General repair Bldg. 703, Camp Darby, Tirrenia (Pisa), Italy
Award Notice Posted
- Solicitation number
- W912PF17R0017
- Agency
-
RCO Vicenza-Africa 414th CSB
Expeditionary Contracting Command, Department of Defense
- Awarded
- to Consorzio Stabile JV BB CLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912PF18C0002 Federal contract award
- NAICS code
- 238140 Masonry Contractors
- PSC
- Not on record
- Place of performance
- Camp Darby ( Tirrenia) Pisa, Italy Non-U.S. Italy
Notice details come from SAM.gov. Updated .
Notice text
4 versions
Update #4 · Latest ·
NOTE: The response date has been changed from 26 June 2017 to 19 June 2017.
DESCRIPTION OF THE PROJECT:
Full design. The project will include the general repair of the Camp Darby Motor Pool.
This project is required to perform a general upgrade of the existing
building, including both the administrative and vehicles shop areas, to
assure building code and life safety conditions.
The main architectural work items are listed as follows:
- The administration area will be renovated considering floors,
windows, doors, false ceilings etc.
- Restrooms and lockers rooms, separate by gender, will be renovated
both for the maintenance area and the admin offices.
- The shop area will be renovated, the industrial floor will be
repaired. Warehouse ceilings, columns and beams are open to the exposed
structure, and plastering and painting will be provided. The overhead doors
will be replaced. A battery charger room shall be provided, as well as other
storages and support spaces. The two existing inspection ditches will be
filled.
- Replacement of existing exterior and interior doors and frames shall
be included.
- The roof waterproofing membrane will be removed and replaced. New
flashings, gutters and downspouts will be installed.
- The external surfaces of the building, will be plastered and
painted.
Structural:
Limited works like some new interior masonry walls with their new foundation
beam.
Mechanical system:
Total replacement of heating, cooling, exhaust, compressed air systems
Plumbing:
Total replacement of cold/hot water and drainage system.
Fire:
New sprinkler system.
Electrical, telephone/data transmission, fire alarm and voice evacuation
(MNS) systems:
Total replacement and upgrade of existing systems.
FUNDING:" This procurement action is subject to the availability of funds"
LOCATION OF THE WORK: The site of the proposed work is Camp Darby,
Tirrenia (Pisa)
MAGNITUDE OF THE PROJECT: The magnitude of this project is between $ 1,000,000 and $ 5,000,000.
METHOD OF CONTRACTING: This will be a Request for Proposal resulting
in a firm fixed price contract.
PERFORMANCE PERIOD: The Performance Period will be 365 calendar days
SOA: Contractor is required to be SOA OG1 classification III qualified
SITE VISIT: The site visit will be held on MAY 31, 2017 at 13:30 hrs at main
gate no. 4 Camp Darby, Tirrenia(Pisa), Italy.
MISCELLANEOUS:
The solicitation package , including the TECHNICAL SPECIFICATIONS , DRAWINGS and additional information will be posted within few weeks on Federal
Business Opportunities (www.fbo.gov).
To be awarded a government contract you MUST have DUNS (Dun&
Bradstreet; tel: 02-28455379) and NCAGE
(www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in
SAM(https://www.sam.gov/portal/public/SAM). We will discuss this at the site
visit.
HOW TO PARTICIPATE: In order to participate all interested parties are
invited to indicate their interest by submitting email not later than close of
Business(COB) APRIL 27, 2017 to the following address:
cristina.pancaccini2.ln@mail.mil.
Please indicate in your e-mail the solicitation number W912PF-17-R-0017 and
the name of the company, address, phone number, e-mail address and name
(s) of the person(s) who will be present at the site visit (maximum two
people). SUBMIT A COPY OF ID (CARTA DI IDENTITA) OR PATENTE OF THE PERSON WHO WILL BE PRESENT AT THE SITE VISIT.
Only the persons who have provided the personal data will be allowed to
attend the site visit. The Guards will check the identification card at the Gate.
The offerors not present on the list will be denied the entrance to the base.
Update #3 ·
DESCRIPTION OF THE PROJECT:
Full design. The project will include the general repair of the Camp Darby Motor Pool.
This project is required to perform a general upgrade of the existing
building, including both the administrative and vehicles shop areas, to
assure building code and life safety conditions.
The main architectural work items are listed as follows:
- The administration area will be renovated considering floors,
windows, doors, false ceilings etc.
- Restrooms and lockers rooms, separate by gender, will be renovated
both for the maintenance area and the admin offices.
- The shop area will be renovated, the industrial floor will be
repaired. Warehouse ceilings, columns and beams are open to the exposed
structure, and plastering and painting will be provided. The overhead doors
will be replaced. A battery charger room shall be provided, as well as other
storages and support spaces. The two existing inspection ditches will be
filled.
- Replacement of existing exterior and interior doors and frames shall
be included.
- The roof waterproofing membrane will be removed and replaced. New
flashings, gutters and downspouts will be installed.
- The external surfaces of the building, will be plastered and
painted.
Structural:
Limited works like some new interior masonry walls with their new foundation
beam.
Mechanical system:
Total replacement of heating, cooling, exhaust, compressed air systems
Plumbing:
Total replacement of cold/hot water and drainage system.
Fire:
New sprinkler system.
Electrical, telephone/data transmission, fire alarm and voice evacuation
(MNS) systems:
Total replacement and upgrade of existing systems.
FUNDING:" This procurement action is subject to the availability of funds"
LOCATION OF THE WORK: The site of the proposed work is Camp Darby,
Tirrenia (Pisa)
MAGNITUDE OF THE PROJECT: The magnitude of this project is between $ 1,000,000 and $ 5,000,000.
METHOD OF CONTRACTING: This will be a Request for Proposal resulting
in a firm fixed price contract.
PERFORMANCE PERIOD: The Performance Period will be 365 calendar days
SOA: Contractor is required to be SOA OG1 classification III qualified
SITE VISIT: The site visit will be held on MAY 31, 2017 at 13:30 hrs at main
gate no. 4 Camp Darby, Tirrenia(Pisa), Italy.
MISCELLANEOUS:
The solicitation package , including the TECHNICAL SPECIFICATIONS , DRAWINGS and additional information will be posted within few weeks on Federal
Business Opportunities (www.fbo.gov).
To be awarded a government contract you MUST have DUNS (Dun&
Bradstreet; tel: 02-28455379) and NCAGE
(www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in
SAM(https://www.sam.gov/portal/public/SAM). We will discuss this at the site
visit.
HOW TO PARTICIPATE: In order to participate all interested parties are
invited to indicate their interest by submitting email not later than close of
Business(COB) APRIL 27, 2017 to the following address:
cristina.pancaccini2.ln@mail.mil.
Please indicate in your e-mail the solicitation number W912PF-17-R-0017 and
the name of the company, address, phone number, e-mail address and name
(s) of the person(s) who will be present at the site visit (maximum two
people). SUBMIT A COPY OF ID (CARTA DI IDENTITA) OR PATENTE OF THE PERSON WHO WILL BE PRESENT AT THE SITE VISIT.
Only the persons who have provided the personal data will be allowed to
attend the site visit. The Guards will check the identification card at the Gate.
The offerors not present on the list will be denied the entrance to the base.
Update #2 ·
DESCRIPTION OF THE PROJECT:
Full design. The project will include the general repair of the Camp Darby Motor Pool.
This project is required to perform a general upgrade of the existing
building, including both the administrative and vehicles shop areas, to
assure building code and life safety conditions.
The main architectural work items are listed as follows:
- The administration area will be renovated considering floors,
windows, doors, false ceilings etc.
- Restrooms and lockers rooms, separate by gender, will be renovated
both for the maintenance area and the admin offices.
- The shop area will be renovated, the industrial floor will be
repaired. Warehouse ceilings, columns and beams are open to the exposed
structure, and plastering and painting will be provided. The overhead doors
will be replaced. A battery charger room shall be provided, as well as other
storages and support spaces. The two existing inspection ditches will be
filled.
- Replacement of existing exterior and interior doors and frames shall
be included.
- The roof waterproofing membrane will be removed and replaced. New
flashings, gutters and downspouts will be installed.
- The external surfaces of the building, will be plastered and
painted.
Structural:
Limited works like some new interior masonry walls with their new foundation
beam.
Mechanical system:
Total replacement of heating, cooling, exhaust, compressed air systems
Plumbing:
Total replacement of cold/hot water and drainage system.
Fire:
New sprinkler system.
Electrical, telephone/data transmission, fire alarm and voice evacuation
(MNS) systems:
Total replacement and upgrade of existing systems.
FUNDING:" This procurement action is subject to the availability of funds"
LOCATION OF THE WORK: The site of the proposed work is Camp Darby,
Tirrenia (Pisa)
MAGNITUDE OF THE PROJECT: The magnitude of this project is between $ 1,000,000 and $ 5,000,000.
METHOD OF CONTRACTING: This will be a Request for Proposal resulting
in a firm fixed price contract.
PERFORMANCE PERIOD: The Performance Period will be 365 calendar days
SOA: Contractor is required to be SOA OG1 classification III qualified
SITE VISIT: The site visit will be held on MAY 31, 2017 at 13:30 hrs at main
gate no. 4 Camp Darby, Tirrenia(Pisa), Italy.
MISCELLANEOUS:
The solicitation package , including the technical specificaiton , description of
the work and addtional information will be posted within few weeks on Federal
Business Opportunities (www.fbo.gov).
To be awarded a government contract you MUST have DUNS (Dun&
Bradstreet; tel: 02-28455379) and NCAGE
(www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in
SAM(https://www.sam.gov/portal/public/SAM). We will discuss this at the site
visit.
HOW TO PARTICIPATE: In order to participate all interested parties are
invited to indicate their interest by submitting email not later than close of
Business(COB) APRIL 27, 2017 to the following address:
cristina.pancaccini2.ln@mail.mil.
Please indicate in your e-mail the solicitation number W912PF-17-R-0017 and
the name of the company, address, phone number, e-mail address and name
(s) of the person(s) who will be present at the site visit (maximum two
people). SUBMIT A COPY OF ID (CARTA DI IDENTITA) OR PATENTE OF THE PERSON WHO WILL BE PRESENT AT THE SITE VISIT.
Only the persons who have provided the personal data will be allowed to
attend the site visit. The Guards will check the identification card at the Gate.
The offerors not present on the list will be denied the entrance to the base.
Update #1 ·
DESCRIPTION OF THE PROJECT:
Full design. The project will include the general repair of the Camp Darby Motor Pool.
This project is required to perform a general upgrade of the existing
building, including both the administrative and vehicles shop areas, to
assure building code and life safety conditions.
The main architectural work items are listed as follows:
- The administration area will be renovated considering floors,
windows, doors, false ceilings etc.
- Restrooms and lockers rooms, separate by gender, will be renovated
both for the maintenance area and the admin offices.
- The shop area will be renovated, the industrial floor will be
repaired. Warehouse ceilings, columns and beams are open to the exposed
structure, and plastering and painting will be provided. The overhead doors
will be replaced. A battery charger room shall be provided, as well as other
storages and support spaces. The two existing inspection ditches will be
filled.
- Replacement of existing exterior and interior doors and frames shall
be included.
- The roof waterproofing membrane will be removed and replaced. New
flashings, gutters and downspouts will be installed.
- The external surfaces of the building, will be plastered and
painted.
Structural:
Limited works like some new interior masonry walls with their new foundation
beam.
Mechanical system:
Total replacement of heating, cooling, exhaust, compressed air systems
Plumbing:
Total replacement of cold/hot water and drainage system.
Fire:
New sprinkler system.
Electrical, telephone/data transmission, fire alarm and voice evacuation
(MNS) systems:
Total replacement and upgrade of existing systems.
FUNDING: The project is not funded
LOCATION OF THE WORK: The site of the proposed work is Camp Darby,
Tirrenia (Pisa)
MAGNITUDE OF THE PROJECT: The magnitude of this project is between $ 1,000,000 and $ 5,000,000.
METHOD OF CONTRACTING: This will be a Request for Proposal resulting
in a firm fixed price contract.
PERFORMANCE PERIOD: The Performance Period will be 365 calendar days
SOA: Contractor is required to be SOA OG1 classification III qualified
SITE VISIT: The site visit will be held on MAY 31, 2017 at 13:30 hrs at main
gate no. 4 Camp Darby, Tirrenia(Pisa), Italy.
MISCELLANEOUS:
The solicitation package , including the technical specificaiton , description of
the work and addtional information will be posted within few weeks on Federal
Business Opportunities (www.fbo.gov).
To be awarded a government contract you MUST have DUNS (Dun&
Bradstreet; tel: 02-28455379) and NCAGE
(www.dlis.dla.mil/Forms/Form_AC135.asp) numbers and be registered in
SAM(https://www.sam.gov/portal/public/SAM). We will discuss this at the site
visit.
HOW TO PARTICIPATE: In order to participate all interested parties are
invited to indicate their interest by submitting email not later than close of
Business(COB) APRIL 27, 2017 to the following address:
cristina.pancaccini2.ln@mail.mil.
Please indicate in your e-mail the solicitation number W912PF-17-R-0017 and
the name of the company, address, phone number, e-mail address and name
(s) of the person(s) who will be present at the site visit (maximum two
people). SUBMIT A COPY OF ID (CARTA DI IDENTITA) OR PATENTE OF THE PERSON WHO WILL BE PRESENT AT THE SITE VISIT.
Only the persons who have provided the personal data will be allowed to
attend the site visit. The Guards will check the identification card at the Gate.
The offerors not present on the list will be denied the entrance to the base.
Files
Show all 25
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity