Attachment 12 - Construction Cost Estimate.xls
XLS spreadsheet 724 KB Posted
- Attached to
- Repair Taxiway Mike & Delta
- Solicitation number
- FA4855-21-R-0008
About this file
This solicitation requests proposals for a single construction project involving repair of two taxiways at Cannon Air Force Base in New Mexico. The project has two phases involving reconstruction of sections of Taxiway Mike and Taxiway Delta. Phase one requires reconstruction of 102,000 square feet of Taxiway Mike, replacing asphalt with Portland cement concrete, including slab replacement and joint seal repair. Phase two requires reconstruction of 25,000 square feet of Taxiway Delta in one section and replacement of 75,000 square feet of asphalt with concrete in another section, along with additional slab replacement and joint seal repair. Both taxiways are located on the same airfield at Cannon Air Force Base. The solicitation was issued by the Department of the Air Force Special Operations Command stemming from needed repairs identified in a 2015 Pavement Condition Index Report.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Unit of Measure
| STANDARD OPERATING PROCEDURE FOR UNITS OF MEASUREMENT ON CONSTRUCTION CONTRACTS | |||
| # | ITEM | UNIT | REMARKS |
| 1 | Hydraulic Dredging - ED | CY | applies to all jobs originating in Engineering Division |
| 2 | Hopper Dredging - ED | CY | applies to all jobs originating in Engineering Division |
| 3 | Hydraulic Dredging - OD | HRS | applies to all jobs originating in Operations Division |
| 4 | Hopper Dredging - OD | HRS | applies to all jobs originating in Operations Division |
| 5 | Pile Dike | ||
| - Piles | LF | ||
| - Wales | LF | ||
| 6 | Guide Walls | ||
| - Piles | LF | ||
| - Guidewalls and Fenders | LS | ||
| - Wales, Thrust Blocks, Shear Blocks and Girts | LF | ||
| 7 | Dolphins - Sheet Piling | ||
| - Sheet Piling | SF | sheet pile is broken out separated from the rest of the dolphin | |
| - New Dolphin | LS | remaining features of work | |
| 8 | Rock / Stone | TONS | measured by barge displacement or truck measure |
| 9 | Bedding | CY | truck measure |
| TONS | barge displacement measurement | ||
| 10 | Surfacing | CY | truck measure |
| 11 | Geotextile | SY | in-place measurement |
| 12 | Pipe | LF | in-place measurement |
| 13 | Catch Basins and Manholes | EA | use separate items for different types |
| 14 | Dewatering | LS | contractor design |
| 15 | Structural Excavation | LS | specifications or drawings must delineate the quantity |
| 16 | Structural Backfill | LS | specifications or drawings must delineate the quantity |
| 17 | Channel Excavation | CY | measured by the end-area method |
| 18 | Canal Excavation | CY | truck measure |
| 19 | Clearing and Grubbing - Levee Work | ||
| - Levee Work | LS | undefined quantity based on borrow and to fill estimated for job | |
| - Misc. | n/a | less than $50,000 placed in job overhead | |
| 20 | Levee Embankments | CY | measured by the end-area method with settlement plates |
| 21 | Earthen Dikes | LS | contractor designed |
| 22 | Sheet Piles | SF | measured by projected area - length x depth |
| may be broken out into separate items for furnishing and driving | |||
| 23 | H-Piles | LF | may be broken out into separate items for furnishing and driving |
| 24 | Timber Piles | LF | may be broken out into separate items for furnishing and driving |
| 25 | Concrete Piles | LF | may be broken out into separate items for furnishing and driving |
| 26 | Temporary Sheet Piling | SF | when Corps designed |
| LS | when contractor designed | ||
| 27 | Work Platform | LS | contractor designed where required |
| 28 | Pile Load Tests | EA | may include subdivided items |
| Examples: AA. "First 4 Tests" and AB. "All Over 4 Tests" | |||
| 29 | Pile Caps | EA | when all caps are of uniform section; includes costs for all forming, rebar, finishing, etc. |
| LS | when dimensions vary; includes costs for all forming, rebar, finishing, etc. | ||
| 30 | Bridge Deck | ||
| - Precast Girders | LF | includes costs for all forming, rebar, finishing, etc. | |
| - Deck Paving | SY | includes costs for all forming, rebar, finishing, etc. | |
| 31 | Concrete Paving | SY | separate items for each thickness; includes costs for all forming, rebar, finishing, etc. |
| 32 | Road Sub-Base | SY | separate items for each thickness |
| CY | measured by truck measure | ||
| 33 | Concrete Curb | LF | use separate items for barrier curb, rollover curb, etc.; includes costs for all forming, rebar, etc. |
| includes costs for all forming, rebar, finishing, etc. | |||
| 34 | Guardrail | LF | |
| 35 | Concrete Slope Paving | SQ | 1 SQ = 100 SF |
| quantity includes cutoff walls; includes costs for all rebar, forming, etc. | |||
| 36 | Concrete I-Walls | LF | uniform cross-section; includes costs for all forming, rebar, finishing, etc. |
| LS | non-uniform cross-section; includes costs for all forming, rebar, finishing, etc. | ||
| 37 | Concrete T-Walls | LS | includes costs for all forming, rebar, finishing, etc. |
| 38 | Concrete Flumes and Box Culverts | LF | uniform cross-section; includes costs for all forming, rebar, finishing, etc. |
| LS | non-uniform cross-section; includes costs for all forming, rebar, finishing, etc. | ||
| 39 | Asphalt | SY | |
| TONS | measured by truck at plant | ||
| 40 | Flood Gates | LS | exception - under supply contracts paid for by the pound. |
| 41 | Miter Gates | LS | exception - under supply contracts paid for by the pound. |
| 42 | Sector Gates | LS | exception - under supply contracts paid for by the pound. |
| 43 | Suice Gates | EA | |
| 44 | Valves | EA | |
| 45 | Fencing | LF | |
| - Permanent Fencing | LF | ||
| - Silt Fencing | LF or n/a | paid for by the linear foot when over $10,000; otherwise covered in job overhead | |
| - Safety Fencing | LF or n/a | paid for by the linear foot when over $10,000; otherwise covered in job overhead | |
| - Silt and Safety Fencing | LF | when both items are along uniform placement they may be covered under a common bid item | |
| 46 | Fertilizing, Seeding and Mulching | Acre | vendor letter prompted NOD policy of quantifying bid items |
| 47 | Sodding | Acre | |
| 48 | Electrical | LS | features of work may be separated into separate line items |
| 49 | Mechanical | ||
| - Pumping Station | |||
| - Pump Engines | EA | ||
| - Gear Reducers | EA | ||
| - Pumps | EA | ||
| 50 | Miscellaneous Metalwork | LS | |
| 51 | Painting / Coatings - Sheetpile | ||
| - Sheetpile | SF or n/a | may be paid for separately or within the sheet pile item | |
| - Pipes | n/a | usually included in the pipe item | |
| - Floodwalls | SF or n/a | may be paid for separately or within the floodwall item |
Instructions
Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
| The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above. |
| Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works. |
| * CSI = Construction Specifications Institute |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Summary
| CONSTRUCTION COST ESTIMATE | |||||||
| SUMMARY | Date: | ||||||
| Fill Here | FILL IN AS REQUIRED (this will link to the entire document) | This spreadsheet contains many formulas... please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas | |||||
| PRIME CONTRACTOR | |||||||
| Fill Here | |||||||
| PROJECT NUMBER | GC Overhead | 7.81% | |||||
| Fill Here | GC Profit | 15.00% | |||||
| PROJECT | Sub Overhead | See Divisions | |||||
| Fill Here | Sub Profit | See Divisions | |||||
| LOCATION | PROJECT NO. | Risk/Bonding | 2.50% | Hide Divisions not used on both SUMMARY and TABS | |||
| Fill Here | PXLY-128S | NMGRT | 6.125% | ||||
| DIVISION | DESCRIPTION | % By | |||||
| Division | Division Total | ||||||
| DIVISION 01 | Div01 - GENERAL REQUIREMENTS | 15.3% | 2,949.75 | ||||
| DIVISION 02 | Div02 - EXISTING CONDITIONS | 77.8% | 14,995.20 | ||||
| DIVISION 03 | Div03 - CONCRETE WORK | 0.0% | - 0 | ||||
| DIVISION 04 | Div04 - MASONRY | 0.0% | - 0 | ||||
| DIVISION 05 | Div05 - METALS | 0.0% | - 0 | ||||
| DIVISION 06 | Div06 - WOOD, PLASTICS AND COMPOSITES | 0.0% | - 0 | ||||
| DIVISION 07 | Div07 - THERMAL AND MOISTURE PROTECTION | 0.0% | - 0 | ||||
| DIVISION 08 | Div08 - OPENINGS | 0.0% | - 0 | ||||
| DIVISION 09 | Div09 - FINISHES | 0.0% | - 0 | ||||
| DIVISION 10 | Div10 - SPECIALTIES | 0.0% | - 0 | ||||
| DIVISION 11 | Div11 - EQUIPMENT | 6.9% | 1,320.00 | ||||
| DIVISION 12 | Div12 - FURNISHINGS | 0.0% | - 0 | ||||
| DIVISION 13 | Div13 - SPECIAL CONSTRUCTION | 0.0% | - 0 | ||||
| DIVISION 14 | Div14 - CONVEYING EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 21 | Div21 - FIRE SUPRESSION | 0.0% | - 0 | ||||
| DIVISION 22 | Div22 - PLUMBING | 0.0% | - 0 | ||||
| DIVISION 23 | Div23 - HEATING, VENTILATING AND A/C | 0.0% | - 0 | ||||
| DIVISION 25 | Div25 - INTEGRATED AUTOMATION | 0.0% | - 0 | ||||
| DIVISION 26 | Div26 - ELECTRICAL | 0.0% | - 0 | ||||
| DIVISION 27 | Div27 - COMMUNICATIONS | 0.0% | - 0 | ||||
| DIVISION 28 | Div28 - ELECTRONIC SAFETY AND SECURITY | 0.0% | - 0 | ||||
| DIVISION 31 | Div31 - EARTHWORK | 0.0% | - 0 | ||||
| DIVISION 32 | Div32 - EXTERIOR IMPROVEMENTS | 0.0% | - 0 | ||||
| DIVISION 33 | Div33 - UTILITIES | 0.0% | - 0 | ||||
| DIVISION 34 | Div34 - TRANSPORTATION | 0.0% | - 0 | ||||
| DIVISION 35 | Div35 - WATERWAYS AND MARINE CONSTRUCTION | 0.0% | - 0 | ||||
| DIVISION 40 | Div40 - PROCESS INTEGRATION | 0.0% | - 0 | ||||
| DIVISION 41 | Div41 - MATERIAL PROCESING AND HANDLING EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 42 | Div42 - PROCESS HEATING, COOLING AND DRYING EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 43 | Div43 - PROCESS GAS & LIQUID HANDLING, PURIFICATION & STORAGE EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 44 | Div44 - POLLUTION CONTROL EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 46 | Div46 - WATER and WASTEWATER EQUIPMENT | 0.0% | - 0 | ||||
| DIVISION 48 | Div48 - ELECTRICAL POWER GENERATION | 0.0% | - 0 | ||||
| ALL DIVISIONS SUB-TOTAL (HARD COST) | 100% | 19,264.95 | |||||
| PRIME GENERAL CONTRACT OFFICE OVERHEAD | 7.810% | 1,504.59 | |||||
| SUBTOTAL | 20,769.55 | ||||||
| PRIME GENERAL CONTRACTOR'S PROFIT | 15.000% | 3,115.43 | |||||
| SUBTOTAL | 23,884.98 | ||||||
| DESIGN (6%) | 6.000% | 1,433.10 | |||||
| SUBTOTAL | 25,318.08 | ||||||
| BUILDER'S RISK / PERFORMANCE BONDS | 2.500% | 597.12 | |||||
| SUBTOTAL | 24,482.10 | ||||||
| NEW MEXICO GROSS RECEIPTS TAX (NMGRT) | 6.125% | 1,499.53 | |||||
| CONTRACT TOTAL | $ 27,414.73 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div1
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | ||||||||||||||
| Fill Here | |||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | ||||||||||||||
| Fill Here | |||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | ||||||||||||||
| Fill Here | 2,949.75 | ||||||||||||||
| Div01 - GENERAL REQUIREMENTS | PROJECT NO. | WORK LOCATION | |||||||||||||
| Fill Here | Fill Here | ||||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER COST | LINE TOTAL | |||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | |||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | ||||||||||
| 1 | asphalt example | SY | 4,111.00 | 6.55 | 26,927.05 | Hrs | 960.00 | 30.00 | 28,800.00 | - 0 | - 0 | 100.00 | 55,827.05 | ||
| 2 | SAMPLE...Project Dumspter (With Non Refund Deposit) | Ea | 2.00 | 80.00 | 160.00 | 30.00 | - 0 | - 0 | 70.00 | 230.00 | |||||
| 3 | SAMPLE...Project Billboard (Ususall not required Sample only) | Ea | 1.00 | 115.00 | 115.00 | Hrs | 0.50 | 27.42 | 13.71 | - 0 | 128.71 | ||||
| 4 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | 27,202.05 | 28,813.71 | - 0 | 170.00 | 56,185.76 | ||||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 5.00% | 2,809.29 | |||||||||||||
| SUBTOTAL | 58,995.05 | ||||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 5.00% | 2,949.75 | |||||||||||||
| TOTAL | $ 2,949.75 | ||||||||||||||
| 960.00 |
&L&"Verdana,Bold"Construction Cost Estimate &R&P of &N
Div2
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | ||||||||||||||
| Fill Here | |||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | ||||||||||||||
| Fill Here | |||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | ||||||||||||||
| Fill Here | 14,995.20 | ||||||||||||||
| Div02 - EXISTING CONDITIONS | PROJECT NO. | WORK LOCATION | |||||||||||||
| Fill Here | Fill Here | ||||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUPMENT COST | OTHER DIRECT COST | LINE TOTAL | |||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | |||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | ||||||||||
| 1 | SAMPLE...Demo Asphalt Driveway 3" Thick (Leave Base Coarse) (480SF) | SY | 53.00 | 480.00 | 25,440.00 | - 0 | 2.00 | 106.00 | 100.00 | 25,646.00 | |||||
| 2 | SAMPLE...Backhoe with 2 Laborors working 8 Hrs | Days | - 0 | Hrs | 28.00 | 2,325.00 | 65,100.00 | - 0 | 65,100.00 | ||||||
| 3 | SAMPLE...Landfill cost | - 0 | - 0 | - 0 | 134.00 | 134.00 | |||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 5 | 480SY | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | 25,440.00 | 65,100.00 | 106.00 | 234.00 | 90,880.00 | ||||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | 9,088.00 | |||||||||||||
| SUBTOTAL | 99,968.00 | ||||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | 14,995.20 | |||||||||||||
| TOTAL | $ 14,995.20 |
Div3
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | ||||||||||||||
| Fill Here | |||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | ||||||||||||||
| Fill Here | |||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | ||||||||||||||
| Fill Here | - 0 | ||||||||||||||
| Div03 - CONCRETE WORK | PROJECT NO. | WORK LOCATION | |||||||||||||
| Fill Here | Fill Here | ||||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | |||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | |||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | ||||||||||
| 1 | - 0 | Hrs | - 0 | - 0 | - 0 | ||||||||||
| 2 | - 0 | Hrs | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | Hrs | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | Hrs | - 0 | - 0 | - 0 | 256 | |||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | |||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | |||||||||||||
| SUBTOTAL | - 0 | ||||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | |||||||||||||
| TOTAL | $ - 0 |
Div4
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div04 - MASONRY | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div5
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div05 - METALS | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div6
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div06 - WOOD, PLASTICS AND COMPOSITES | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div7
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div07 - THERMAL AND MOISTURE PROTECTION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div8
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div08 - OPENINGS | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div9
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div09 - FINISHES | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div10
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div10 - SPECIALTIES | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div11
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | 1,320.00 | |||||||||||||
| Div11 - EQUIPMENT | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | SF | 4,000.00 | - 0 | - 0 | 2.00 | 8,000.00 | 8,000.00 | |||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | 8,000.00 | - 0 | 8,000.00 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | 800.00 | ||||||||||||
| SUBTOTAL | 8,800.00 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | 1,320.00 | ||||||||||||
| TOTAL | $ 1,320.00 |
Div12
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div12 - FURNISHINGS | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div13
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div13 - SPECIAL CONSTRUCTION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div14
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div14 - CONVEYING EQUIPMENT | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div21
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div21 - FIRE SUPRESSION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div22
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div22 - PLUMBING | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div23
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div23 - HEATING, VENTILATING AND A/C | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div25
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div25 - INTEGRATED AUTOMATION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div26
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div26 - ELECTRICAL | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div27
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div27 - COMMUNICATIONS | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div28
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div28 - ELECTRONIC SAFETY AND SECURITY | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div31
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div31 - EARTHWORK | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div32
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div32 - EXTERIOR IMPROVEMENTS | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div33
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div33 - UTILITIES | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div34
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div34 - TRANSPORTATION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div35
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div35 - WATERWAYS AND MARINE CONSTRUCTION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div40
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div40 - PROCESS INTEGRATION | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div41
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div41 - MATERIAL PROCESING AND HANDLING EQUIPMENT | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 17 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 18 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 19 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 20 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| SUBTOTAL MATERIAL / LABOR / OTHER DIRECT COST | - 0 | - 0 | - 0 | - 0 | - 0 | |||||||||
| Sub-Contractor's Overhead (If Prime Contractor Performing Woek Put 0%) | 10.00% | - 0 | ||||||||||||
| SUBTOTAL | - 0 | |||||||||||||
| Sub-Contractor's Profit (If Prime Contractor Performing Woek Put 0%) | 15.00% | - 0 | ||||||||||||
| TOTAL | $ - 0 |
Div42
| CONSTRUCTION COST ESTIMATE BREAKDOWN | DATE: | |||||||||||||
| Fill Here | ||||||||||||||
| CONTRACTOR (OR SUB-CONTRACTOR PERFORMING WORK | ADDRESS | |||||||||||||
| Fill Here | ||||||||||||||
| PROJECTY NAME | PROPOSED TOTAL ESTIMATED AMOUNT | |||||||||||||
| Fill Here | - 0 | |||||||||||||
| Div42 - PROCESS HEATING, COOLING AND DRYING EQUIPMENT | PROJECT NO. | WORK LOCATION | ||||||||||||
| Fill Here | Fill Here | |||||||||||||
| No. | ITEM | MATERIAL COST | LABOR COST | EQUIPMENT COST | OTHER DIRECT COST | LINE TOTAL | ||||||||
| MEASURE | QTY | UNIT | TOTAL | MANHOURS | ||||||||||
| MANDAYS | QTY | AVG RATE | TOTAL | UNIT | TOTAL | |||||||||
| 1 | - 0 | - 0 | 2.00 | - 0 | - 0 | |||||||||
| 2 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 3 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 4 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 5 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 6 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 7 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 8 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 9 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 10 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 11 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 12 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 13 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 14 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 15 | - 0 | - 0 | - 0 | - 0 | ||||||||||
| 16 | - 0 | - 0 | - 0 | - 0 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .