This document summarizes bids received for the AZ FLAP 439(1) & 202(1), MARTINEZ LAKE & RED CLOUD MINE ROAD federal contract opportunity. Six contractors submitted bids for the project to perform minor realignment and paving of approximately 9.1 miles of existing asphalt and gravel roads in Yuma County, Arizona, including drainage improvements and installing new culverts. Kirkland Construction, LLLP provided the highest bid at $25,939,239.25, while Show Low Construction, Inc. submitted the lowest bid at $20,941,541.10. The engineer's estimate for the project was $19,180,325. Significantly, the work involves approximately 33,000 tons of asphalt, 97,000 tons of aggregate base, 22,000 tons of cement treated aggregate course, and 219,000 cubic yards of roadway excavation, along with metal pipes and concrete box culverts. The contract is being awarded through the Federal Highway Administration for the Arizona Department of Transportation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Opening Summary
Project Name: Martinez Lake and Red Cloud Mine Road Project Number: AZ FLAP 439(1) & 202(1)
Bid Opening Date: 12/3/19 Time: 1:00 p.m.
Bid Opening Location: Lakewood, CO Bid Opening Officer: Eric Grosskreuz
Amendments:
Bidder’s Name Bid Total
1. Kirkland Construction, LLLP Rye, CO
A: $18,033,325.20 X: $ 5,962,266.60 Y: $ 1,765,910.05 Z: $ 177,737.40 Total: $25,939,239.25
2. Show Low Construction, Inc.
Show Low, AZ
A: $14,735,587.46 X: $ 4,691,324.11 Y: $ 1,358,378.53 Z: $ 156,251.00 Total: $20,941,541.10
3. Pyramid Construction and Aggregates, Inc.
Heber, CA
A: $20,457,803.80 X: $ 5,695,304.73 Y: $ 3,041,972.45 Z: $ 249,194.27 Total: $29,444,275.25
4. Stormwater Plans, LLC dba Contracting and Paving Glendale, AZ
A: $20,800,495.00 X: $ 4,648,369.00 Y: $ 3,584,198.00 Z: $ 942,510.00 Total: $29,975,572.00
5. InterMountain West Civil Constructors, Inc.
Mesa, AZ
A: $13,413,826.20 X: $ 4,672,304.70 Y: $ 1,641,674.80 Z: $ 241,528.40 Total: $19,969,334.10
6. Steve Manning Construction, Inc.
Redding, CA
A: $17,305,151.00 X: $ 5,358,271.00 Y: $ 2,347,034.00 Z: $ 322,214.00 Total: $25,332,670.00
Engineer’s Estimate
A: $12,630,166.00 X: $ 4,605,342.00 Y: $ 1,746,805.00 Z: $ 198,012.00 Total: $19,180,325.00
All bids subject to verification
File details come from the government source that posted it. Updated .