This document provides details for a federal contract solicitation to perform road construction work. The solicitation seeks offers for a project consisting of road realignment and paving of approximately 9.1 miles of existing asphalt and gravel roads leading to Imperial National Wildlife Refuge in Yuma County, Arizona. Significant work includes providing 33,000 tons of asphalt concrete pavement; 97,000 tons of aggregate base; 22,000 tons of cement treated aggregate course; 219,000 cubic yards of roadway excavation; 5,200 linear feet of guardrail; 4,600 cubic yards of riprap; 2,000 linear feet of concrete box culverts; and 4,400 linear feet of metal pipe culverts. Construction phasing and traffic control will be important to minimize disruptions during performance from November 2019 to September 2020. Offers are due by December 3, 2019.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AZ FLAP 439(1) & 202(1) Martinez Lake and Red Cloud Mine Road
SOLICITATION, OFFER
AND AWARD
(Construction, Alteration or Repair)
1. SOLICITATION NO.
6982AF19B000024
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
10/23/2019
PAGE OF
PAGES
IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
HFLCEO190292PR
6. PROJECT NO.
AZ FLAP 439(1) & 202(1) Martinez Lake and Red Cloud Mine Road
7. ISSUED BY:
FEDERAL HIGHWAY ADMINISTRATION
CENTRAL FEDERAL LANDS DIVISION
12300 WEST DAKOTA AVENUE, SUITE 167
LAKEWOOD, COLORADO 80228
CODE: 69050001 8. ADDRESS OFFER TO:
Eric Grosskreuz, Acquisition Program Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228
9. FOR INFORMATION CALL
SEE PAGE A-3
A. NAME:
SEE PAGE A-3
B. TELEPHONE NO. (Include area code)
SEE PAGE A-3
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:
ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:
1. FEDERAL ACQUISITION AND TRANSPORATION ACQUISITION REGULATIONS (FAR & TAR)
2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENT RATES
3. SPECIAL CONTRACT REQUIREMENTS
4. PLANS
5. BID SCHEDULE
6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY
PROJECTS, FP-14, U.S. CUSTOMARY UNITS
See Subsection 104.04 of the FP-14 for governing order of precedence
11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 1:00 p.m. (hour) local time on 12/3/19 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is is not required.
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-102 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53-236-1(e)
X
X
X
X
X
A-1 Amendment A003
11/21/19
D‐1 Amendment A003 11/21/19
WAGE DETERMINATIONS
Davis-Bacon Act WD # AZ20190008 Wage Determination Modification # Construction Highway Last Revised Date Nov 01, 2019
States and Counties
State Arizona Counties Coconino, Maricopa, Mohave, Pima, Pinal, Yavapai, Yuma
"General Decision Number: AZ20190008 11/01/2019
Superseded General Decision Number: AZ20180008
State: Arizona
Construction Type: Highway
Counties: Coconino, Maricopa, Mohave, Pima, Pinal, Yavapai and Yuma Counties in Arizona.
HIGHWAY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year
D‐2 Amendment A003 11/21/19
2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/04/2019 1 02/08/2019 2 03/08/2019 3 07/19/2019 4 07/26/2019 5 11/01/2019
CARP0408-005 07/01/2019
Rates Fringes
CARPENTER (Including Cement Form Work).......................$ 28.08 12.74
ENGI0428-001 07/01/2019
Rates Fringes
POWER EQUIPMENT OPERATOR
Group 1.....................$ 25.94 11.04 Group 2.....................$ 29.21 11.04 Group 3.....................$ 30.29 11.04 Group 4.....................$ 31.32 11.04
POWER EQUIPMENT OPERATORS CLASSIFICATIONS:
GROUP 1: A-frame boom truck, air compressor, Beltcrete, boring bridge and texture, brakeman, concrete mixer (skip type), conductor, conveyor, cross timing and pipe float, D‐3 Amendment A003 11/21/19 curing machine, dinky (under 20 tons), elevator hoist (Husky and similar), firemen, forklift, generator (all), handler, highline cableway signalman, hydrographic mulcher, joint inserter, jumbo finishing machine, Kolman belt loader, machine conveyor, multiple power concrete saw, pavement breaker, power grizzly, pressure grout machine, pump, self-propelled chip spreading machine, slurry seal machine (Moto paver driver), small self-propelled compactor (with blade-backfill, ditch operation), straw blower, tractor (wheel type), tripper, tugger (single drum), welding machine, winch truck
GROUP 2:
ALL COUNTIES INCLUDING MARICOPA: Aggregate Plant, Asphalt plant Mixer, Bee Gee, Boring Machine, Concrete Pump, Concrete Mechanical Tamping-Spreading Finishing Machine, Concrete Batch Plant, Concrete Mixer (paving & mobile), Elevating Grader (except as otherwise classified), Field Equipment Serviceman, Locomotive Engineer (including Dinky 20 tons & over), Moto-Paver, Oiler-Driver, Operating Engineer Rigger, Power Jumbo Form Setter, Road Oil Mixing Machine, Self-Propelled Compactor (with blade-grade operation), Slip Form (power driven lifting device for concrete forms), Soil Cement Road Mixing Machine, Pipe-Wrapping & Cleaning Machine (stationary or traveling), Surface Heater & Planer, Trenching Machine, Tugger (2 or more drums).
MARICOPA COUNTY ONLY: Backhoe < 1 cu yd, Motor Grader (rough), Scraper (pneumatic tired), Roller (all types asphalt), Screed, Skip Loader (all types 3<6 cu yd), Tractor (dozer, pusher-all).
GROUP 3:
ALL COUNTIES INCLUDING MARICOPA: Auto Grade Machine, Barge, Boring Machine (including Mole, Badger & similar type directional/horizontal), Crane (crawler & pneumatic 15>100 tons), Crawler type Tractor with boom attachment & slope bar, Derrick, Gradall, Heavy Duty Mechanic-Welder, Helicopter Hoist or Pilot, Highline Cableway, Mechanical Hoist, Mucking Machine, Overhead Crane, Pile Driver Engineer (portable, stationary or skid), Power Driven Ditch Lining or Ditch Trimming Machine, Remote Control Earth Moving Machine, Slip Form Paving Machine (including Gunnert, Zimmerman & similar types), Tower Crane or similar type.
D‐4 Amendment A003 11/21/19
MARICOPA COUNTY ONLY: Backhoe<10 cu yd, Clamshell < 10 cu yd, Concrete Pump (truck mounted with boom only), Dragline <10 cu yd, Grade Checker, Motor Grader (finish-any type power blade), Shovel < 10 cu yd.
GROUP 4: Backhoe 10 cu yd and over, Clamshell 10 cu yd and over, Crane (pneumatic or crawler 100 tons & over), Dragline 10 cu yd and over, Shovel 10 cu yd and over.
All Operators, Oilers, and Motor Crane Drivers on equipment with Booms, except concrete pumping truck booms, including Jibs, shall receive $0.01 per hour per foot over 80 ft in addition to regular rate of pay
Premium pay for performing hazardous waste removal $0.50 per hour over base rate.
* IRON0075-004 08/01/2019
COCONINO, MARICOPA, MOHAVE, YAVAPAI & YUMA COUNTIES
Rates Fringes
Ironworker, Rebar................$ 27.80 19.05
Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson Zone 2: 050 to 100 miles - Add $4.00 Zone 3: 100 to 150 miles - Add $5.00 Zone 4: 150 miles & over - Add $6.50
* LABO1184-008 06/01/2019
Rates Fringes
Laborers:
Group 1.....................$ 20.18 5.71 Group 2.....................$ 20.18 5.71 Group 3.....................$ 20.88 5.71 Group 4.....................$ 21.82 5.71 Group 5.....................$ 22.68 5.71
LABORERS CLASSIFICATIONS:
GROUP 1: All Counties: Chipper, Rip Rap Stoneman. Pinal County Only: General/Cleanup Laborer. Maricopa County
D‐5 Amendment A003 11/21/19
Only: Flagger.
GROUP 2: Asphalt Laborer (Shoveling-excluding Asphalt Raker or Ironer), Bander, Cement Mason Tender, Concrete Mucker, Cutting Torch Operator, Fine Grader, Guinea Chaser, Power Type Concrete Buggy
GROUP 3: Chain Saw, Concrete Small Tools, Concrete Vibrating Machine, Cribber & Shorer (except tunnel), Hydraulic Jacks and similar tools, Operator and Tender of Pneumatic and Electric Tools (not herein separately classified), Pipe Caulker and Back-Up Man-Pipeline, Pipe Wrapper, Pneumatic Gopher, Pre-Cast Manhole Erector, Rigger and Signal Man-Pipeline
GROUP 4: Air and Water Washout Nozzleman; Bio-Filter, Pressman, Installer, Operator; Scaffold Laborer; Chuck Tender; Concrete Cutting Torch; Gunite; Hand-Guided Trencher; Jackhammer and/or Pavement Breaker; Scaler (using boson's chair or safety belt); Tamper (mechanical all types).
GROUP 5: AC Dumpman, Asbestos Abatement, Asphalt Raker II, Drill Doctor/Air Tool Repairman, Hazardous Waste Removal, Lead Abatement, Lead Pipeman, Process Piping Installer, Scaler (Driller), Pest Technician/Weed Control, Scissor Lift, Hydro Mobile Scaffold Builder.
PAIN0086-001 04/01/2017
Rates Fringes
PAINTER
PAINTER (Yavapai County only), SAND BLASTER/WATER BLASTER (all Counties)......$ 19.58 6.40
ZONE PAY: More than 100 miles from Old Phoenix Courthouse $3.50 additional per hour.
SUAZ2009-001 04/20/2009
Rates Fringes
CEMENT MASON.....................$ 19.28 3.99
D‐6 Amendment A003 11/21/19
ELECTRICIAN......................$ 22.84 6.48
IRONWORKER (Rebar) Pima County.................$ 23.17 14.83 Pinal County................$ 20.27 8.35
LABORER
Asphalt Raker...............$ 15.49 3.49 Compaction Tool Operator....$ 14.59 2.91 Concrete Worker.............$ 13.55 3.20 Concrete/Asphalt Saw........$ 13.95 2.58 Driller-Core, diamond, wagon, air track............$ 16.94 3.12 Dumpman Spotter.............$ 14.99 3.16 Fence Builder...............$ 13.28 2.99 Flagger Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 12.35 1.59 Formsetter..................$ 16.09 3.97 General/Cleanup Laborer Coconino, Maricopa, Mohave, Pima, Yavapai & Yuma.......................$ 14.54 3.49 Grade Setter (Pipeline).....$ 17.83 5.45 Guard Rail Installer........$ 13.28 2.99 Landscape Laborer...........$ 11.39 Landscape Sprinkler Installer...................$ 15.27 Pipelayer...................$ 14.81 2.96 Powderman, Hydrasonic.......$ 16.39 2.58
OPERATOR: Power Equipment Asphalt Laydown Machine.....$ 21.19 6.05 Backhoe < 1 cu yd Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 17.37 3.85 Backhoe < 10 cu yd Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.72 3.59 Clamshell < 10 cu yd Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.72 3.59 Concrete Pump (Truck Mounted with boom only) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 19.92 7.10
D‐7 Amendment A003 11/21/19
Crane (under 15 tons).......$ 21.35 7.36 Dragline (up to 10 cu yd) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.72 3.59 Drilling Machine (including Water Wells).....$ 20.58 5.65 Grade Checker Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 16.04 3.68 Hydrographic Seeder.........$ 15.88 7.67 Mass Excavator..............$ 20.97 4.28 Milling Machine/Rotomill....$ 21.42 7.45 Motor Grader (Finish-any type power blade) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 21.92 4.66 Motor Grader (Rough) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 20.07 4.13 Oiler.......................$ 18.15 8.24 Power Sweeper...............$ 16.76 4.44 Roller (all types Asphalt) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.27 3.99 Roller (excluding asphalt)..$ 15.65 3.32 Scraper (pneumatic tired) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 17.69 3.45 Screed Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 17.54 3.72 Shovel < 10 cu yd Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.72 3.59 Skip Loader (all types <3 cu yd)......................$ 18.28 5.30 Skip Loader (all types 3 < 6 cu yd) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 18.64 4.86 Skip Loader (all types 6 < 10 cu yd)...................$ 20.15 4.52 Tractor (dozer, pusher -all) Coconino, Mohave, Pima, Pinal, Yavapai & Yuma......$ 17.26 2.65
D‐8 Amendment A003 11/21/19
PAINTER
Coconino, Maricopa, Mohave, Pima, Pinal & Yuma..$ 15.57 3.92
TRUCK DRIVER
2 or 3 Axle Dump or Flatrack....................$ 16.27 3.30 5 Axle Dump or Flatrack.....$ 13.97 2.89 6 Axle Dump or Flatrack (< 16 cu yd)...................$ 17.79 6.42 Belly Dump..................$ 14.67 Oil Tanker Bootman..........$ 22.03 Self-Propelled Street Sweeper.....................$ 13.11 5.48 Water Truck 2500 < 3900 gallons.....................$ 18.14 4.55 Water Truck 3900 gallons and over....................$ 15.92 3.33 Water Truck under 2500 gallons.....................$ 15.94 4.16
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after
D‐9 Amendment A003 11/21/19 award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates
D‐10 Amendment A003 11/21/19 the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
D‐11 Amendment A003 11/21/19 and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"