AZ flap 439(1) & 202(1), martinez lake & red cloud mine road
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF19B000024
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Access to Imperial National Wildlife Refuge Yuma, Arizona, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks offers to perform road construction services along approximately 9.1 miles of Martinez Lake Road and Red Cloud Mine Road in Yuma County, Arizona. The work includes minor road realignments, paving existing asphalt and gravel sections, drainage upgrades such as culvert replacement and installation, and must be completed between November 2019 and September 2020. Significant work elements involve quantities of 33,000 tons of asphalt, 97,000 tons of aggregate base, and 219,000 cubic yards of excavation. Bids were due December 3, 2019.
The solicitation is set aside for total small business concerns. The primary NAICS code is 237110 for water and sewer line and related structures construction, and PSC codes include 8105 for road construction and repair services. The incumbent contractor is Show Low Construction, Inc. The estimated value is between $15-20 million. The place of performance encompasses approximately 9.1 miles along Martinez Lake Road and Red Cloud Mine Road near the Imperial National Wildlife Refuge in Yuma, Arizona.
Notice text
5 versions
Update #5 · Latest ·
Note: Amendment A001 is re-attached without restrictions.
Amendment A002 extends the bid opening to 12/3/2019.
DRAINAGE, EARTHWORK, AGGREGATE BASE, ASPHALT SURFACING, BOX CULVERTS, AND CATTLE GUARDS
Update #4 ·
Note: Amendment A001 is re-attached without restrictions.
DRAINAGE, EARTHWORK, AGGREGATE BASE, ASPHALT SURFACING, BOX CULVERTS, AND CATTLE GUARDS
Update #3 ·
DRAINAGE, EARTHWORK, AGGREGATE BASE, ASPHALT SURFACING, BOX CULVERTS, AND CATTLE GUARDS
Update #2 ·
THIS IS AN INVITATION FOR BID, PLANS AND SPECS ARE AVAILABLE AT THIS TIME.
This project consists of minor realignment and paving of approximately 6 miles of existing asphalt paved roadway and 2.1 miles of gravel roadway leading to Imperial National Wildlife Refuge within Yuma County, Arizona. An additional length of approximately 1 mile will be a full realignment for a total project length of approximately 9.1 miles. Work also includes drainage improvements, including culvert replacement and constructing new culverts.
SIGNIFICANT QUANTITIES:
33,000 tons of asphalt concrete pavement, gyratory mix,
97,000 tons of aggregate base,
22,000 tons of cement treated aggregate course,
219,000 cubic yards of roadway excavation,
5,200 linear feet of guardrail,
4,600 cubic yards of riprap,
2,000 linear feet of concrete box culverts, and
4,400 linear feet of metal pipe culverts.
MISCELLANEOUS: Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to refuge visitors throughout construction and achieve customer satisfaction.
Update #1 ·
THIS IS NOT AN INVITATION FOR BID, PLANS AND SPECS ARE NOT AVAILABLE AT THIS TIME.
This project consists of minor realignment and paving of approximately 6 miles of existing asphalt paved roadway and 2.1 miles of gravel roadway leading to Imperial National Wildlife Refuge within Yuma County, Arizona. An additional length of approximately 1 mile will be a full realignment for a total project length of approximately 9.1 miles. Work also includes drainage improvements, including culvert replacement and constructing new culverts.
The estimated price range is between $15,000,000 and $20,000,000. The anticipated advertisement date is mid October 2019 with construction anticipated from November 2019 to September 2020.
SIGNIFICANT QUANTITIES:
33,000 tons of asphalt concrete pavement, gyratory mix,
97,000 tons of aggregate base,
22,000 tons of cement treated aggregate course,
219,000 cubic yards of roadway excavation,
5,200 linear feet of guardrail,
4,600 cubic yards of riprap,
2,000 linear feet of concrete box culverts, and
4,400 linear feet of metal pipe culverts.
MISCELLANEOUS: Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to refuge visitors throughout construction and achieve customer satisfaction.
Files
Show all 12
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ flap 439(1) & 202(1), martinez lake & red cloud mine road | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity