3.1.6.1 | G | ||
| 133 | 26 56 20 | 7 | Certificates | Crimping tool | 3.2.2.2 | G | ||
| 134 | 26 56 20 | 7 | Certificates | Cable penciler | 3.2.2.3 | |||
| 135 | 26 56 20 | 7 | Certificates | List of parts | 3.11.1 | G | ||
| 136 | 26 56 20 | 8 | Manufacturer’s Instructions | Posted instructions | 3.10.4 | G | ||
| 137 | 26 56 20 | 10 | Operation and Maintenance Data | Maintenance and repair instructions | 3.11.2 | G | ||
| 138 | 26 56 20 | 10 | Operation and Maintenance Data | Posted operations and maintenance | ||||
| instructions | 3.11.3 | |||||||
| 139 | 26 56 20 | 11 | Closeout Submittals | As-built drawings | 3.10.3 | |||
| 140 | 31 00 00 | 1 | Preconstruction Submittals | Shoring | 3.5 | G | ||
| 141 | 31 00 00 | 1 | Preconstruction Submittals | Dewatering Work Plan | 1.4.3 | G | ||
| 142 | 31 00 00 | 3 | Product Data | Utilization of Excavated Materials | 3.8 | G | ||
| 143 | 31 00 00 | 3 | Product Data | Shoulder Construction | 3.14 | |||
| 144 | 31 00 00 | 6 | Test Reports | Testing | 3.17 | |||
| 145 | 31 00 00 | 7 | Certificates | Testing | 3.17 | |||
| 146 | 32 01 11.51 | 1 | Preconstruction Submittals | Schedule of work | 1.2 | G | ||
| 147 | 32 01 11.51 | 1 | Preconstruction Submittals | Rubber and Paint Removal Process | ||||
| Plan | 3.1 | G | ||||||
| 148 | 32 01 11.51 | 1 | Preconstruction Submittals | Waste Collection, Identification and | ||||
| Disposal Plan | 3.4 | G | ||||||
| 149 | 32 01 11.51 | 3 | Product Data | Mechanical rubber and paint removal | ||||
| equipment | 1.4 | |||||||
| 150 | 32 01 11.51 | 3 | Product Data | Rubber and Paint Removal Detergents | ||||
| or Chemicals | 2.1 | G | ||||||
| 151 | 32 01 11.51 | 6 | Test Reports | Test Section Results | 1.5 | |||
| 152 | 32 01 16.71 | 1 | Preconstruction Submittals | Waste Collection, Identification And | ||||
| Disposal Plan | 1.3.2 | G | ||||||
| 153 | 32 01 16.71 | 1 | Preconstruction Submittals | Waste Collection, Identification And Disposal Plan | 1.3.2 | G | ||
| 154 | 32 01 16.71 | 3 | Product Data | Equipment | 1.3 | G | ||
| 155 | 32 01 19.61 | 3 | Product Data | Sealants | 2.1 | |||
| 156 | 32 01 19.61 | 3 | Product Data | Manufacturer's Recommendations | 3.5.2 | |||
| 157 | 32 01 19.61 | 4 | Samples | Sealants | 2.1 | |||
| 158 | 32 01 19.61 | 4 | Samples | Blocking Media/Backup Materials | 2.3.1 | |||
| 159 | 32 01 19.61 | 4 | Samples | Backer Rod | 3.3.4.1 | |||
| 160 | 32 01 19.61 | 4 | Samples | Bond Breaking Tapes | 2.3.2 | |||
| 161 | 32 01 19.61 | 6 | Test Reports | Sealants | 2.1 | |||
| 162 | 32 01 19.61 | 7 | Certificates | Equipment List | 3.1 | |||
| 163 | 32 01 19.61 | 8 | Manufacturer’s Instructions | Sealants | 2.1 | |||
| 164 | 32 01 29.61 | 2 | Shop Drawings | Shop Drawings | 1.3.3 | G | ||
| 165 | 32 01 29.61 | 3 | Product Data | Concrete Mix Design | 1.3.1 | G | ||
| 166 | 32 01 29.61 | 3 | Product Data | Concrete Mix Design | 2.1.4.1 | G | ||
| 167 | 32 01 29.61 | 3 | Product Data | Rigid Proprietary Repair Products | 2.1.10 | G | ||
| 168 | 32 01 29.61 | 3 | Product Data | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | G | ||||||
| 169 | 32 01 29.61 | 3 | Product Data | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | G | ||||||
| 170 | 32 01 29.61 | 3 | Product Data | Aggregate Service Record | 2.1.10.6 | |||
| 171 | 32 01 29.61 | 4 | Samples | Absorbent Curing Material | 3.5.1 | G | ||
| 172 | 32 01 29.61 | 4 | Samples | Joint Filler | 2.1.8 | G | ||
| 173 | 32 01 29.61 | 4 | Samples | Joint Sealant | 2.1.7 | G | ||
| 174 | 32 01 29.61 | 5 | Design Data | Concrete Mix Design | 1.3.1 | G | ||
| 175 | 32 01 29.61 | 5 | Design Data | Concrete Mix Design | 2.1.4.1 | G | ||
| 176 | 32 01 29.61 | 6 | Test Reports | Test Results | 1.3.1 | |||
| 177 | 32 01 29.61 | 6 | Test Reports | Gradation | 1.3.1.2 | |||
| 178 | 32 01 29.61 | 6 | Test Reports | Gradation | 2.1.1.4 | |||
| 179 | 32 01 29.61 | 6 | Test Reports | Cement | 1.3.1.1 | |||
| 180 | 32 01 29.61 | 6 | Test Reports | Slump | 2.1.4.1 | |||
| 181 | 32 01 29.61 | 6 | Test Reports | Air Content | 2.1.4.1 | |||
| 182 | 32 01 29.61 | 6 | Test Reports | Compressive Strength | 2.1.10.1 | |||
| 183 | 32 01 29.61 | 6 | Test Reports | Mixer Calibration and Efficiency | 1.3.2 | |||
| 184 | 32 01 29.61 | 6 | Test Reports | Concrete Uniformity | 1.3.2 | |||
| 185 | 32 01 29.61 | 6 | Test Reports | Bond Strength | 2.1.10.2 | |||
| 186 | 32 01 29.61 | 7 | Certificates | Cement | 1.3.1.1 | |||
| 187 | 32 01 29.61 | 7 | Certificates | Aggregate | 1.3.1.2 | |||
| 188 | 32 01 29.61 | 7 | Certificates | Admixtures | 2.1.3 | |||
| 189 | 32 01 29.61 | 7 | Certificates | Absorbent curing material | 3.5.1 | |||
| 190 | 32 01 29.61 | 7 | Certificates | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | |||||||
| 191 | 32 01 29.61 | 7 | Certificates | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | |||||||
| 192 | 32 01 29.61 | 7 | Certificates | Joint Filler | 2.1.8 | |||
| 193 | 32 01 29.61 | 7 | Certificates | Joint Sealant | 2.1.7 | |||
| 194 | 32 05 33 | 1 | Preconstruction Submittals | Integrated Pest Management Plan | 2.4 | G | ||
| 195 | 32 05 33 | 3 | Product Data | Fertilizer | 2.1 | G | ||
| 196 | 32 05 33 | 3 | Product Data | Mulches Topdressing | 2.3 | |||
| 197 | 32 05 33 | 3 | Product Data | Organic Mulch Materials | 2.3.1 | |||
| 198 | 32 05 33 | 7 | Certificates | Maintenance Inspection Report | 3.3.1 | |||
| 199 | 32 11 20 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||
| 200 | 32 11 20 | 6 | Test Reports | Initial Tests | 2.2.1 | G | ||
| 201 | 32 11 20 | 6 | Test Reports | In-Place Tests | 3.12.1 | G | ||
| 202 | 32 11 23 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||
| 203 | 32 11 23 | 3 | Product Data | Aggregate | 2.1 | G | ||
| 204 | 32 11 23 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||
| 205 | 32 11 23 | 6 | Test Reports | In-Place Tests | 3.13.1 | G | ||
| 206 | 32 11 23.23 | 3 | Product Data | Plants, Equipment, and Tools | 1.3.1 | G | ||
| 207 | 32 11 23.23 | 6 | Test Reports | Initial Tests | 1.4.3.1 | G | ||
| 208 | 32 11 23.23 | 6 | Test Reports | In-Place Tests | 1.4.3.2 | G | ||
| 209 | 32 11 23.23 | 6 | Test Reports | Test Section Construction Report | 3.6.7 | |||
| 210 | 32 11 36.13 | 5 | Design Data | Mix Design | 2.1 | |||
| 211 | 32 11 36.13 | 6 | Test Reports | Mix Design Review | 1.5.2 | |||
| 212 | 32 11 36.13 | 6 | Test Reports | Aggregate Testing | 3.7.2.1 | |||
| 213 | 32 11 36.13 | 6 | Test Reports | Slump | 3.7.2.2 | |||
| 214 | 32 11 36.13 | 6 | Test Reports | Air Content | 3.7.2.2 | |||
| 215 | 32 11 36.13 | 6 | Test Reports | Concrete Temperature | 3.7.2.2 | |||
| 216 | 32 11 36.13 | 6 | Test Reports | Yield | 3.7.2.2 | |||
| 217 | 32 11 36.13 | 6 | Test Reports | Compressive Strength | 3.7.2.2 | |||
| 218 | 32 11 36.13 | 7 | Certificates | Ready-mix Concrete Plant | 1.5.1 | |||
| 219 | 32 11 36.13 | 7 | Certificates | Batch Ticket Information | 1.5.1 | |||
| 220 | 32 11 36.13 | 7 | Certificates | Cement | 2.2.1 | |||
| 221 | 32 11 36.13 | 7 | Certificates | Aggregates | 2.2.3 | |||
| 222 | 32 11 36.13 | 7 | Certificates | Admixtures | 2.2.4 | |||
| 223 | 32 11 36.13 | 7 | Certificates | Curing Materials | 2.2.5 | |||
| 224 | 32 12 13 | 3 | Product Data | Local/Regional Materials | 2.2.3 | |||
| 225 | 32 12 13 | 6 | Test Reports | Sampling and Testing | 3.7 | |||
| 226 | 32 12 15.13 | 2 | Shop Drawings | Placement Plan | 2.1 | G | ||
| 227 | 32 12 15.13 | 3 | Product Data | Diamond Grinding Plan | 2.1.6 | G | ||
| 228 | 32 12 15.13 | 3 | Product Data | Mix Design | 2.4 | G | ||
| 229 | 32 12 15.13 | 3 | Product Data | Contractor Quality Control | 3.1 | G | ||
| 230 | 32 12 15.13 | 4 | Samples | Aggregates | 2.2 | |||
| 231 | 32 12 15.13 | 4 | Samples | Asphalt Cement Binder | 2.3 | |||
| 232 | 32 12 15.13 | 6 | Test Reports | Aggregates | 2.2 | G | ||
| 233 | 32 12 15.13 | 6 | Test Reports | QC Monitoring | 3.1.3.10 | |||
| 234 | 32 12 15.13 | 7 | Certificates | Asphalt Cement Binder | 2.3 | G | ||
| 235 | 32 12 15.13 | 7 | Certificates | Testing Laboratory | 3.7 | |||
| 236 | 32 13 14.13 | 3 | Product Data | Diamond Grinding Plan | 2.1.7 | G | ||
| 237 | 32 13 14.13 | 3 | Product Data | Dowels | 2.9.1 | G | ||
| 238 | 32 13 14.13 | 3 | Product Data | Dowel Bar Assemblies | 2.9.2 | G | ||
| 239 | 32 13 14.13 | 3 | Product Data | Equipment | 2.11 | |||
| 240 | 32 13 14.13 | 3 | Product Data | Proposed Techniques | 3.1.2 | G | ||
| 241 | 32 13 14.13 | 3 | Product Data | Aggregates | 1.4.4.1 | G | ||
| 242 | 32 13 14.13 | 5 | Design Data | Preliminary Proposed Proportioning | 2.13.2 | G DO | ||
| 243 | 32 13 14.13 | 5 | Design Data | Proportioning Studies | 2.13.2 | G | ||
| 244 | 32 13 14.13 | 6 | Test Reports | Batch Plant Manufacturer's Inspection | ||||
| Report | 1.4.1 | G | ||||||
| 245 | 32 13 14.13 | 6 | Test Reports | Slipform Paver Manufacturer's Inspection Report | 1.4.1 | G | ||
| 246 | 32 13 14.13 | 6 | Test Reports | Sampling and Testing | 2.1.4.1 | G | ||
| 247 | 32 13 14.13 | 6 | Test Reports | Diamond Grinding of PCC Surfaces | 2.1.7 | G | ||
| 248 | 32 13 14.13 | 6 | Test Reports | Mixer Performance (Uniformity) | ||||
| Testing | 2.11.2.3 | G | ||||||
| 249 | 32 13 14.13 | 6 | Test Reports | Repair Recommendations Plan | 3.9.1 | G | ||
| 250 | 32 13 14.13 | 7 | Certificates | Contractor Quality Control Staff | 1.4.1 | G | ||
| 251 | 32 13 14.13 | 7 | Certificates | Laboratory Accreditation and | ||||
| Validation | 1.4.3 | |||||||
| 252 | 32 13 14.13 | 7 | Certificates | Commercial Laboratory | 1.4.3.3 | G | ||
| 253 | 32 13 14.13 | 7 | Certificates | NRMCA Certificate of Conformance | 2.11 | |||
| 254 | 32 17 23 | 3 | Product Data | Surface Preparation Equipment List | 2.1.1.2 | G | ||
| 255 | 32 17 23 | 3 | Product Data | Application Equipment List | 2.1.2 | G | ||
| 256 | 32 17 23 | 3 | Product Data | Exterior Surface Preparation | 3.2 | |||
| 257 | 32 17 23 | 3 | Product Data | Safety Data Sheets | 1.3.1 | G | ||
| 258 | 32 17 23 | 3 | Product Data | Reflective media for airfields | 2.2.2.1 | G | ||
| 259 | 32 17 23 | 6 | Test Reports | Reflective Media for Airfields | 2.2.2.1 | G | ||
| 260 | 32 17 23 | 6 | Test Reports | Waterborne Paint | 2.2.1 | G | ||
| 261 | 32 17 23 | 6 | Test Reports | Test Reports | 3.4.1 | |||
| 262 | 32 17 23 | 7 | Certificates | Qualifications | 1.3.2 | G | ||
| 263 | 32 17 23 | 7 | Certificates | Reflective Media for Airfields | 2.2.2.1 | |||
| 264 | 32 17 23 | 7 | Certificates | Waterborne Paint | 2.2.1 | |||
| 265 | 32 17 23 | 7 | Certificates | Volatile Organic Compound | 1.3.1 | G | ||
| 266 | 32 17 23 | 8 | Manufacturer’s Instructions | Waterborne Paint | 2.2.1 | G | ||
| 267 | 32 92 19 | 3 | Product Data | Wood Cellulose Fiber Mulch | 2.5.1 | |||
| 268 | 32 92 19 | 3 | Product Data | Fertilizer | 2.4 | |||
| 269 | 32 92 19 | 6 | Test Reports | Topsoil Composition Tests | 2.2.3 | |||
| 270 | 32 92 19 | 7 | Certificates | Seed | 2.1 | |||
| 271 | 32 92 19 | 8 | Manufacturer’s Instructions | Erosion Control Materials | 2.7 | |||
| 272 | 33 40 00 | 4 | Samples | Pipe for Culverts and Storm Drains | 2.1 | |||
| 273 | 33 40 00 | 7 | Certificates | Hydrostatic Test on Watertight Joints | 3.8.1.1 | |||
| 274 | 33 40 00 | 7 | Certificates | Determination of Density | 3.8.1.2 | |||
| 275 | 33 40 00 | 7 | Certificates | Frame and Cover for Gratings | 2.3.4 | |||
| 276 | 33 40 00 | 7 | Certificates | Post-Installation Inspection Report | 3.8.2.1.2 | |||
| 277 | 33 40 00 | 7 | Certificates | Placing Pipe | 3.3 | |||
| 278 | 33 46 16 | 3 | Product Data | Aggregates | 2.3 | G | ||
| 279 | 33 46 16 | 3 | Product Data | Manhole Frames And Covers | 2.2 | G | ||
| 280 | 33 46 16 | 4 | Samples | Geotextile | 2.2 | |||
| 281 | 33 46 16 | 4 | Samples | Pipe and Pipe Fittings | 2.1 | |||
| 282 | 33 46 16 | 7 | Certificates | Geotextile | 2.2 | |||
| 283 | 33 46 16 | 7 | Certificates | Pipe and Pipe Fittings | 2.1 | |||
| 284 | 33 71 02 | 2 | Shop Drawings | Precast underground structures | 1.4.1 | G | ||
| 285 | 33 71 02 | 3 | Product Data | Precast concrete structures | 2.6.2.1 | G | ||
| 286 | 33 71 02 | 3 | Product Data | Sealing Material | 2.6.2.4 | |||
| 287 | 33 71 02 | 3 | Product Data | Pulling-In Irons | 3.3.3 | |||
| 288 | 33 71 02 | 3 | Product Data | Manhole frames and covers | 2.6.3 | G | ||
| 289 | 33 71 02 | 3 | Product Data | Handhole frames and covers | 2.6.4 | G | ||
| 290 | 33 71 02 | 3 | Product Data | Frames and Covers for Airfield | ||||
| Facilities | 2.6.5 | G | ||||||
| 291 | 33 71 02 | 3 | Product Data | Ductile Iron Frames and Covers for | ||||
| Airfield Facilities | 2.6.6 | |||||||
| 292 | 33 71 02 | 3 | Product Data | Cable supports | 2.7 | G | ||
| 293 | 33 71 02 | 6 | Test Reports | Field Acceptance Checks and Tests | 3.10.1 | G | ||
| 294 | 33 71 02 | 7 | Certificates | Cable Installer Qualifications | 1.4.2 | G | ||
| Prepared for: |
AIR FORCE CIVIL ENGINEER CENTER
27 SOCONS/CC
110 E ALISON AVE, BLDG 600 CANNON AFB, NM 88103-5321
Prepared By:
Reconstruct Taxiway M
Cannon Air Force Base, New Mexico Project No.: 1070402
Sheet1
| TITLE: | SUBMITTAL REGISTER | SUBMITTAL REGISTER | |||||||||||||||||
| JOB NAME: | RECONSTRUCT TAXIWAY Mike and Delta | ||||||||||||||||||
| LOCATION: | CANNON AFB, NEW MEXICO | ||||||||||||||||||
| CONTRACT NO: | |||||||||||||||||||
| CONTRACTOR: | |||||||||||||||||||
| CONTRACTOR SCHEDULE | |||||||||||||||||||
| DATES | CONTRACTOR | ||||||||||||||||||
| ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
Line Acti vity # Trans mittal # Specification Section SD # Submittal Description Item Submitted Paragraph # Classification: GOVT or A/E Reviewer Submit Approval Needed By Material Needed By Action Code Date Of Action Date FWD to APPR / Auth Date RCD From CONTR Date FWD To Other Revwr Date RCD From Other Reviewer Action Code Date Of Action Mailed To CONTR/ Date RCD
| From APPR Authority | Remarks | |||||||
| 1 | 01 11 00 | 1 | Preconstruction Submittals | Salvage Plan | 1.6 | G | ||
| 2 | 01 14 00 | 1 | Preconstruction Submittals | List of Contact Personnel | 1.4.1.1 (Mike Specs)/1.3.1(Delta Specs) | G | ||
| 3 | 01 14 00 | 1 | Preconstruction Submittals | Personnel List | 1.4.1.1(M) | G | ||
| 5 | 01 30 00 | 1 | Preconstruction Submittals | View Location Map | 1.3 | G | ||
| 6 | 01 30 00 | 1 | Preconstruction Submittals | Progress and Completion Pictures | 1.4 | G | ||
| 7 | 01 30 00 | 1 | Preconstruction Submittals | AF 833 | 1.4(M) | G | ||
| 9 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Preliminary Project Schedule | 3.4.1 | G | ||
| 10 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Initial Project Schedule | 3.4.2 | G | ||
| 11 | 01 32 01.00 10 | 1 | Preconstruction Submittals | Periodic Schedule Update | 3.6.2 | G | ||
| 12 | 01 33 00 | 1 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||
| 13 | 01 35 13 | 1 | Preconstruction Submittals | Heavy Equipment and Vehicle List | 3.1.2 | |||
| 14 | 01 35 13 | 1 | Preconstruction Submittals | Existing Conditions Survey | 3.1.2 | |||
| 15 | 01 35 13 | 1 | Preconstruction Submittals | Construction Operations Plan | 3.1.2 | |||
| 16 | 01 35 13 | 1 | Preconstruction Submittals | Safety Plan | 3.1.2 | |||
| 17 | 01 35 13 | 1 | Preconstruction Submittals | Schedule of Work | 3.1.2 | |||
| 18 | 01 35 13 | 1 | Preconstruction Submittals | Form Faa 7460-1 Notice Of Proposed Construction Or Alteration | 3.1.1 | G | ||
| 21 | 01 35 26 | 6 | Test Reports | Monthly Exposure Reports | 1.4 | |||
| 23 | 01 35 26 | 6 | Test Reports | Notification & Accident Reports | 1.12 | G | ||
| 24 | 01 35 26 | 6 | Test Reports | LHE (load handling equipment) Inspection Reports | 1.12.3 | |||
| 25 | 01 35 26 | 7 | Certificates | Crane Operators/Riggers | 1.6.1.4 | |||
| 26 | 01 35 26 | 7 | Certificates | Standard Lift Plan | 1.7.2.2 | G | ||
| 27 | 01 35 26 | 7 | Certificates | Critical Lift Plan | 1.7.2.3 | G | ||
| 28 | 01 35 26 | 7 | Certificates | Activity Hazard Analysis (AHA) | 1.7 (D) 1.8(M) | |||
| 29 | 01 35 26 | 7 | Certificates | Confined Space Entry Permit | 1.9.1(M) | |||
| 30 | 01 35 26 | 7 | Certificates | Hot Work Permit | 1.9.1(M)/1.8.1(D) | |||
| 31 | 01 35 26 | 7 | Certificates | Certificate of Compliance | 1.12.4(M)/1.11.4(D) | |||
| 32 | 01 35 26 | 7 | Certificates | License Certificates | 1.14 | |||
| 33 | 01 35 26 | 7 | Certificates | Radiography Operation Planning Work & Portable Gauge Operations Planning Worksheet | ||||
| Sheet | 1.14.1 | G | ||||||
| 34 | 01 45 00.00 10 | 1 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 3.2 | G | ||
| 35 | 01 45 00.00 10 | 1 | Preconstruction Submittals | CQC System Manager And Alternate | ||||
| Qualifications | 3.4.2 | G | ||||||
| 36 | 01 45 00.00 10 | 6 | Test Reports | Verification Statement | 3.9.2 | |||
| 37 | 01 50 00 | 1 | Preconstruction Submittals | Construction Site Plan | 1.3 | G | ||
| 38 | 01 50 00 | 1 | Preconstruction Submittals | Traffic Control Plan | 3.4.1 | G | ||
| 39 | 01 50 00 | 1 | Preconstruction Submittals | Haul Road Plan | 2.2.1 | G | ||
| 42 | 01 50 00 | 6 | Test Reports | Backflow Preventer Tests | 2.4 | |||
| 43 | 01 50 00 | 7 | Certificates | Backflow Tester | 1.4.1 | |||
| 44 | 01 50 00 | 7 | Certificates | Backflow Preventers | 1.4 | |||
| 45 | 01 57 19 | 1 | Preconstruction Submittals | Preconstruction Survey | 1.7.3 | |||
| 46 | 01 57 19 | 1 | Preconstruction Submittals | Environmental Protection Plan | 1.9(M)/1.8(D) | G | ||
| 47 | 01 57 19 | 1 | Preconstruction Submittals | Regulatory Notifications and Permits | 1.7.2 | |||
| 48 | 01 57 19 | 6 | Test Reports | Inspection Reports | 3.4.1(M)/3.2.1.3(D) | G | ||
| 49 | 01 57 19 | 6 | Test Reports | Solid Waste Management Report | 1.9.3.6.1(M)/1.11(D) | G | ||
| 50 | 01 57 19 | 6 | Test Reports | Waste Determination For All Waste | ||||
| Streams | 1.9.3.6.3 | G CEIE | ||||||
| 51 | 01 57 19 | 7 | Certificates | Employee Training Records | 1.6.5 | G | ||
| 52 | 01 57 19 | 7 | Certificates/Plans | Erosion and Sediment Control Plan & |
Inspector
| 53 | 01 57 19 | 7 | Certificates | Certificates Of Competency | 1.9.2 | G | ||
| 54 | 01 57 19 | 11 | Closeout Submittals | Regulatory Notifications/Permits | 1.7.2 | G CEIE | ||
| 55 | 01 57 19 | 11 | Closeout Submittals | Erosion Control Plan Compliance Notebook | 3.4.5 | G CEIE | ||
| 56 | 01 57 19 | 11 | Closeout Submittals | Assembled Employee Training | ||||
| Records | 1.8.2 | G | ||||||
| 57 | 01 57 19 | 11 | Closeout Submittals | Monthly Hazardous Material Usage | ||||
| Totals | 3.6 | G CEIE | ||||||
| 58 | 01 57 19 | 11 | Closeout Submittals | Solid Waste Management Report | 1.9.3.6.1 | G CEIE | ||
| 59 | 01 57 19 | 11 | Closeout Submittals | As-Built Topographic Survey | 3.4.5 | G CEIE | ||
| 60 | 01 58 00 | 02 | Shop Drawings | Preliminary One Line | (Delta Specs) | G | ||
| 61 | 01 74 19 | 1 | Preconstruction Submittals | Construction Waste Management Plan | 1.7(M)/1.5(D) | G | ||
| 62 | 01 74 19 | 6 | Test Reports | Quarterly Reports | 1.9.2 | |||
| 63 | 01 74 19 | 6 | Test Reports | Annual Report | 1.9.3 | |||
| 64 | 01 74 19 | 11 | Closeout Submittals | Final Construction Waste Diversion | ||||
| Report/Disposal Documentation Haz Waste/Debris | 1.7.1(M) | S | ||||||
| 65 | 01 78 00 | 3 | Product Data | Warranty Management Plan | ||||
| 67 | 01 78 00 | 3 | Product Data | Spare Parts Data | ||||
| 69 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.3 | G | ||
| 70 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||
| 71 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.2 | G | ||
| 74 | 01 78 00 | 11 | Closeout Submittals | Construction Contract Specifications | 3.2.5 | |||
| 75 | 01 78 00 | 11 | Closeout Submittals | Certification Of USDA Designated | ||||
| Items | 2.2 | G | ||||||
| 77 | 02 41 00 | 1 | Preconstruction Submittals | Demolition Plan | 1.2.1 | G | ||
| 78 | 02 41 00 | 1 | Preconstruction Submittals | Existing Conditions | 1.11 | |||
| 79 | 02 41 00 | 7 | Certificates | Notification of Demo Projects | 1.7(M) | G | ||
| 80 | 03 30 53 | 3 | Product Data | Air-Entraining Admixture | 2.2.3.1 | |||
| 81 | 03 30 53 | 3 | Product Data | Water-Reducing or Retarding | ||||
| Admixture | 2.2.3.2 | |||||||
| 82 | 03 30 53 | 3 | Product Data | Curing Materials | 2.2.10 | |||
| 83 | 03 30 53 | 3 | Product Data | Expansion Joint Filler Strips, | ||||
| Premolded | 2.2.6 | |||||||
| 84 | 03 30 53 | 3 | Product Data | Joint Sealants - Field Molded Sealants | 2.2.7 | |||
| 85 | 03 30 53 | 3 | Product Data | Waterstops | 2.4.1 | |||
| 86 | 03 30 53 | 3 | Product Data | Batching and Mixing Equipment | 3.1.3.3 | |||
| 87 | 03 30 53 | 3 | Product Data | Conveying and Placing Concrete | 3.2 | |||
| 88 | 03 30 53 | 3 | Product Data | Formwork | 2.2.8 | |||
| 89 | 03 30 53 | 3 | Product Data | Ready-Mix Concrete | 2.3 | |||
| 90 | 03 30 53 | 3 | Product Data | Curing Compound | 2.4.2 | |||
| 91 | 03 30 53 | 3 | Product Data | Mechanical Reinforcing Bar | ||||
| Connectors | 2.2.5 | |||||||
| 92 | 03 30 53 | 6 | Test Reports | Aggregates | 2.2.2 | |||
| 93 | 03 30 53 | 6 | Test Reports | Concrete Mixture Proportions | 2.1.3 | G | ||
| 94 | 03 30 53 | 6 | Test Reports | Compressive Strength Testing | 3.8.3 | G | ||
| 95 | 03 30 53 | 6 | Test Reports | Slump | 3.8.3 | G | ||
| 96 | 03 30 53 | 6 | Test Reports | Air Content | 3.8.3 | |||
| 97 | 03 30 53 | 6 | Test Reports | Water | 2.2.4 | |||
| 98 | 03 30 53 | 7 | Certificates | Cementitious Materials | 2.2.1 | |||
| 99 | 03 30 53 | 7 | Certificates | Pozzolan | 2.2.1.2 | |||
| 100 | 03 30 53 | 7 | Certificates | Aggregates | 2.2.2 | |||
| 101 | 03 30 53 | 7 | Certificates | Delivery Tickets | 2.3 | |||
| 102 | 03 30 53 | 8 | Manufacturer’s Instructions | Curing Compound | 2.4.2 | |||
| 103 | 26 56 20 | 1 | Preconstruction Submittals | Protection plan | 1.5.4 | G | ||
| 104 | 26 56 20 | 1 | Preconstruction Submittals | Training | 3.10.2 | G | ||
| 105 | 26 56 20 | 2 | Shop Drawings | Lighting and visual navigation aids | 2.1 | G | ||
| 106 | 26 56 20 | 2 | Shop Drawings | Posted instructions | 3.10.4 | G | ||
| 107 | 26 56 20 | 3 | Product Data | Type L-823 | 2.8.1.5 | G | ||
| 108 | 26 56 20 | 3 | Product Data | Runway edge lights | 2.2.1 | G | ||
| 109 | 26 56 20 | 3 | Product Data | Runway threshold and end lights | 2.2.2 | G | ||
| 110 | 26 56 20 | 3 | Product Data | Taxiway edge lights | 2.3.1 | G | ||
| 111 | 26 56 20 | 3 | Product Data | Runway hold position lights | 2.3.2 | G | ||
| 112 | 26 56 20 | 3 | Product Data | Light bases | 2.4 | G | ||
| 113 | 26 56 20 | 3 | Product Data | Isolation transformers | 2.7 | G | ||
| 114 | 26 56 20 | 3 | Product Data | Frangible couplings | 2.8.2.4 | G | ||
| 115 | 26 56 20 | 6 | Test Reports | Visual inspection | 3.8 | G | ||
| 116 | 26 56 20 | 6 | Test Reports | Progress testing for series lighting | ||||
| circuits | 3.8.4 | G | ||||||
| 117 | 26 56 20 | 6 | Test Reports | Counterpoise system test and | ||||
| inspection | 3.8.3 | G | ||||||
| 118 | 26 56 20 | 6 | Test Reports | Operating test | 3.8.2 | G | ||
| 119 | 26 56 20 | 6 | Test Reports | Electrical acceptance tests | 3.8.5 | G | ||
| 120 | 26 56 20 | 7 | Certificates | Qualifications of contractor | 1.5.3 | G | ||
| 121 | 26 56 20 | 7 | Certificates | Special tools | 2.9.1 | G | ||
| 122 | 26 56 20 | 7 | Certificates | 4-Jack positioning jig | 3.1.6 | G | ||
| 123 | 26 56 20 | 7 | Certificates | Elevated light level | 3.1.6.1 | G | ||
| 124 | 26 56 20 | 7 | Certificates | Crimping tool | 3.2.2.2 | G | ||
| 125 | 26 56 20 | 7 | Certificates | Cable penciler | 3.2.2.3 | |||
| 126 | 26 56 20 | 7 | Certificates | List of parts | 3.11.1 | G | ||
| 127 | 26 56 20 | 10 | Operation and Maintenance Data | Maintenance and repair instructions | 3.11.2 | G | ||
| 128 | 26 56 20 | 10 | Operation and Maintenance Data | Posted operations and maintenance | ||||
| instructions | 3.11.3 | |||||||
| 129 | 26 56 20 | 11 | Closeout Submittals | As-built drawings | 3.10.3 | |||
| 130 | 31 00 00 | 1 | Preconstruction Submittals | Shoring Plan | 3.5 | G | ||
| 131 | 31 00 00 | 1 | Preconstruction Submittals | Dewatering Work Plan | 1.4.3 | G | ||
| 132 | 31 00 00 | 3 | Product Data | Utilization of Excavated Materials | 3.8 | G | ||
| 133 | 31 00 00 | 3 | Product Data | Shoulder Construction | 3.14 | |||
| 134 | 31 00 00 | 6 | Test Reports | Testing | 3.17 | |||
| 135 | 32 01 11.51 | 1 | Preconstruction Submittals | Schedule of Work/Phasing Plan | 1.2/3.1 | G | ||
| 136 | 32 01 11.51 | 1 | Preconstruction Submittals | Waste Collection, Identification and | ||||
| Disposal Plan | 3.4 | G | ||||||
| 137 | 32 01 11.51 | 3 | Product Data | Mechanical rubber and paint removal | ||||
| equipment | 1.4 | |||||||
| 138 | 32 01 11.51 | 3 | Product Data | Rubber and Paint Removal Detergents | ||||
| or Chemicals | 2.1 | G | ||||||
| 139 | 32 01 11.51 | 6 | Test Reports | Test Section of Removal Results | 1.5 | |||
| 140 | 32 01 16.71 | 1 | Preconstruction Submittals | Waste Collection, Identification And Disposal Plan | 1.3.2 | G | ||
| 141 | 32 01 16.71 | 3 | Product Data | Equipment | 1.3 | G | ||
| 142 | 32 01 19.61 | 3 | Product Data | Sealants | 2.1 | |||
| 143 | 32 01 19.61 | 3 | Product Data | Manufacturer's Recommendations | 3.5.2 | |||
| 144 | 32 01 19.61 | 4 | Samples | Blocking Media/Backup Materials | 2.3.1 | |||
| 145 | 32 01 19.61 | 4 | Samples | Backer Rod | 3.3.4.1 | |||
| 146 | 32 01 19.61 | 4 | Samples | Bond Breaking Tapes | 2.3.2 | |||
| 147 | 32 01 19.61 | 6 | Test Reports | Sealants | 2.1 | |||
| 148 | 32 01 19.61 | 7 | Certificates | Equipment List | 3.1 | |||
| 149 | 32 01 29.61 | 3 | Product Data | Concrete Mix Design | 1.3.1/2.1.4.1 | G | ||
| 150 | 32 01 29.61 | 3 | Product Data | Rigid Proprietary Repair Products | 2.1.10 | G | ||
| 151 | 32 01 29.61 | 3 | Product Data | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | G | ||||||
| 152 | 32 01 29.61 | 3 | Product Data | Aggregate Service Record | 2.1.10.6 | |||
| 153 | 32 01 29.61 | 4 | Samples | Absorbent Curing Material | 3.5.1 | G | ||
| 154 | 32 01 29.61 | 4 | Samples | Joint Filler | 2.1.8 | G | ||
| 155 | 32 01 29.61 | 4 | Samples | Joint Sealant | 2.1.7 | G | ||
| 156 | 32 01 29.61 | 5 | Design Data | Concrete Mix Design | 1.3.1/2.1.4.1 | G | ||
| 157 | 32 01 29.61 | 6 | Test Reports | Test Results | 1.3.1 | |||
| 158 | 32 01 29.61 | 6 | Test Reports | Gradation | 1.3.1.2 | |||
| 159 | 32 01 29.61 | 6 | Test Reports | Gradation | 2.1.1.4 | |||
| 160 | 32 01 29.61 | 6 | Test Reports | Cement | 1.3.1.1 | |||
| 161 | 32 01 29.61 | 6 | Test Reports | Slump | 2.1.4.1 | |||
| 162 | 32 01 29.61 | 6 | Test Reports | Air Content | 2.1.4.1 | |||
| 163 | 32 01 29.61 | 6 | Test Reports | Compressive Strength | 2.1.10.1 | |||
| 164 | 32 01 29.61 | 6 | Test Reports | Mixer Calibration and Efficiency | 1.3.2 | |||
| 165 | 32 01 29.61 | 6 | Test Reports | Concrete Uniformity | 1.3.2 | |||
| 166 | 32 01 29.61 | 6 | Test Reports | Bond Strength | 2.1.10.2 | |||
| 167 | 32 01 29.61 | 7 | Certificates | Cement | 1.3.1.1 | |||
| 168 | 32 01 29.61 | 7 | Certificates | Aggregate | 1.3.1.2 | |||
| 169 | 32 01 29.61 | 7 | Certificates | Admixtures | 2.1.3 | |||
| 170 | 32 01 29.61 | 7 | Certificates | Absorbent curing material | 3.5.1 | |||
| 171 | 32 01 29.61 | 7 | Certificates | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | |||||||
| 172 | 32 01 29.61 | 7 | Certificates | Pigmented Liquid Membrane-Forming | ||||
| Compound | 2.1.5.1 | |||||||
| 173 | 32 01 29.61 | 7 | Certificates | Joint Filler | 2.1.8 | |||
| 174 | 32 01 29.61 | 7 | Certificates | Joint Sealant | 2.1.7 | |||
| 175 | 32 05 33 | 1 | Preconstruction Submittals | Integrated Pest Management Plan | 2.4 | G | ||
| 176 | 32 05 33 | 3 | Product Data | Fertilizer | 2.1 | G | ||
| 177 | 32 05 33 | 3 | Product Data | Mulches Topdressing | 2.3 | |||
| 179 | 32 05 33 | 7 | Certificates | Maintenance Inspection Report | 3.3.1 | |||
| 180 | 32 11 20 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||
| 181 | 32 11 20 | 6 | Test Reports | Initial Tests | 2.2.1 | G | ||
| 182 | 32 11 20 | 6 | Test Reports | In-Place Tests | 3.12.1 | G | ||
| 183 | 32 11 23 | 3 | Product Data | Plant, Equipment, and Tools | 1.4 | G | ||
| 184 | 32 11 23 | 3 | Product Data | Aggregate | 2.1 | G | ||
| 185 | 32 11 23 | 6 | Test Reports | Initial Tests | 2.3.1 | G | ||
| 186 | 32 11 23 | 6 | Test Reports | In-Place Tests | 3.8/3.13.1 | G | ||
| 187 | 32 11 23.23 | 3 | Product Data | Plants, Equipment, and Tools | 1.3.1 | G | ||
| 188 | 32 11 23.23 | 6 | Test Reports | Initial Tests | 1.4.3.1 | G | ||
| 189 | 32 11 23.23 | 6 | Test Reports | In-Place Tests | 1.4.3.2 | G | ||
| 190 | 32 11 23.23 | 6 | Test Reports | Test Section Construction Report | 3.6.7 | |||
| 191 | 32 11 36.13 | 5 | Design Data | Mix Design | 2.1 | |||
| 192 | 32 11 36.13 | 6 | Test Reports | Mix Design Review | 1.5.2 | |||
| 193 | 32 11 36.13 | 6 | Test Reports | Aggregate Testing | 3.7.2.1 | |||
| 194 | 32 11 36.13 | 6 | Test Reports | Slump | 3.7.2.2 | |||
| 195 | 32 11 36.13 | 6 | Test Reports | Air Content | 3.7.2.2 | |||
| 196 | 32 11 36.13 | 6 | Test Reports | Concrete Temperature | 3.7.2.2 | |||
| 197 | 32 11 36.13 | 6 | Test Reports | Yield | 3.7.2.2 | |||
| 198 | 32 11 36.13 | 6 | Test Reports | Compressive Strength | 3.7.2.2 | |||
| 199 | 32 11 36.13 | 7 | Certificates | Ready-mix Concrete Plant | 1.5.1 | |||
| 200 | 32 11 36.13 | 7 | Certificates | Batch Ticket Information | 1.5.1 | |||
| 201 | 32 11 36.13 | 7 | Certificates | Cement | 2.2.1 | |||
| 202 | 32 11 36.13 | 7 | Certificates | Aggregates | 2.2.3 | |||
| 203 | 32 11 36.13 | 7 | Certificates | Admixtures | 2.2.4 | |||
| 204 | 32 11 36.13 | 7 | Certificates | Curing Materials | 2.2.5 | |||
| 205 | 32 12 13 | 3 | Product Data | Local/Regional Materials | 2.2.3 | |||
| 206 | 32 12 13 | 6 | Test Reports | Sampling and Testing | 3.7 | |||
| 207 | 32 12 15.13 | 2 | Shop Drawings | Placement Plan | 2.1 | G | ||
| 208 | 32 12 15.13 | 3 | Product Data | Diamond Grinding Plan | 2.1.6 | G | ||
| 209 | 32 12 15.13 | 3 | Product Data | Mix Design | 2.4 | G | ||
| 210 | 32 12 15.13 | 3 | Product Data | Contractor Quality Control | 3.1 | G | ||
| 211 | 32 12 15.13 | 6 | Test Reports | Aggregates | 2.2 | G | ||
| 212 | 32 12 15.13 | 6 | Test Reports | QC Monitoring Tests | 3.1.3.10 | |||
| 213 | 32 12 15.13 | 7 | Certificates | Asphalt Cement Binder | 2.3 | G | ||
| 214 | 32 12 15.13 | 7 | Certificates | Testing Laboratory | 3.7 | |||
| 215 | 32 12 36.13 | 3 | Product Data | Waybills and Delivery Tickets | 1.1.3 | |||
| 216 | 32 12 36.13 | 04 | Samples | Bituminous Materials | 1.5.2 | |||
| 217 | 32 12 36.13 | 04 | Samples | Fog Seal | 2.1 | G | ||
| 218 | 32 13 14.13 | 3 | Product Data | Diamond Grinding Plan | 2.1.7 | G | ||
| 219 | 32 13 14.13 | 3 | Product Data | Dowels | 2.9.1 | G | ||
| 220 | 32 13 14.13 | 3 | Product Data | Dowel Bar Assemblies | 2.9.2 | G | ||
| 221 | 32 13 14.13 | 3 | Product Data | Equipment | 2.11 | |||
| 222 | 32 13 14.13 | 3 | Product Data | Proposed Techniques | 3.1.2 | G | ||
| 223 | 32 13 14.13 | 3 | Product Data | Aggregates | 1.4.4.1 | G | ||
| 224 | 32 13 14.13 | 5 | Design Data | Proportioning Studies | 2.13.2 | G | ||
| 225 | 32 13 14.13 | 6 | Test Reports | Batch Plant Manufacturer's Inspection | ||||
| Report | 1.4.1 | G | ||||||
| 226 | 32 13 14.13 | 6 | Test Reports | Slipform Paver Manufacturer's Inspection Report | 1.4.1 | G | ||
| 227 | 32 13 14.13 | 6 | Test Reports | Sampling and Testing | 2.1.4.1 | G | ||
| 228 | 32 13 14.13 | 6 | Test Reports | Diamond Grinding of PCC Surfaces | 2.1.7 | G | ||
| 229 | 32 13 14.13 | 6 | Test Reports | Mixer Performance (Uniformity) | ||||
| Testing | 2.11.2.3 | G | ||||||
| 230 | 32 13 14.13 | 6 | Test Reports | Repair Recommendations Plan | 3.9.1 | G | ||
| 231 | 32 13 14.13 | 7 | Certificates | Contractor Quality Control Staff | 1.4.1 | G | ||
| 232 | 32 13 14.13 | 7 | Certificates | Laboratory Accreditation and | ||||
| Validation | 1.4.3 | |||||||
| 233 | 32 13 14.13 | 7 | Certificates | Commercial Laboratory | 1.4.3.3 | G | ||
| 234 | 32 13 14.13 | 7 | Certificates | NRMCA Certificate of Conformance | 2.11 | |||
| 235 | 32 13 14.13 | 7 | Certificates | Air Quality Permit | 2.11 | |||
| 236 | 32 17 23 | 3 | Product Data | Surface Preparation Equipment List | 2.1.1.2 | G | ||
| 237 | 32 17 23 | 3 | Product Data | Application Equipment List | 2.1.2 | G | ||
| 238 | 32 17 23 | 3 | Product Data | Exterior Surface Preparation | 3.2 | |||
| 239 | 32 17 23 | 3 | Product Data | Safety Data Sheets | 1.3.1 | G | ||
| 240 | 32 17 23 | 3 | Product Data | Reflective media for airfields | 2.2.2.1 | G | ||
| 241 | 32 17 23 | 6 | Test Reports | Reflective Media for Airfields | 2.2.2.1 | G | ||
| 242 | 32 17 23 | 6 | Test Reports | Waterborne Paint | 2.2.1 | G | ||
| 243 | 32 17 23 | 6 | Test Reports | Test Reports | 3.4.1 | |||
| 244 | 32 17 23 | 7 | Certificates | Qualifications | 1.3.2 | G | ||
| 245 | 32 17 23 | 8 | Manufacturer’s Instructions | Waterborne Paint | 2.2.1 | G | ||
| 246 | 32 92 19 | 3 | Product Data | Wood Cellulose Fiber Mulch | 2.5.1 | |||
| 247 | 32 92 19 | 3 | Product Data | Fertilizer | 2.4 | |||
| 248 | 32 92 19 | 6 | Test Reports | Topsoil Composition Tests | 2.2.3 | |||
| 249 | 32 92 19 | 7 | Certificates | Seed | 2.1 | |||
| 250 | 32 92 19 | 8 | Manufacturer’s Instructions | Erosion Control Materials | 2.7 | |||
| 251 | 33 40 00 | 4 | Samples | Pipe for Culverts and Storm Drains | 2.1 | |||
| 252 | 33 40 00 | 7 | Certificates | Hydrostatic Test on Watertight Joints | 3.8.1.1 | |||
| 253 | 33 40 00 | 7 | Certificates | Determination of Density | 3.8.1.2 | |||
| 254 | 33 40 00 | 7 | Certificates | Frame and Cover for Gratings | 2.3.4 | |||
| 255 | 33 40 00 | 7 | Certificates | Post-Installation Inspection Report | 3.8.2.1.2 | |||
| 256 | 33 40 00 | 7 | Certificates | Placing Pipe | 3.3 | |||
| 257 | 33 46 16 | 3 | Product Data | Aggregates | 2.3 | G | ||
| 258 | 33 46 16 | 3 | Product Data | Manhole Frames And Covers | 2.2 | G | ||
| 259 | 33 46 16 | 7 | Certificates | Geotextile | 2.2 | |||
| 260 | 33 46 16 | 7 | Certificates | Pipe and Pipe Fittings | 2.1 | |||
| 261 | 33 71 02 | 2 | Shop Drawings | Precast underground structures | 1.4.1 | G | ||
| 262 | 33 71 02 | 3 | Product Data | Precast concrete structures | 2.6.2.1 | G | ||
| 263 | 33 71 02 | 3 | Product Data | Sealing Material | 2.6.2.4 | |||
| 264 | 33 71 02 | 3 | Product Data | Pulling-In Irons | 3.3.3 | |||
| 265 | 33 71 02 | 3 | Product Data | Manhole frames and covers | 2.6.3 | G | ||
| 266 | 33 71 02 | 3 | Product Data | Handhole frames and covers | 2.6.4 | G | ||
| 267 | 33 71 02 | 3 | Product Data | Frames and Covers for Airfield | ||||
| Facilities | 2.6.5 | G | ||||||
| 268 | 33 71 02 | 3 | Product Data | Ductile Iron Frames and Covers for | ||||
| Airfield Facilities | 2.6.6 | |||||||
| 269 | 33 71 02 | 3 | Product Data | Cable supports | 2.7 | G | ||
| 270 | 33 71 02 | 6 | Test Reports | Field Acceptance Checks and Tests | 3.10.1 | G | ||
| 271 | 33 71 02 | 7 | Certificates | Cable Installer Qualifications | 1.4.2 | G |