AZ_FLAP_439(1)_&_202(1)_Questions_and_Answers_during_Advertisement_.pdf

PDF 75 KB Posted

Attached to
AZ FLAP 439(1) & 202(1), MARTINEZ LAKE & RED CLOUD MINE ROAD
Solicitation number
6982AF19B000024
Issued by

About this file

This document contains questions and answers regarding a federal transportation project in Arizona. The project consists of improvements to approximately 9.1 miles of roadway in Yuma County, including minor realignment, paving of asphalt and gravel sections, and drainage upgrades. One question asked if reinforced concrete pipe could be substituted for specified corrugated metal pipe and end sections, to which the response indicated that pipe requirements are as stated in the project plans, and that contractors may reference the value engineering provision if proposing alternatives.

11/7/19 Question and Answer during Advertisement

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for AZ FLAP 439(1) & 202(1), Martinez Lake & Red Cloud Mine Road

November 7, 2019

Questions Answers

We are a precast manufacture that will be bidding on the box culverts shown on the Martinez Lake & Red Cloud project over in Yuma, Az. After reviewing project, I noticed there’s some Corrugated Metal Pipe and End Section. Will DOT allow Reinforced Concrete Pipe in lieu of the Corrugated Metal?

The pipe culvert requirements will be as called out on the project plans. If the contractor desires to use reinforced concrete pipe, they should reference FP Section 103.03 Value Engineering.