Amnt 25 - Technical QA for PRD Rev E.pdf

PDF 145 KB Posted

Attached to
Draft RFP - Near Earth Orbit Network Program's Sounder for Microwave-Based Applications
Solicitation number
DRFP-NEON-SMBA-2025
Issued by

About this file

This is a Technical Q&A document for the NS1 NEON Sounder for Microwave-Based Applications (SMBA) Performance Requirements Document (PRD), Revision E, updated March 12, 2026. The document clarifies calculation methodologies and technical requirements rather than specifying products or services. It addresses how Noise Equivalent Differential Temperature (NEDT) is calculated for both heritage and non-heritage microwave radiometer channels, with thermal noise dominating total NEDT alongside 1/f noise components. The document provides detailed equations and three worked examples demonstrating NEDT thermal noise calculations using bandwidth and integration time parameters, as well as 1/f noise ratio calculations capped at 0.1 per requirement SMBA-30 for all channels.

The Q&A further clarifies that the spatial horizontal resolution requirement (SMBA-44) applies to instantaneous field of view at nadir rather than aggregated footprint measurements, following traditional imaging practices to ensure no spatial gaps in along-scan or along-track directions. The passband gain ripple requirement (SMBA-41) is design-agnostic, allowing compliance through either hardware or software approaches. The PRD accommodates flexibility regarding instrument power status at launch, permitting designs that require either powered ON or OFF configurations. The document notes that in case of discrepancies, final Request for Proposal provisions and contract terms take precedence.

View the file

Other files

File Type Posted
Amnt 23 - MS Sections L and M.pdf PDF
Amnt 22 - Acquisition Strategy Update.pdf PDF
NS1-SMBA-SOW-0002C_01152026.pdf PDF
Technical QA topics for PRD.pdf PDF
Amendment 15 - Amendment 13 QA 1 and 2.pdf PDF
Amendment 13 - Industry Day.pdf PDF
Amnt13 - DRFP Cover Letter - 80GSFC25R7005 SMBA (Amendment 13).pdf PDF
Amnt13 - RFP - 80GSFC25R7005 SMBA (20250829).pdf PDF
Amnt13 - NS1-SMBA-SOW-0002B_NS1 SMBA SOW_08192025.pdf PDF
Amnt13 - Attachment B - Financial Management Reporting Requirements.pdf PDF
Amnt13 - Attachment G - Small Business Subcontracting Plan.pdf PDF
Amnt13 - Attachment I - Government Furnished Property.pdf PDF
Amnt13 - Attachment J - Reserved.pdf PDF
Amnt13 - Attachment K - TM Rate Matrices.pdf PDF
Amnt13 - SF33-22 - 80GSFC25R7005 SMBA.pdf PDF
Amnt13 - DRD 1 - OCI Plan.pdf PDF
Amnt13 - DRD 2 - Security Requirements for Unclassified IT Resources.pdf PDF
Amnt13 - Attachment F - Safety and Health Plan.pdf PDF
Amnt13 - Attachment H - Requirements Statements List.pdf PDF
Amnt13 - NS1-SMBA-CDRL-0001B_NS1 SMBA CDRL_08192025.pdf PDF
Amnt13 - Enclosure 1 - Reserved.pdf PDF
Amnt13 - Attachment D - OCI Plan.pdf PDF
Amnt13 - Attachment L - Contractor Proposed Enhancements.pdf PDF
Amnt13 - Attachment N - Applicable Documents List.pdf PDF
Amnt13 - Attachment O - Down-Select Sections L and M.pdf PDF
SMBA DFRP QA 1-4.pdf PDF
470-LEO-ANYS-00018 - Radiation Environment.pdf PDF
GPR-7120.4E.pdf PDF
Enclosure 1 - Performance Evaluation Plan.pdf PDF
Enclosure 3 - Past Performance Questionnaire.pdf PDF
Enclosure 2 - Cost Exhibits 1-7.xlsx XLSX spreadsheet
SMBA Post-DRFP Industry Day Slides.pdf PDF
Post-DRFP Industry Day.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
Attachment B - Financial Management Reporting Requirements.pdf PDF
Attachment C - Non-Technical Contract Data Requirements List.pdf PDF
NS1-SMBA-CDRL-0001A_NS1 SMBA CDRL_04102025.pdf PDF
Attachment A - NS1-SMBA-SOW-0002A_NS1 SMBA SOW_04172025.pdf PDF
Attachment G - Small Business Subcontracting Plan.pdf PDF
DRD 2 - Security Requirements for Unclassified IT Resources.pdf PDF
DRD 1 - OCI Plan.pdf PDF
Attachment J - CWBS.pdf PDF
Attachment K - Rates Matrices.pdf PDF
Attachment N - Applicable Documents List.pdf PDF
Attachment F - Safety and Health Plan.pdf PDF
Attachment I - Government Furnished Property.pdf PDF
NS1-SMBA-REQ-0001B_NS1 SMBA PRD_04172025.pdf PDF
DRD 3 - SCV Reporting.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
DRFP - 80GSFC25R7005 SMBA (20250418).pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated March 12, 2026

Technical Q&A for NS1 NEON SMBA PRD

NS1-SMBA-REQ-0001 Rev E

Below are questions and answers related to the Sounder for Microwave-Based Applications (SMBA) Performance Requirements Document (PRD), Revision E. In the event of any discrepancy, the final Request for Proposal provisions and contract terms will take precedence.

Question: How is the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 calculated for heritage and non-heritage channels? How is the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓 calculated?

Answer: Microwave radiometer total noise 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 is commonly dominated by thermal noise 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 and 1/f noise 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓 and may be calculated by:

SMBA PRD Equation 5: 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 = �(𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒)2 + (𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓)2�1/2

The thermal noise, 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒, can be calculated by:

𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 = 𝑇𝑇ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝑡𝑡𝑡𝑡 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁

√𝐵𝐵×𝜏𝜏

Where the “Thermal Noise Contribution to 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁” is the value in the 4th column of Table 4.1-4, B is the channel bandwidth (the sum of all passbands in the channel) in MHz, and 𝜏𝜏 is the integration time in ms.

𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 is then scaled for the SMBA design and sets the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 limit.

For heritage channels, the channel bandwidth and the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 requirements are listed in Table 4.1-3 and the integration time is established by the SMBA proposer’s design.

For non-heritage channels, integration time and channel bandwidth is established by the SMBA proposer’s design and the resulting 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 is reported in CDRL documentation.

For 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓, SMBA-30 applies to both heritage and non-heritage channels.

The 1/f noise ratio, 𝑅𝑅1/𝑓𝑓 , can be calculated from

SMBA PRD Equation 6: 𝑅𝑅1/𝑓𝑓 = (𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓)2

𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁2

Example 1: Thermal Noise Contribution to 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 = 21.6𝐾𝐾 taken from Table 4.1-4 for V-band < 56 GHz, 𝐵𝐵 = 180 𝑀𝑀𝑀𝑀𝑀𝑀, and using 𝜏𝜏 = 18 𝑚𝑚𝑚𝑚 as an example, from the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒equation above, the resulting 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 = 0.3795𝐾𝐾.

Example 2: From Example 1, using 𝑅𝑅1/𝑓𝑓 = 0.1 as the max allowed by SMBA-30, with 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 = 0.4 K from Table 4.1-3, SMBA PRD Equation 6 can be used to solve for 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓.

𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓 = �𝑅𝑅1/𝑓𝑓 × 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 = 0.1265𝐾𝐾

Example 3: Using the results from Examples 1 & 2, the 𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 can now be computed using SMBA PRD Equation 5.

𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 = �(𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒)2 + (𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁1/𝑓𝑓)2�1/2 = [(0.3795)2 + (0.1265)2]1/2 = 0.4𝐾𝐾

Question: Does the spatial horizontal resolution requirement (SMBA-44) apply to instantaneous footprint or aggregated footprint?

Answer: The spatial horizontal resolution requirement (SMBA-44) applies at an instant of time (i.e., Instantaneous Field of View) rather than over the time duration of a footprint.

IFOV is the portion of the Earth’s surface enclosed by the projected -3dB antenna contour at an instant of time (i.e., instantaneous footprint). An IFOV does not include smearing due to scanning or satellite orbital movement, nor any aggregating or spatial resampling of different footprints.

SMBA follows traditional practice of using the IFOV to check compliance with requirements for imaging without spatial gaps in the along-scan or along-track directions. The SMBA footprint size requirements (SMBA-42 and SMBA-44) must be met at the IFOV level at nadir.

Question: Is compliance to the new passband gain ripple requirement (SMBA-41) constrained to front end hardware design?

Answer: SMBA-41 is agnostic of hardware design and/or software design choices employed to comply.

Question: Will the SMBA instrument be powered ON or OFF during launch?

Answer: PRD is written to be inclusive of instrument designs that require being powered ON and instrument designs that require being OFF at launch.

File details come from the government source that posted it. Updated .