FXSB 17-4704 Repair Tank Farm 3 and 4
Closed Solicitation Posted
- Solicitation number
- FA500023B0001
- Agency
-
Pacific Air Forces
Air Force, Department of Defense
- Responses due
- Set-aside
- Competitive 8(a)
Opportunity facts
- NAICS code
- 237120 Oil and Gas Pipeline and Related Structures Construction
- Place of performance
- Jber, Alaska 99506, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to consolidate and repair the bulk fuel storage and distribution capabilities at Tank Farms 3 and 4 located at Joint Base Elmendorf-Richardson in Alaska. The Department of the Air Force Pacific Air Forces requires demolition of existing 1950s-era underground storage tanks and infrastructure at the two tank farms, and reconstruction of a new consolidated system at Tank Farm 4. This will include installation of six new 50,000-gallon double-wall tanks for jet fuel and one 25,000-gallon double-wall tank for diesel, plus construction of a new filter building, control room, motor control center, truck loading and unloading areas, and a retail fuel station. Questions are due by June 1, 2023, with site visits scheduled for May 24, 2023 and proposals due by July 26, 2023.
The solicitation is set aside as an 8(a) competitive opportunity. The NAICS code is 237990 and PSC code is Q200. The estimated value is between $10-25 million. The place of performance is Joint Base Elmendorf-Richardson in Anchorage, Alaska. Key numerical details include demolition and reconstruction of the bulk fuel storage and distribution capabilities from two tank farms into a single consolidated system, including installation of six 50,000-gallon and one 25,000-gallon underground storage tanks.
Notice text
5 versions
Update #5 · Latest ·
AMENDMENT 0004
The pupose of this amendment is to:
1. Provide an updated Wage Determination AK20230001
2. Extend the bid due date to 1 August 2023 at 1300 (AKDT)
------------------------------------------------------End of Amendment 0004---------------------------------
AMENDMENT 0003
The purpose of this amendment is to:
1. Provide Attachment 21 - Clarification to Specifications
------------------------------------------------------End of Amendment 0003---------------------------------
AMENDMENT 0002
The purpose of this amendment is to:
1. Provide an updated Wage Determination AK20230001, dated 23 June 2023
2. Provide Attachment 17 - RTA ED151
3. Provide Attachment 18 - Attachments for A33
4. Provide Attachment 19 - JBER 2022 Atlas Map Book
5. Provide Attachment 20 - Round 2 of Questions Tank Farm 3 & 4
6. Extend the bid due date to 26 July 2023 at 1300 (AKDT)
------------------------------------------------------End of Amendment 0002---------------------------------
AMENDMENT 0001:
The purpose of this amendment is to:
1. Extend the bid due date to 19 July 2023 at 1300 (AKDT).
2. Offer additional time to receive questions. New questions are due on 26 June 2023 at 1300 (AKDT).
3. Add Clause 52.204-27 Prohibition on a ByteDance Covered Application Jun 2023
4. Update Attachment 1 - Wage Determination AK200300001 5_19_2023
5. Update Attachment 3 - Specifications REV001
6. Add Attachments 10 - Site Specific Spill Plan
7. Add Attachment 11 - JBER Spill Reporting Poster
8. Add Attachment 12 - 2019 JBER Environmental Handbook
9. Add Attachment 13 - JBE057_058_Asbestos_Final
10. Add Attachment 14 - Sign-in Sheet
11. Add Attachment 15 - Questions and Answers
12. Add Attachment 16 - Class J&A ALC
------------------------------------------------------End of Amendment 0001---------------------------------
IAW DFAR 236.204(i), Disclosure of Magnitude of Construction Projects, the estimated price range of this between $10,000,000 and $25,000,000.
Payment and Performance bonds shall be obtained IAW FAR 28.102.
Requirement / Description
Contractor shall provide all labor, materials, equipment, hardware, software and programming necessary to provide fully functional repairs for Tank Farms 3 and 4 as detailed in the attached Statement of Work (Attachment 1), drawings (Attachment 2), and specifications (Attachment 3).
The purpose of this project is to consolidate the bulk JP-8 and Ultra-low Sulfur Diesel (ULSD) storage and issue capabilities of Fuel Farm #3 and Fuel Farm #4. The existing bulk storage Underground Storage Tank (USTs) at Fuel Farm #3 and #4 are of 1950s vintage and have reached the end of their service life. The Fuel Farm #3 and #4 aviation and bulk ULSD infrastructure will be demolished, along with the underground JP-8 transfer pipeline, and reconstructed as a consolidated system at the Fuel Farm #4 area. The consolidated facility will have six 50,000-gallon double-wall USTs for JP-8 storage and one 25,000-gallon double-wall UST for ULSD storage. A new filter building with control room and motor control center (MCC) will also be constructed at Fuel Farm #4. A new truck loading and offloading area will be provided for ULSD receipt and issue west of the existing truck fill stands. Additionally, a return to bulk station will be constructed at the existing JP-8 truck fill stand.
In place of Fuel Farm #3, a new Retail Station with two ULSD and two JP-8 dispensers will be constructed. The existing USTs for retail sales will be reused. The new service station building will contain an office, bathroom, and eyewash station.
Site Visit:
IAW FAR 52.236-27 SITE VISIT (Construction)
Alternate I (Feb1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Bidders are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 24 May 2023 at 10:00AM AKDT.
i. If interested parties would like to attend the site visit and requires temporary base access, please contact Christopher
Nelson at Christopher.Nelson.70@us.af.mil at least three (3) days prior to the site visit.
(c) Participants will meet at BLDG 10480 Sijan Avenue in RM 211. After a brief discussion, all parties will be escorted to the
site where the work will be performed.
Questions Due Date:
Due to the importance of maintaining the schedule for this project, it is requested that all questions regarding the specifications and/or drawings be submitted by 10:00 AM AKDT, Thursday, 1 June 2023. All questions must be in writing and shall be emailed to Christopher.Nelson.70@us.af.mil and Brian.Barcelona@us.af.mil with the SUBJECT identified as "FA500023B0001 - QUESTION". Any questions received after the above date and time are at the discretion of the Contracting Officer. Requests for hardcopies of the solicitation, specifications, drawings, and amendments (if applicable) will not be honored.
Update #4 ·
AMENDMENT 0003
The purpose of this amendment is to:
1. Provide Attachment 21 - Clarification to Specifications
------------------------------------------------------End of Amendment 0003---------------------------------
AMENDMENT 0002
The purpose of this amendment is to:
1. Provide an updated Wage Determination AK20230001, dated 23 June 2023
2. Provide Attachment 17 - RTA ED151
3. Provide Attachment 18 - Attachments for A33
4. Provide Attachment 19 - JBER 2022 Atlas Map Book
5. Provide Attachment 20 - Round 2 of Questions Tank Farm 3 & 4
6. Extend the bid due date to 26 July 2023 at 1300 (AKDT)
------------------------------------------------------End of Amendment 0002---------------------------------
AMENDMENT 0001:
The purpose of this amendment is to:
1. Extend the bid due date to 19 July 2023 at 1300 (AKDT).
2. Offer additional time to receive questions. New questions are due on 26 June 2023 at 1300 (AKDT).
3. Add Clause 52.204-27 Prohibition on a ByteDance Covered Application Jun 2023
4. Update Attachment 1 - Wage Determination AK200300001 5_19_2023
5. Update Attachment 3 - Specifications REV001
6. Add Attachments 10 - Site Specific Spill Plan
7. Add Attachment 11 - JBER Spill Reporting Poster
8. Add Attachment 12 - 2019 JBER Environmental Handbook
9. Add Attachment 13 - JBE057_058_Asbestos_Final
10. Add Attachment 14 - Sign-in Sheet
11. Add Attachment 15 - Questions and Answers
12. Add Attachment 16 - Class J&A ALC
------------------------------------------------------End of Amendment 0001---------------------------------
IAW DFAR 236.204(i), Disclosure of Magnitude of Construction Projects, the estimated price range of this between $10,000,000 and $25,000,000.
Payment and Performance bonds shall be obtained IAW FAR 28.102.
Requirement / Description
Contractor shall provide all labor, materials, equipment, hardware, software and programming necessary to provide fully functional repairs for Tank Farms 3 and 4 as detailed in the attached Statement of Work (Attachment 1), drawings (Attachment 2), and specifications (Attachment 3).
The purpose of this project is to consolidate the bulk JP-8 and Ultra-low Sulfur Diesel (ULSD) storage and issue capabilities of Fuel Farm #3 and Fuel Farm #4. The existing bulk storage Underground Storage Tank (USTs) at Fuel Farm #3 and #4 are of 1950s vintage and have reached the end of their service life. The Fuel Farm #3 and #4 aviation and bulk ULSD infrastructure will be demolished, along with the underground JP-8 transfer pipeline, and reconstructed as a consolidated system at the Fuel Farm #4 area. The consolidated facility will have six 50,000-gallon double-wall USTs for JP-8 storage and one 25,000-gallon double-wall UST for ULSD storage. A new filter building with control room and motor control center (MCC) will also be constructed at Fuel Farm #4. A new truck loading and offloading area will be provided for ULSD receipt and issue west of the existing truck fill stands. Additionally, a return to bulk station will be constructed at the existing JP-8 truck fill stand.
In place of Fuel Farm #3, a new Retail Station with two ULSD and two JP-8 dispensers will be constructed. The existing USTs for retail sales will be reused. The new service station building will contain an office, bathroom, and eyewash station.
Site Visit:
IAW FAR 52.236-27 SITE VISIT (Construction)
Alternate I (Feb1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Bidders are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 24 May 2023 at 10:00AM AKDT.
i. If interested parties would like to attend the site visit and requires temporary base access, please contact Christopher
Nelson at Christopher.Nelson.70@us.af.mil at least three (3) days prior to the site visit.
(c) Participants will meet at BLDG 10480 Sijan Avenue in RM 211. After a brief discussion, all parties will be escorted to the
site where the work will be performed.
Questions Due Date:
Due to the importance of maintaining the schedule for this project, it is requested that all questions regarding the specifications and/or drawings be submitted by 10:00 AM AKDT, Thursday, 1 June 2023. All questions must be in writing and shall be emailed to Christopher.Nelson.70@us.af.mil and Brian.Barcelona@us.af.mil with the SUBJECT identified as "FA500023B0001 - QUESTION". Any questions received after the above date and time are at the discretion of the Contracting Officer. Requests for hardcopies of the solicitation, specifications, drawings, and amendments (if applicable) will not be honored.
Update #3 ·
AMENDMENT 0002
The purpose of this amendment is to:
1. Provide an updated Wage Determination AK20230001, dated 23 June 2023
2. Provide Attachment 17 - RTA ED151
3. Provide Attachment 18 - Attachments for A33
4. Provide Attachment 19 - JBER 2022 Atlas Map Book
5. Provide Attachment 20 - Round 2 of Questions Tank Farm 3 & 4
6. Extend the bid due date to 26 July 2023 at 1300 (AKDT)
------------------------------------------------------End of Amendment 0002---------------------------------
AMENDMENT 0001:
The purpose of this amendment is to:
1. Extend the bid due date to 19 July 2023 at 1300 (AKDT).
2. Offer additional time to receive questions. New questions are due on 26 June 2023 at 1300 (AKDT).
3. Add Clause 52.204-27 Prohibition on a ByteDance Covered Application Jun 2023
4. Update Attachment 1 - Wage Determination AK200300001 5_19_2023
5. Update Attachment 3 - Specifications REV001
6. Add Attachments 10 - Site Specific Spill Plan
7. Add Attachment 11 - JBER Spill Reporting Poster
8. Add Attachment 12 - 2019 JBER Environmental Handbook
9. Add Attachment 13 - JBE057_058_Asbestos_Final
10. Add Attachment 14 - Sign-in Sheet
11. Add Attachment 15 - Questions and Answers
12. Add Attachment 16 - Class J&A ALC
------------------------------------------------------End of Amendment 0001---------------------------------
IAW DFAR 236.204(i), Disclosure of Magnitude of Construction Projects, the estimated price range of this between $10,000,000 and $25,000,000.
Payment and Performance bonds shall be obtained IAW FAR 28.102.
Requirement / Description
Contractor shall provide all labor, materials, equipment, hardware, software and programming necessary to provide fully functional repairs for Tank Farms 3 and 4 as detailed in the attached Statement of Work (Attachment 1), drawings (Attachment 2), and specifications (Attachment 3).
The purpose of this project is to consolidate the bulk JP-8 and Ultra-low Sulfur Diesel (ULSD) storage and issue capabilities of Fuel Farm #3 and Fuel Farm #4. The existing bulk storage Underground Storage Tank (USTs) at Fuel Farm #3 and #4 are of 1950s vintage and have reached the end of their service life. The Fuel Farm #3 and #4 aviation and bulk ULSD infrastructure will be demolished, along with the underground JP-8 transfer pipeline, and reconstructed as a consolidated system at the Fuel Farm #4 area. The consolidated facility will have six 50,000-gallon double-wall USTs for JP-8 storage and one 25,000-gallon double-wall UST for ULSD storage. A new filter building with control room and motor control center (MCC) will also be constructed at Fuel Farm #4. A new truck loading and offloading area will be provided for ULSD receipt and issue west of the existing truck fill stands. Additionally, a return to bulk station will be constructed at the existing JP-8 truck fill stand.
In place of Fuel Farm #3, a new Retail Station with two ULSD and two JP-8 dispensers will be constructed. The existing USTs for retail sales will be reused. The new service station building will contain an office, bathroom, and eyewash station.
Site Visit:
IAW FAR 52.236-27 SITE VISIT (Construction)
Alternate I (Feb1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Bidders are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 24 May 2023 at 10:00AM AKDT.
i. If interested parties would like to attend the site visit and requires temporary base access, please contact Christopher
Nelson at Christopher.Nelson.70@us.af.mil at least three (3) days prior to the site visit.
(c) Participants will meet at BLDG 10480 Sijan Avenue in RM 211. After a brief discussion, all parties will be escorted to the
site where the work will be performed.
Questions Due Date:
Due to the importance of maintaining the schedule for this project, it is requested that all questions regarding the specifications and/or drawings be submitted by 10:00 AM AKDT, Thursday, 1 June 2023. All questions must be in writing and shall be emailed to Christopher.Nelson.70@us.af.mil and Brian.Barcelona@us.af.mil with the SUBJECT identified as "FA500023B0001 - QUESTION". Any questions received after the above date and time are at the discretion of the Contracting Officer. Requests for hardcopies of the solicitation, specifications, drawings, and amendments (if applicable) will not be honored.
Update #2 ·
AMENDMENT 0001:
The purpose of this amendment is to:
1. Extend the bid due date to 19 July 2023 at 1300 (AKDT).
2. Offer additional time to receive questions. New questions are due on 26 June 2023 at 1300 (AKDT).
3. Add Clause 52.204-27 Prohibition on a ByteDance Covered Application Jun 2023
4. Update Attachment 1 - Wage Determination AK200300001 5_19_2023
5. Update Attachment 3 - Specifications REV001
6. Add Attachments 10 - Site Specific Spill Plan
7. Add Attachment 11 - JBER Spill Reporting Poster
8. Add Attachment 12 - 2019 JBER Environmental Handbook
9. Add Attachment 13 - JBE057_058_Asbestos_Final
10. Add Attachment 14 - Sign-in Sheet
11. Add Attachment 15 - Questions and Answers
12. Add Attachment 16 - Class J&A ALC
------------------------------------------------------End of Amendment 0001---------------------------------
IAW DFAR 236.204(i), Disclosure of Magnitude of Construction Projects, the estimated price range of this between $10,000,000 and $25,000,000.
Payment and Performance bonds shall be obtained IAW FAR 28.102.
Requirement / Description
Contractor shall provide all labor, materials, equipment, hardware, software and programming necessary to provide fully functional repairs for Tank Farms 3 and 4 as detailed in the attached Statement of Work (Attachment 1), drawings (Attachment 2), and specifications (Attachment 3).
The purpose of this project is to consolidate the bulk JP-8 and Ultra-low Sulfur Diesel (ULSD) storage and issue capabilities of Fuel Farm #3 and Fuel Farm #4. The existing bulk storage Underground Storage Tank (USTs) at Fuel Farm #3 and #4 are of 1950s vintage and have reached the end of their service life. The Fuel Farm #3 and #4 aviation and bulk ULSD infrastructure will be demolished, along with the underground JP-8 transfer pipeline, and reconstructed as a consolidated system at the Fuel Farm #4 area. The consolidated facility will have six 50,000-gallon double-wall USTs for JP-8 storage and one 25,000-gallon double-wall UST for ULSD storage. A new filter building with control room and motor control center (MCC) will also be constructed at Fuel Farm #4. A new truck loading and offloading area will be provided for ULSD receipt and issue west of the existing truck fill stands. Additionally, a return to bulk station will be constructed at the existing JP-8 truck fill stand.
In place of Fuel Farm #3, a new Retail Station with two ULSD and two JP-8 dispensers will be constructed. The existing USTs for retail sales will be reused. The new service station building will contain an office, bathroom, and eyewash station.
Site Visit:
IAW FAR 52.236-27 SITE VISIT (Construction)
Alternate I (Feb1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Bidders are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 24 May 2023 at 10:00AM AKDT.
i. If interested parties would like to attend the site visit and requires temporary base access, please contact Christopher
Nelson at Christopher.Nelson.70@us.af.mil at least three (3) days prior to the site visit.
(c) Participants will meet at BLDG 10480 Sijan Avenue in RM 211. After a brief discussion, all parties will be escorted to the
site where the work will be performed.
Questions Due Date:
Due to the importance of maintaining the schedule for this project, it is requested that all questions regarding the specifications and/or drawings be submitted by 10:00 AM AKDT, Thursday, 1 June 2023. All questions must be in writing and shall be emailed to Christopher.Nelson.70@us.af.mil and Brian.Barcelona@us.af.mil with the SUBJECT identified as "FA500023B0001 - QUESTION". Any questions received after the above date and time are at the discretion of the Contracting Officer. Requests for hardcopies of the solicitation, specifications, drawings, and amendments (if applicable) will not be honored.
Update #1 ·
IAW DFAR 236.204(i), Disclosure of Magnitude of Construction Projects, the estimated price range of this between $10,000,000 and $25,000,000.
Payment and Performance bonds shall be obtained IAW FAR 28.102.
Requirement / Description
Contractor shall provide all labor, materials, equipment, hardware, software and programming necessary to provide fully functional repairs for Tank Farms 3 and 4 as detailed in the attached Statement of Work (Attachment 1), drawings (Attachment 2), and specifications (Attachment 3).
The purpose of this project is to consolidate the bulk JP-8 and Ultra-low Sulfur Diesel (ULSD) storage and issue capabilities of Fuel Farm #3 and Fuel Farm #4. The existing bulk storage Underground Storage Tank (USTs) at Fuel Farm #3 and #4 are of 1950s vintage and have reached the end of their service life. The Fuel Farm #3 and #4 aviation and bulk ULSD infrastructure will be demolished, along with the underground JP-8 transfer pipeline, and reconstructed as a consolidated system at the Fuel Farm #4 area. The consolidated facility will have six 50,000-gallon double-wall USTs for JP-8 storage and one 25,000-gallon double-wall UST for ULSD storage. A new filter building with control room and motor control center (MCC) will also be constructed at Fuel Farm #4. A new truck loading and offloading area will be provided for ULSD receipt and issue west of the existing truck fill stands. Additionally, a return to bulk station will be constructed at the existing JP-8 truck fill stand.
In place of Fuel Farm #3, a new Retail Station with two ULSD and two JP-8 dispensers will be constructed. The existing USTs for retail sales will be reused. The new service station building will contain an office, bathroom, and eyewash station.
Site Visit:
IAW FAR 52.236-27 SITE VISIT (Construction)
Alternate I (Feb1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Bidders are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 24 May 2023 at 10:00AM AKDT.
i. If interested parties would like to attend the site visit and requires temporary base access, please contact Christopher
Nelson at Christopher.Nelson.70@us.af.mil at least three (3) days prior to the site visit.
(c) Participants will meet at BLDG 10480 Sijan Avenue in RM 211. After a brief discussion, all parties will be escorted to the
site where the work will be performed.
Questions Due Date:
Due to the importance of maintaining the schedule for this project, it is requested that all questions regarding the specifications and/or drawings be submitted by 10:00 AM AKDT, Thursday, 1 June 2023. All questions must be in writing and shall be emailed to Christopher.Nelson.70@us.af.mil and Brian.Barcelona@us.af.mil with the SUBJECT identified as "FA500023B0001 - QUESTION". Any questions received after the above date and time are at the discretion of the Contracting Officer. Requests for hardcopies of the solicitation, specifications, drawings, and amendments (if applicable) will not be honored.
Files
Show all 31
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Repair Tank Farm 3 and 4, JBER, Alaska | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan | ENDIST Japan | No set-aside | |
| Vandenberg SFB Tank Inspection | ENDIST Omaha | Service-Disabled Veteran-Owned Small Business | |
| Mather Fueling System Repairs | ENDIST Omaha | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity