NASA's Goddard Space Flight Center is soliciting responses to a Draft Request for Proposal for the design, development, fabrication, integration, testing, and post-delivery support of Sounder for Microwave-Based Applications (SMBA) instruments under the Near Earth Orbit Network (NEON) program. The procurement seeks a contractor to develop up to eight SMBA Flight Model instruments, which are passive microwave radiometric sensors designed to collect hyperspectral atmospheric data across frequencies from 20-300 GHz for weather forecasting and climate monitoring applications. Key contract requirements include systems engineering, comprehensive environmental testing, mission assurance activities, software development, ground support equipment provision, and sustained engineering support through the contract period. The evaluation will employ a 1,000-point Mission Suitability scoring framework weighted as follows: Technical Approach (500 points), Management Approach (400 points), and Small Business Utilization (100 points), with evaluation criteria addressing system performance, instrument design, manufacturing capabilities, and contractor risk management abilities. The deadline for submitting comments and questions on the Draft RFP is May 9, 2025 at 5:00 PM Eastern Time, with responses directed to Bruce Tsai at Bruce.B.Tsai@nasa.gov and referenced as DRFP-NEON-SMBA-2025; the final RFP is anticipated for release in late Q1 or early Q2 of 2026, with proposals due 45-60 calendar days after release and contract award targeted for Q2-Q3 of 2027.

This procurement carries no small business set-aside designation and does not identify any current incumbents. The total estimated contract value ranges from $500,000 to $40,900,000, with a base period funding profile of $12 million in Government Fiscal Year 2026, $60 million in GFY 2027, and $60 million in GFY 2028. The contract structure includes three base Contract Line Item Numbers: CLIN 0001 is a Cost Plus Fixed Fee with Schedule Incentive covering Flight Model 1 non-recurring engineering and production through launch plus six months; CLIN 0002 is Firm Fixed Price for Flight Models 2 and 3 production; and CLIN 0003 is Time and Material for task orders including special studies and post-commissioning support. Flight Model deliveries are staggered annually from July 1, 2032 (FM1) through July 1, 2034 (FM3), with corresponding planned launch dates of October 1, 2034, 2037, and 2040. The NAICS code is 334511 (Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufacturing) with a small business size standard of 1,350 employees, and the Product Service Code is 1675 (Space Vehicle Components).

Notice text

27 versions

Update #27 · Latest ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Amendment 22: Post Acquisition Strategy Update.

Amendment 23: Mission Suitability Section L and M Update.

Amendment 24: Post Performance Requirements Document, Revision E. The Government plans to conduct a virtual Industry Day regarding Amendment 24 on March 18, 2026, at 1PM EST. Please email the primary point of contact to participate.

Amendment 25: Post questions and answers related to Performance Requirements Document, Revision E. The Government will conduct vendor One-on-One meetings the week of March 23, 2026. If interested, please email the primary point of contact with your availability.

Amendment 26: Post the Industry Day presentation for Amendment 25.

Update #26 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Amendment 22: Post Acquisition Strategy Update.

Amendment 23: Mission Suitability Section L and M Update.

Amendment 24: Post Performance Requirements Document, Revision E. The Government plans to conduct a virtual Industry Day regarding Amendment 24 on March 18, 2026, at 1PM EST. Please email the primary point of contact to participate.

Amendment 25: Post questions and answers related to Performance Requirements Document, Revision E. The Government will conduct vendor One-on-One meetings the week of March 23, 2026. If interested, please email the primary point of contact with your availability.

Update #25 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Amendment 22: Post Acquisition Strategy Update.

Amendment 23: Mission Suitability Section L and M Update.

Amendment 24: Post Performance Requirements Document, Revision E. The Government plans to conduct a virtual Industry Day regarding Amendment 24 on March 18, 2026, at 1PM EST. Please email the primary point of contact to participate.

Update #24 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Amendment 22: Post Acquisition Strategy Update.

Amendment 23: Mission Suitability Section L and M Update.

Update #23 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Amendment 22: Post Acquisition Strategy Update.

Update #22 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Amendment 21: Post slides presented at the American Meteorological Society (AMS) and clarify that there will no longer be an explicit requirement for an Engineering Development Unit or Engineering Test Unit; instead, it will be an Engineering Development Program. The Final Request for Proposal will supersede any statement in Amendment 21.

Update #21 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Amendment 20: Post Acquisition Strategy Update.

Update #20 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Amendment 19: Post the Industry Day presentation for Amendment 18 and associated Performance Requirements Document Questions and Answers.

Update #19 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Amendment 18: The Government will host a virtual Technical Industry Day on January 21 at 12:00 PM EST. Vendor one-on-one meetings will follow on January 21 and 22. To participate, please email the designated point of contact and include your availability for January 21 and 22.

Update #18 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Amendment 17: Post the Industry Day presentation for Amendment 16.

Update #17 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2.

Amendment 16: Post Acquisition Strategy Change and Draft Request for Proposal Questions and Answers.

Update #16 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Amendment 15: Post DRFP Amendment 13, Questions and Answers 1 and 2

Update #15 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Amendment 14: Post the Industry Day presentation for Amendment 13.

Update #14 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Amendment 13: Post draft RFP update and extend the response deadline to October 6, 2025. The Government plans to conduct a virtual Industry Day regarding Amendment 13 on September 9, 2025, at 3PM EST. Please email the primary point of contact to participate.

Update #13 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Amendment 12: Given the changes to the SMBA contract type, the draft RFP response deadline is extended to September 30, 2025. This date will allow sufficient time for the Government to update its documents to align with the new approach and for potential offerors to provide feedback.

Update #12 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Amendment 11: 

The National Environmental Satellite, Data, and Information Service (NESDIS) perspective on the go-forward is the following:

  1. Multi-phase, Multi-select Acquisition
  2. Phase 1
    • Number of contractors: Up to two contractors
    • Period of Performance: Through Engineering Test Unit (ETU) development and environmental testing
    • Scope: Includes long lead items for ETU and Flight Models 1-4; and all associated reviews through Contract Data Requirements List (CDRL) item RE-13: ETU Test Summary Review Package delivery
    • Contract Type: Cost Reimbursement
  3. Down-Select for Phase 2
    • Point in time: Occurs at approximately contract authorization to proceed (ATP) plus two years
    •  Evaluation Criteria: Will include Critical Design Review (CDR) package, ETU test data, forward plans, and other related items. However, these evaluation factors are not final and NASA reserves the right to change them at any time, up to and including the date upon which Phase 2 proposals are requested.
  4. Phase 2
    • Number of contractors: one contractor
    • Period of Performance: Flight Model 1 forward
    • Contract Type: Fixed Price

The Government procurement team will proceed with this go-forward plan while the leadership chain is briefed. The go-forward plan may change during this process. Changes to the go-forward plan (if any) or contract documents will be posted as soon as they are available.

Update #11 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Amendment 10: SMBA may start as a Cost Plus development but will transition to a Fixed Price contract type. The Government is also considering a multi-award with a down-select at approximately Critical Design Review. More information will be provided as soon as it becomes available.

Update #10 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Amendment 9: Extend the Draft RFP response date for vendor feedback to June 30, 2025. Potential offerors should anticipate changes to the contract type among other aspects of the Draft RFP. The Government will release changes upon approval.

Update #9 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Amendment 8: Post Questions and Answers 1-4

Update #8 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Amendment 7:  Potential offerors should continue the request in Amendment 4, but omit the portion addressing severability. This entails providing the feedback in Items 1 and 2 for a Firm Fixed Price contract type.

Update #7 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Amendment 6: Provide Attachment N documents: 1. Goddard Procedural Requirements (GPR) 7120.4E - Risk Management Procedural Requirements; and 2. 470-LEO-ANYS-0018, Revision -, Radiation Environment for the Low Earth Orbit Programs Division Near Earth Orbit Network Program Assets.

Update #6 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Amendment 5: 1. Update Attachment J - Contract Work Breakdown Structure; and 2. Add Enclosure 1 - Performance Evaluation Plan, Enclosure 2 - Cost Exhibits 1-7, Enclosure 3 - Past Performance Questionnaire, and Enclosure 4 - Financial Capability Disclosure.

Update #5 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Amendment 4: The Government is contemplating a Firm Fixed Price contract with severable funding.

This entails a Contract Line Item Number (CLIN) structure where funding must be obligated and expended within the timeframe specified by the appropriations type. Please provide feedback on: 1. Positive and negative effects on your business from this contract structure; and 2. Preferred CLIN structure in this scenario (e.g, broken out by milestones, etc...) To ensure your feedback is considered, provide feedback as soon as possible, even if it’s separate from the Draft RFP response.

Update #4 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Amendment 3:   Extend the Draft RFP response date for vendor feedback to May 30, 2025.

Update #3 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Amendment 2:  1. Attach "SMBA Post-DRFP Industry Day Slides.pdf"; 2. Update the planned release timeframe for the final Request for Proposal to Calendar Year 2025, Quarter 4; and 3. Note: The Government may share major changes between the Draft and Final Request for Proposal as an amendment to this posting.   

Update #2 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Amendment 1: Virtual Industry Day - Please refer to the document entitled, "Post-DRFP Industry Day.pdf" for instructions

Update #1 ·

THIS IS NOT A REQUEST FOR PROPOSAL. NO PROPOSALS ARE TO BE SUBMITTED IN RESPONSE TO THIS NOTICE.

This notice is issued by the NASA/GSFC to post a Draft RFP to solicit responses from interested parties. This document is for information and planning purposes and to allow industry the opportunity to verify reasonableness and feasibility of the requirement, as well as promote competition.

This Draft RFP is for the Sounder for Microwave-Based Applications (SMBA) requirement. The principal purpose of this requirement is to design, develop, and support the SMBA instruments under the Near Earth Orbit Network (NEON) program.

This presolicitation synopsis is not to be construed as a commitment by the Government, nor will the Government pay for the information submitted in response. The Government may not respond to questions/concerns submitted. The Government will use the information to finalize the RFP as necessary.

All comments or questions shall be submitted electronically via email to Bruce Tsai at Bruce.B.Tsai@nasa.gov no later than 5:00 PM Eastern Time on May 9, 2025. When responding, reference DRFP-NEON-SMBA-2025.

NASA Clause 1852.215-84, Ombudsman, is applicable. The Center Ombudsman for this acquisition can be found at: https://www.hq.nasa.gov/office/procurement/regs/Procurement-Ombuds-Comp-Advocate-Listing.pdf

If a solicitation is released, then it and any additional documents will be available on Sam.gov. It is the offeror's responsibility to monitor this website for the release of the solicitation and amendments (if any). Potential offerors will be responsible for downloading their own copy of the solicitation and amendments, if any.

NASA intends to publicize a listing of respondents to facilitate teaming arrangements. Should your firm desire not to be included in this listing, clearly indicate this desire in your response.

Files

File Type Posted
Amnt 26 - Industry Day - Recent Updates (20260318).pdf PDF
Amnt 25 - Technical QA for PRD Rev E.pdf PDF
Amnt 24 - SMBA PRD Rev E.pdf PDF
Amnt 23 - MS Sections L and M.pdf PDF
Amnt 22 - Acquisition Strategy Update.pdf PDF
Knizhnik - AMS2026 - Streamlining Sounder for Microwave-Based Applications (SMBA)_Updated.pdf PDF
NS1-SMBA-SOW-0002C_01152026.pdf PDF
NS1-SMBA-CDRL-0001C_01152026.pdf PDF
Amnt 20 - Acquisition Strategy Update.pdf PDF
Technical QA topics for PRD.pdf PDF
Industry Day for PRD Change Summary.pdf PDF
Draft RFP Amendment 16 Industry Day v3 01052026.pdf PDF
Amendment 16 - Acq Strategy Change and DRFP QA.pdf PDF
Amendment 15 - Amendment 13 QA 1 and 2.pdf PDF
Amendment 13 - Industry Day.pdf PDF
Amnt13 - Attachment C - Non-Technical Contract Data Requirements List.pdf PDF
Amnt13 - Attachment D - OCI Plan.pdf PDF
Amnt13 - DRD 1 - OCI Plan.pdf PDF
Amnt13 - DRD 3 - SCV Reporting.pdf PDF
Amnt13 - Attachment L - Contractor Proposed Enhancements.pdf PDF
Amnt13 - DRD 2 - Security Requirements for Unclassified IT Resources.pdf PDF
Amnt13 - Attachment E - C-SCRM Plan.pdf PDF
Amnt13 - Attachment N - Applicable Documents List.pdf PDF
Amnt13 - Attachment F - Safety and Health Plan.pdf PDF
Amnt13 - Attachment M - Reserved.pdf PDF
Amnt13 - Attachment O - Down-Select Sections L and M.pdf PDF
Amnt13 - Attachment H - Requirements Statements List.pdf PDF
Amnt13 - NS1-SMBA-REQ-0001C_NS1 SMBA PRD_08192025_revised.pdf PDF
Amnt13 - Attachment P.2-P.10 Payment Schedules (CLIN 0004-0012).pdf PDF
Amnt13 - NS1-SMBA-CDRL-0001B_NS1 SMBA CDRL_08192025.pdf PDF
Amnt13 - Attachment P.1 Payment Schedules (CLIN 0001).pdf PDF
Amnt13 - Enclosure 5 - CWBS.pdf PDF
Amnt13 - Enclosure 1 - Reserved.pdf PDF
Amnt13 - Enclosure 2 - Cost Exhibits 1-7.xlsx XLSX spreadsheet
Amnt13 - DRFP Cover Letter - 80GSFC25R7005 SMBA (Amendment 13).pdf PDF
Amnt13 - Enclosure 3 - Past Performance Questionnaire.pdf PDF
Amnt13 - RFP - 80GSFC25R7005 SMBA (20250829).pdf PDF
Amnt13 - Enclosure 4 - Financial Capability Disclosure.pdf PDF
Amnt13 - NS1-SMBA-SOW-0002B_NS1 SMBA SOW_08192025.pdf PDF
Amnt13 - Attachment B - Financial Management Reporting Requirements.pdf PDF
Amnt13 - Attachment G - Small Business Subcontracting Plan.pdf PDF
Amnt13 - Attachment I - Government Furnished Property.pdf PDF
Amnt13 - Attachment J - Reserved.pdf PDF
Amnt13 - Attachment K - TM Rate Matrices.pdf PDF
Amnt13 - SF33-22 - 80GSFC25R7005 SMBA.pdf PDF
SMBA DFRP QA 1-4.pdf PDF
GPR-7120.4E.pdf PDF
470-LEO-ANYS-00018 - Radiation Environment.pdf PDF
Enclosure 1 - Performance Evaluation Plan.pdf PDF
Enclosure 2 - Cost Exhibits 1-7.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

Notice history

Notice Type Posted
Near Earth Orbit Network Program's Sounder for Microwave-Based Applications Latest solicitation Solicitation
This notice Pre-Solicitation
Near Earth Orbit Network Program's Sounder for Microwave-Based Applications Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Ground Systems and Mission Operations-4 (GSMO-4) United States · NAICS 541330 Goddard Space Center No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity