WWCX151009-RepairArcticFoundationB4002-Specifications_rev2.pdf

PDF 8 MB Posted

Attached to
Repair Arctic Foundation Bldg 4002 (WWCX 15-1009) Pituffik Space Base, Greenland - Amendment 0001
Solicitation number
FA252325R0002
Issued by

About this file

This document is a detailed solicitation for repairs to the Arctic Foundation of Building 4002 at Pituffik Space Base, Greenland, issued by the Department of the Air Force under Solicitation Number FA252325R0002. The project requires comprehensive repairs to the facility's arctic foundation, including clearing arctic ducts and headers of debris, installing new dampers, actuators, motors, controllers, and associated equipment to create a complete and usable system. The contractor must provide all necessary materials per the drawings and specifications, with a contract performance period of 240 days.

Specific requirements include providing 10% additional components (bolts, nuts, washers for arctic air stacks, dampers, and actuators) as bench stock for the base maintenance contractor, with all materials to be properly labeled with project number, building number, date, and functional description. The work involves detailed technical specifications for installation, environmental considerations, safety protocols, and compliance with various federal and military standards. The project will be located at Pituffik Space Base, situated at 76°32' North latitude, 68°50' West longitude, which presents unique logistical and environmental challenges for construction and material delivery.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 01 00-1

WWCX 15-1009 - REPAIR ARCTIC FOUNDATION, B4002

SECTION 01 01 00

GENERAL REQUIREMENTS

1. DEFINITION OF INSTALLATION: Installation will be defined as the property and facilities located within the jurisdiction of the particular base, post, air station, or compound where work is being accomplished. Pituffik Space Base is located at 76 32’ North latitude, 68 50’ West longitude. Pituffik Space Base and PSB refer to the same location and incorporate the Thule defense area.

2. PRECEDENCE: Individual and installation-specific specification sections shall take precedence over the general requirements in this section when in conflict.

3. PROJECT DESCRIPTION: The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of maintenance, repair, and minor construction work on various real property facilities at installations covered under this contract, to include design and engineering services. The Contracting Officer (CO) will conduct negotiations with the Contractor and issue the contract documents with the contract award to include these specifications.

4. CONTRACT DOCUMENTS, REFERENCE STANDARDS, AND PUBLICATIONS

4.1 The following documents are a part of the solicitation and any resultant contract. The Contractor shall utilize the referenced documents in the accomplishment of tasks prescribed in TOs. The standards and publications listed in each section of the specifications form part of these specifications to the extent referenced. The Contractor shall conform to the provisions of the most recent issue at contract solicitation of the listed standard or publication unless specifically noted otherwise.

4.2 Specification: The specifications are taken from the Unified Facilities Guide Specifications (UFGS). The UFGS website is http://www.wbdg.org. The specifications have been edited for this specific contract and will remain unchanged throughout the contract unless officially modified.

4.3 Unified Facilities Criteria (UFC): UFC’s shall be used as the standard building code for all construction under this contract. The website is http://www.wbdg.org. Any and all changes to UFC’s will immediately become requirements of this contract at the time of solicitation.

4.4 Installation Design Standards: Installation’s standards shall be adhered to on all construction projects. Any possible deviations from these standards shall be brought to the CO before implementation.

5. PRE-PERFORMANCE MEETING: Before work begins on this contract, the Contracting Officer will arrange for a meeting with the Contractor to discuss the contract in general, including administrative matters, project requirements, submittal procedures, approval and http://www.wbdg.org/ccbU20T http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4U20T

01 01 00-2 payment schedule, quality control expectations, request for proposal and TO procedures, traffic control, construction access requirements, as-built criteria, performance requirements, security procedures, accident prevention, safety, and fire prevention briefings.

6. BUSINESS TELEPHONE: At the beginning of this contract, the Contractor shall provide the Contracting Officer a Contractor personnel telephone number, e-mail, and website for regular working hours. The Contractor shall also provide after hours (emergency) telephone numbers for the Program Manager and Installation Construction Manager, as a minimum. Whenever changes in personnel or phone numbers occur, the Contractor shall provide the CO with an updated phone list within 14 calendar days. The Contractor is required to provide a means of mobile communications (i.e., cellular phone and/or pager) for the Program Manager and Installation Construction Manager, Superintendent, Quality Control Officer, and their respective alternates, for the life of the contract. Communications equipment will require special coordination and clearance with installation communications authorities.

7. WORK HOURS:

7.1 The Contractor shall complete work between the hours of 7:00 a.m. and 6:00 p.m. local time, excluding Sundays, and Federal Holidays unless otherwise agree with the CO. Access to work sites may be restricted to these hours and days unless previously agreed. Work that requires inspection during accomplishment or that prevents inspection of other work after accomplishment must be coordinated with and approved in advance by the Contracting Officer or Subject Matter Expert (SME). Inclement weather, operational delays, and security related delays might affect the Contractor’s work periods. The Contractor must make allowances for these events, as resulting lost time will not be reimbursable in either days granted or dollars.

7.2 The US Government only recognizes the following legal holidays established by federal statute:

New Year's Day, 1 January Martin Luther King Jr. Day, third Monday in January Washington’s Birthday, third Monday in February Memorial Day, last Monday in May Juneteenth National Independence Day, 19 June Independence Day, 4 July Labor Day, first Monday in September Columbus Day, second Monday in October Veteran's Day, 11 November Thanksgiving Day, fourth Thursday in November Christmas Day, 25 December

8. WORK INTERRUPTIONS AND DELAYS: The Contractor may be required to temporarily stop work for operational requirements, special events, installation exercises, or while Distinguished Visitor (DV) familiarization visits/tours are conducted. Official late reporting and weather calls will affect the Contractor’s work periods. The Contractor must make allowances for these events and resulting lost time will not be reimbursable. Notification to the Contractor

01 01 00-3 shall be provided by the applicable Contracting Officer.

9. FIRE PROTECTION: The Contractor shall be responsible for furnishing adequate and proper fire protection for all phases of the contract work in accordance with UFC 3-600-01 and National Fire Protection Association (NFPA) standards. See Section 01 35 29, Safety and Health Requirements.

10. FAIR OPPORTUNITY PROPOSAL REQUEST (FOPR):

10.1 Project Documents: The Contractor will be furnished with one electronic copy of the Statement of Work (SOW), drawings, specifications, and a Submittal Schedule, as available.

The level of the design provided to the Contractor shall be anywhere from a basic concept to a complete design package. The Contractor may reproduce the drawings and specifications at the Contractor’s own expense if additional copies are needed. The Contractor shall check all drawings and specifications immediately upon receipt for discrepancies and notify the CO immediately of any/all discrepancies found in the form of a Request for Information (RFI).

Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall compare all drawings and verify the installation before laying out the work and shall be responsible for any errors which might have been avoided thereby.

10.2 Site Visit: Prior to negotiations, the Government and the Contractor may conduct a pre-proposal site visit. Discussions may include, but are not limited to: scope of work, method of construction, sequence of operations, progress schedule, means of access to project site, delivery and storage of materials and equipment, work restrictions, coordination requirements, project goals, liquidated damages, and potential difficulties/problems. The Contractor shall email detailed site visit minutes to the Contracting Officer within three (3) workdays following the site visit. The Contracting Officer, or designated representative, will provide meeting notes to all Contractors and the Civil Engineer Squadron (CES) within five (5) workdays of the site visit.

10.3 On-Site Conditions: Drawings showing the location of equipment, piping, ducts and conduit, etc. may be diagrammatic and may not show every detail required. In addition, site conditions will not always permit installation in the locations shown. Drawings showing equipment, piping, ducts, conduit, etc., to be removed, altered, or installed may require deviation from the configuration of the demolition or installation drawings due to existence of conflicting ducts, conduits, hangers, light fixtures, structural items, and temporary walls, etc. All such minor details of work which are not shown on the drawings, as well as such items not specifically mentioned in the specifications, but which are essential and necessary for the completion of the work, and to make all systems or equipment operational, shall be considered as incidental and shall be included as part of the work. When this situation occurs, the final placement of permanently installed items shall be subject to approval by the applicable CO. The Contractor shall be responsible for inspecting to their satisfaction all areas/items of possible conflict. Failure to verify the dimensions and locations will be at the Contractor's risk and shall not relieve the Contractor from accomplishing the work required by the contract.

10.4 Project Proposal:

01 01 00-4

10.4.1 The Contractor shall provide a written proposal describing their approach to the proposed project work described in the Government’s SOW and/or project drawings, if any.

10.4.2 The proposal shall include, but is not limited to, a cover page or pages, project cost estimate, and a narrative. The narrative shall only address concerns or alternative solutions to the Government’s design. If there are no concerns or alternatives, then the Contractor shall so state. The cover page shall include project number, project title, total project cost, and performance period.

10.4.3 Construction Schedule: A construction schedule is required in accordance with FAR

36.515. The construction schedule shall be on an AF Form 3064 or equivalent and completed according to the instructions on the reverse side of the form, or as directed. In addition to the construction schedule, the Contractor shall be required to submit a critical path Gantt chart schedule with milestones for all projects with a performance period of 90 days or more.

10.5 Record Drawings: During the progress of the contract, the Contractor shall keep a set of red-line drawings on the job site. These drawings shall be used to create as-builts. If the Contractor fails to maintain the record drawings as required herein, the Contracting Officer will consider that satisfactory progress has not been achieved for the period in question. Final payment will be withheld until as-built record drawings are submitted and approved by the CO.

10.6 Delivery Of Materials: Delivery of materials and equipment shall be made with a minimum of interference to Government operations and personnel. Contractor shall coordinate with all applicable offices for delivery to the installation, storage area on the installation, and delivery routes on the installation. The CO will assist in coordination with the Contractor to the correct offices.

10.7 Clean-Up:

10.7.1 Hallways, exits, and access routes must be kept free of debris and safe at all times. Prior to departure from the work area each day, the Contractor shall remove and properly dispose of all waste materials or rubbish generated by the project work. Daily cleanup of all job sites includes leaving the affected project area in good state of order. Exterior jobsites shall be properly secured to prevent damage from the elements to include wind/snow/ice. Thorough daily cleanup may be required in certain high-visibility areas on a case-by-case basis as described in the SOW or noted on the drawings.

10.7.2 Upon completion of the project, the Contractor shall conduct a thorough final cleaning.

This shall include normal daily cleanup, vacuuming, dusting, mopping, and all other necessary items as appropriate. Upon Pre-Final Inspection, the work area shall be ready to be occupied by the customer without any additional cleanup.

10.8 Government-Furnished Equipment/Materials: The Contractor with their own forces shall transport all Government furnished equipment (GFE) and/or Government furnished materials (GFM), if any, described in the contract. The GFE/GFM shall be transported from the Government’s storage area to the work site or as indicated on the contract. The Contractor shall

01 01 00-5 follow the instructions of the Contracting Officer regarding the disposition of all Government furnished property not consumed in performance of the contract.

10.9 Equipment and Furniture on the Site: The Contractor shall cover equipment and furniture that is to remain in place within the contract operations area and protect it against damage or loss. Store equipment and furniture that is removed in performance of work where directed, or reuse in work as required by project SOW, drawings, or specifications. Equipment and furniture temporarily removed shall be protected, cleaned, and replaced equal or better than its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.

10.10 Damage to Real Property: Any damage done by the Contractor to existing Government property shall be repaired to prior conditions or better as acceptable to the Contracting Officer.

Match the existing conditions and meet the requirements of these specifications. The Contracting Officer will determine if the repair work done is sufficient. All repair work will be at the Contractor’s expense.

10.11 Covered Chutes: All chutes used for refuse, and the like, shall be covered or of such design to fully confine the material to prevent the dissemination of dust and/or debris.

10.12 Salvageable Items: The Contracting Officer will determine if materials are salvageable or unsalvageable. Salvageable materials shall be managed as directed by the Contracting Officer.

10.13 Trash Removal: Unsalvageable materials shall become the property of the Contractor and disposed of at the Contractor's expense. Materials to be removed shall be removed without damage to adjacent areas. All damage resulting from the removal activity shall be repaired by the Contractor at no cost to the Government. Repair shall be made with materials of like nature, type, and construction as were damaged or exist adjacent to the areas to be repaired.

10.14 Standard Products: Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. All products shall be new unless otherwise directed in the contract SOW/drawings/specifications.

11. ELECTRONIC DOCUMENTS AND CORRESPONDENCE:

11.1 The Contractor shall submit all documents electronically unless noted otherwise in the contract. This requirement is in addition to any other requirement throughout this contract. If any other specification or section requires hard copy documents, the Contractor shall submit these documents in both hardcopy and electronic copy to the Contracting Officer or designated office.

11.2 All documents submitted by the Contractor requiring a signature shall be submitted to the Contracting Officer with an electronic digital signature. All documents submitted by the Contractor requiring further action and signature by the Government shall be capable of being digitally signed and saved by the Government representative(s) as required.

01 01 00-6

11.3 All documents submitted by the Contractor shall follow a standardized file naming convention as indicated herewith. File naming conventions shall be strictly adhered to and may only be modified by the Contracting Officer. File names shall have no spaces. The following items in the below naming conventions are defined as followed:

XXXXYYYYYY = Project number as defined by Civil Engineering Example: WWCX201234

YYYYMMDD = Effective date of document or report

ZZZ = Contractor’s Company Initials

001 = Submittal Number or Serial Report Number

Submittals:

XXXXYYYYYY-FORM#-001 (Brief Description of Submittal) Example: WWCX152579-AF3000-04 CeramicTile

RFIs:

XXXXYYYYYY-RFI-001

Daily Reports:

XXXXYYYYYY-Daily Report-001-YYYYMMDD

Progress Reports:

XXXXYYYYYY-PR-001-YYYYMMDD

Proposals:

XXXXYYYYYY-Proposal#-ZZZ-Document Description

Other Miscellaneous Documents/Reports:

XXXXYYYYYY-FormNumber Or Description-YYYYMMDD

Electronic Correspondence (e-mail):

All electronic correspondence from the Contractor regarding a specific project shall follow a standardized subject line naming convention. File naming conventions shall be strictly adhered to and may only be modified by the Contracting Officer. Subject Line for all electronic correspondence shall be as follows: XXXXYYYYYY Project Title: Subject of E-mail

12. CONCURRENT CONSTRUCTION: Construction work closely related to and/or located at the site of the work under this contract, including other military projects, and normal maintenance and repair work may occur. The Government reserves the right to engage in and to perform work, with its own forces or other Contractor forces, of the same type as the successful offeror without breaching or violating this contract.

01 01 00-7

13. UTILITY SERVICES:

13.1 Availability of Utility Services: All reasonably required amounts of water and electricity, where available, will be made available to the Contractor by the Government from existing system outlets and supplies. The quality, quantity, and consistency of the utilities supplied are not guaranteed. The Contractor shall, at their own expense, make all temporary connections and install distribution lines. All temporary lines shall be installed and maintained by the Contractor in a safe and workmanlike manner subject to approval by the CO and shall be removed by the Contractor in like manner prior to final acceptance of the construction. Where electricity is not readily available the Contractor shall provide their own generator or may rent equipment from the Base Maintenance Contract (BMC). Contractor shall work directly with BMC for renting of equipment and fuel (as described below). Reasonable quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government as determined by the Contracting Officer prior to execution.

13.2 Availability of other Utilities: Arctic diesel fuel is available for purchase from the Base Maintenance Contractor (BMC). Contractor shall work with BMC for purchasing as needed for the contract. Other fuels are available on very limited basis and shall be pre-coordinated in advance with CO if needed. If the contractor expects to use large quantities of fuel they shall coordinate at least 9 months in advance to ensure fuel is readily available on the installation.

13.3 Fire Hydrant Connections: Only compatible adapters shall be utilized for hydrant connections. All connections to fire hydrants shall be provided with a backflow preventor.

Backflow preventor, hoses, valves, and other accessories shall be properly supported during operation to prevent damage to the fire hydrant threads. A hydrant wrench of the correct size shall be used on the hydrant, a contractor provided valve shall be used for any control of the flow. Temporary connections to fire hydrants shall be disconnected at the end of each working day and during freezing temperatures. Any use of fire hydrants shall be coordinated with the Government and the fire department prior to work. Notification by the Contractor to the Government shall be made ten (10) workdays prior to any work.

13.4 Conservation Of Utilities:

13.4.1 The Contractor shall be responsible for operating under conditions that preclude the waste of utilities and shall comply with energy conservation directives for the installation.

13.4.2 Supplemental lighting shall be used only in areas where and when work is actually being performed. When work areas are vacated, lighting shall be turned off.

13.4.3 Mechanical equipment for heating, ventilation, and air conditioning systems shall be adjusted by authorized craftsman only.

13.4.4 Water faucets or valves shall be turned off after the required usage has been accomplished.

13.5 Utility Outages:

01 01 00-8

13.5.1 The Contractor shall request, in writing, any utility outage necessitated by the project work at least 14 calendar days prior to the proposed outage unless otherwise approved in writing by the Contracting Officer. The Contractor shall not operate any valve, circuit breaker, or other utility shut-off device unless approved by the CO. The Contractor shall verify that there are no conflicts with the scheduled outage immediately before shutting off the utility. The Contractor will be responsible to implement lockout/tag out procedures, as needed.

13.5.2 The request shall be directed to the Contracting Officer. It shall reference the contract number; stipulate the specific utility system and/or circuits to be affected; the location of the work; the time, date, and duration of the requested outage for each system; and describe the contingency plans for restoring the utility to service. The request shall be accomplished on the current utility outage request form through the Base Maintenance Contractor (BMC).

13.5.3 Outages shall be kept to a minimum both in number and in duration. Where multiple outages are required, as many outages as can be accurately scheduled shall be submitted as a group.

14. VEHICLES/PARKING: Contractor shall provide contractor vehicles for use during the duration of the project. No government furnished vehicles will be provided. Vehicles may be available for rent through the Base Maintenance Contractor (BMC). Coordinate with BMC for renting and fuel agreements. Parking of Contractor vehicles shall be restricted to the project parking lot at the location designated by the Contracting Officer or 821 SBG. The company name shall be prominently displayed on all construction vehicles at all times. Parking shall not violate fire or safety regulations.

15. TRAFFIC CONTROL: The Contractor shall comply with the recommendations contained in Part 6 of the U S Department of Transportation, Federal Highway Administration Manual on Uniform Traffic Control Devices to ensure proper warnings to motorists and adequate traffic control. All signs, warning lights, barricades, and other traffic control devices shall be provided by the Contractor. The Contractor shall maintain the normal traffic egress to and from the installation during construction at all times. If traffic flow on any roadway or parking area is to be modified for any reason, the Contractor must notify the Government by submitting a traffic coordination plan for approval to the Contracting Officer 14 calendar days prior to commencing with construction activities. The schedule and phasing of roadway lane or parking closure will be discussed in a pre-construction meeting.

16. SANITARY PROVISIONS:

16.1 Use of Government facilities may not be available or allowed. The Contractor shall utilize only those rest rooms designated for their use, provided such usage does not conflict with usage by installation personnel and that such usage does not result in unsanitary conditions or damage to the rest room. In no instance, shall paint or other construction materials be disposed of in the rest room, janitor’s closet, drinking fountain, floor drain, storm drain or any other drain or other fixture within the facility, nor shall fixtures be utilized for cleaning tools or construction equipment.

01 01 00-9

16.2 The Government, at its discretion, may direct the Contractor to provide temporary toilets for the Contractor’s use. When the Contractor provides their own temporary toilets, they shall ensure that they satisfy state and local health requirements for the use of construction personnel.

Location, type, proposed maintenance, etc., shall be approved by the Contracting Officer prior to placing toilets. Temporary toilets shall be promptly removed at the completion of construction. All costs incurred in connection with the temporary toilets shall be borne by the Contractor.

17. ARCTIC ENVIRONMENT CONSIDERATIONS:

17.1 Arctic Clothing: Contractor shall be responsible to ensure all personnel have appropriate cold weather and arctic gear for the environment and the work performed. All personnel shall have appropriate arctic gear during storm season.

17.2 Contractor shall ensure all personnel are properly trained for the hazards associated with the environment and are familiar with the operations on the base to include storm shelters and storm warnings (storm conditions or STORMCON).

18. TOBACCO: The Contractor shall limit smoking and use of tobacco to authorized areas only.

Tobacco use shall be in accordance with applicable installation and DoD policy.

19. SYNONYMOUS TERMS: References to Superintendent are synonymous with Project Superintendent, Installation Construction Manager are synonymous with Project Manager and Quality Control Supervisor, Quality Control Manager, and Quality Manager are synonymous with Quality Control Officer.

END OF SECTION 01 01 00

PAGE IS INTENTIONALLY LEFT BLANK

01 02 05-1

SECTION 01 02 05

SECURITY REQUIREMENTS- PITUFFIK SB

1. SECURITY CLEARANCE AND PERMITS

1.1 Controlled Access Areas: If the location of the work is to be performed under this contract is a “controlled access area”, access to the area by contractor personnel will be in accordance with existing Pituffik SB regulations.

1.2 Passes And Badges: Contractor employees requiring entrance to unrestricted and/or restricted base areas will be required to execute the necessary forms to enter these areas through the Base Contracting Office or authorized representative. The contractor shall return all temporary passes and restricted area badges issued for their personnel upon project completion.

The Contractor is responsible to turn in all security passes and badges from any employee whose employment is terminated before project completion.

1.3 Vehicle Passes: All contractor vehicle drivers are required to execute the necessary forms and provide necessary information to obtain temporary or permanent vehicle passes before driving on Pituffik SB. All vehicles will be properly marked with the company name while on Pituffik SB.

1.4 Vehicle Operation: All contractors that are driving on Pituffik SB shall be properly licensed for the vehicle they are operating. Either proper US, Danish, or Greenlandic license may be accepted.

2. TELEPHONE COMMUNICATIONS SECURITY (COMSEC) MONITORING: Contractor personnel are advised that any time they place a call to or receive a call from a Department of Air Force organization, they are subject to COMSEC procedures, such as monitoring. All communications with Department of Defense (DoD) organizations are subject to COMSEC review. Telecommunications networks are continually subject to intercept by unfriendly intelligence organizations. The DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from or terminating at DoD organizations. The Contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with official DoD information.

3. SECURITY REQUIREMENTS

3.1 Request For Entry: The contractor shall comply with security regulations imposed by the Installation Commander and/or the agency occupying the space where work is to be performed, including any necessary security clearances. Prior to mobilization the Contractor shall provide the Contracting Officer or authorized representative a list of personnel requiring authority to work on Pituffik SB. The list shall be kept current, and the Contracting Officer or authorized representative notified as to any changes on the list.

3.1.1 Danish/Southern Greenlandic Entry: Contractor personnel traveling to Pituffik from Denmark or Southern Greenland shall have the appropriate letter from the Danish Ministry of Foreign Affairs Office authorizing travel to Pituffik. Contractor shall provide a copy of all letters of authorization, forms, and contract information to the Contracting Officer. Contracting Officer will provide appropriate forms and contact information upon request.

3.2 Temporary Closure: The contractor shall be aware that access to some areas will be restricted on a temporary basis and all employees will comply with any 821 SFS personnel or regulations. The pier will be restricted during loading/unloading of materials, equipment, and goods. Contractor shall coordinate with 821 SFS and 821 CE prior to ship departure from port to ensure required personnel have adequate access.

3.3 Circulation Control: Restricted Area Badges for Unescorted Entry only (i.e. not requiring or authorized access to classified information) may be issued to contractor personnel upon special request to the Contracting Officer. Contractor personnel must at a minimum meet the following qualifications for consideration to receiving Unescorted Entry:

3.3.1 Subject will be employed for six or more months.

3.3.2 Contract is for more than six months.

3.3.3 A Tier-1 investigation (formally NACI) is the minimum investigation required for unescorted entry. Pending completion of the open investigation, unescorted entry into restricted areas may be granted after a favorable review and submission of the individual’s personnel security background investigation (SF85, SF85P or SF86), favorable local files check and favorable FBI fingerprint check.

3.3.4 Subject has received a favorable local agency/files check initiated by USAF Security Forces.

3.4 Security Breaches: Whenever facility security is breached to perform work required under this contract, the Contractor will be responsible for providing temporary measures in order to assure security is maintained at the level existing prior to construction. This may include such security items as fencing around a facility or closing all openings in a structure during non-work hours. Contractor shall coordinate a minimum of 15 working days in advance of any breaches with both the Contracting Officer and 821st SFS

4. WORK IN SPECIAL SECURITY AREAS

4.1 Escorts: The contractor may be required to provide escorts for access to secure areas while working in certain facilities at Pituffik SB. Escorts must have unescorted entry and meet the requirements outlined in PSB security instructions.

4.2 Applicable Regulations: AFI 31-101, Chapter 5, Restricted Area Circulation Control Procedures will apply to construction projects within the Pituffik SB.

01 02 05-2

01 02 05-3

5. VEHICLE RESTRICTIONS

5.1 The Installation Commander or designated representative reserves the right to control vehicles wishing to enter Pituffik SB. Any delays caused by contractor vehicle searches will not be claimed against the Government.

5.2 The contractor should be aware that any vehicle may be subject to search by Security Forces when entering, leaving, or while on Pituffik SB.

6. MATERIAL DELIVERY

6.1 Access for materials and equipment is constrained due to the geographical restrictions of Pituffik SB. The contractor shall plan for material delivery through the annual sealift wherever possible. Military airlift may be available depending on the availability of the cargo space but is very costly and will be done at the contractor’s expense unless otherwise approved by the Contracting Officer. The annual sealift operations are limited to summer months only and run from Denmark to Pituffik SB and Virgina to Pituffik SB once per year. Due to the total daylight at Pituffik SB during this time the contractor may schedule continuous loading/unloading of the ships.

6.2 All material entering Pituffik SB is subject to inspection by 821 SFS. Any delays from these inspections will not be considered grounds for an extension or contract delay. It is the contractor’s responsibility to ensure that all material is properly containerized for shipping and properly stored after any inspections.

7. CONTACT INFORMATION: The contractor shall provide a 24-hour, 7-day-a-week contact number to 821 SFS in case of suspicious activity at the construction site or if the site is found insecure. If required by 821 SFS, the contractor will have someone respond to the construction site within 1 hour.

8. CLEAR AREA: The Contractor shall ensure that at the end of the work day all vehicles and materials are keep at a minimum of 82 feet away from all inhabited facilities.

9. RIGHT TO DENY ENTRY: The Installation Commander or designated representative reserves the right to deny entry to any contractor who has derogatory criminal history, and the right to terminate the entry authorization of any contractor employee upon disclosure of information which indicates the individual’s continued entry to Pituffik SB is not in the best interest of national security. Additionally, the violation of or any deviation from established security procedures by the contractor’s employee may result in the confiscation of restricted area badge and the removal from Pituffik SB at the contractor’s expense.

END OF SECTION 01 02 05

WWCX 15-1009 – REPAIR ARCTIC FOUNDATION, B4002

01 11 00-1

SECTION 01 11 00

STATEMENT OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes repairs to the arctic foundation of B4002 as indicated in the drawings and incidental related work. Contractor shall clear arctic ducts and headers of any debris within the areas that are causing more than 10% blockage of the airflow. Contractor shall provide all new dampers, actuators, motors, controllers, equipment, and all associated appurtenances as required for a complete and usable system per the drawings and specifications. Provide all material as needed and as shown in the drawings for a complete and usable facility. Contractor shall provide for an additional 10% of the number of bolts, nuts, and washers for the arctic air stacks (AAS) for bench stock to the base maintenance contractor. Contractor shall provide 10% additional dampers and actuators for bench stock to the base maintenance contractor. All bench stock materials shall be properly labeled with the project number, building number, date, and short description of function.

1.2.2 Period of Performance

Contractor shall have 240 days to perform the work. Contract period of performance may be adjusted IAW these specifications and contract documents as required.

1.2.3 Location

The work is located at the B4002, approximately as indicated. The exact location will be shown by the Contracting Officer and/or 821 SPTS/CE and as shown on the drawings.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Contractor shall post safety signage as required in prominent locations in the work area to adequately inform all occupants of work. Before work is started, arrange with the Contracting Officer, 821 SPTS/CE, and 12 SWS a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

01 11 00-2

1.4 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain and in accordance with the drawings and other specifications.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UTILITIES

Obtain work clearance permits prior to start of excavation and comply with Installation requirements for locating and marking aboveground, underground, and hidden utilities. Verify existing utility locations indicated on contract drawings, within area of work.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting any excavation work.

1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

None.

1.7 GOVERNMENT-INSTALLED WORK

None.

1.8 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver, and off-load the salvaged property at the storage area as identified by the Contracting Officer and/or 821 SPTS/CE. Contractor shall coordinate at least 14 calendar days in advance of any salvage materials delivery with the Contracting Officer and 821 SPTS/CE.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location.

Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

01 11 00-3

Not used.

END OF SECTION 01 11 00

01 11 00-4

01 33 00-1

SECTION 01 33 00

SUBMITTAL PROCEDURES

1. SUBMITTAL REGISTER: Maintain the submittal register as the work progresses. Use the electronic submittal register program furnished by the Government or other format indicated in the TO or approved by the CO.

2. PROCEDURES FOR SUBMISSION

2.1 The Contractor shall submit all items listed or specified for each proposal within 10 working days after award to the CO, or as otherwise established or directed by the CO.

The CO may request submittals in addition to those listed when deemed necessary to adequately describe the work covered in the respective sections. Submittals pertinent to materials and equipment that are subject to advance approval shall be scheduled and made prior to the acquisition or the delivery thereof. Each submittal shall be complete and in sufficient detail for ready determination of compliance with the contract requirements.

Submittals shall include such items as: project schedule, descriptive literature (i.e. catalog cuts, diagrams, operation charts/data); test reports; certificates of compliance; actual material sample; fabricator's drawings; shop drawings; operation and maintenance (O&M) manuals including parts lists, certifications, warranties and other such required submittals.

2.2 The Contractor shall use an electronic AF Form 3000 Material Submittal, for all submittals. A form template will be provided to the Contractor by the CO. Special care should be exercised to ensure proper listing of the specification/drawing reference pertinent for each item submitted. All submittals shall be provided 100% electronically to the CO. Physical samples or other items which are submitted but cannot be sent electronically shall be scanned in color or photographed and the image sent as part of the submittal while the associated physical sample shall be delivered to the CO or COR on site.

2.3 Variations: Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to the Government.

2.4 Proposing Variations: When proposing variation, deliver a written request to the CO with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation. When delivering a variation for approval, the Contractor shall warrant that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work. The Government reserves the right to reject any proposed variation without justification.

2.5 Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.

01 33 00-2

2.6 Ensure no work has begun until submittals for that work have been returned as "approved," or "approved as noted", except to the extent that a portion of work must be accomplished as basis of submittal.

2.7 Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled.

2.8 The Contractor shall be responsible for all scheduling requirements during the construction process. All applicable submittals must be approved prior to construction start. All utility outages or road closures must comply with the applicable local standard.

2.9 Shop drawings shall be accomplished using a computer aided drafting program and plotted to PDF format for review by the Government. Hand-drawn sketches are not allowed.

3. GOVERNMENT ACTIONS

3.1 Submittals marked "approved" or "approved as noted" authorize the Contractor to proceed with work covered unless specified otherwise.

3.2 Submittals marked "disapproved" indicate the submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until resubmittal is approved.

4. QUANTITY OF SUBMITTALS: Submit one electronic copy to the CO for review and approval. Courtesy copies are not to be sent to other Government organizations.

5. APPROVED SUBMITTALS: The CO's approval of submittals shall not be construed as a complete check but will indicate only that the general method of construction, materials, detailing, and other information are satisfactory and the design, general method of construction, materials, detailing, and other information appear to meet the Solicitation and Accepted Proposal. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

6. DISAPPROVED SUBMITTALS: The Contractor shall make all corrections required by the CO and promptly within 10 working days furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the CO.

7. WITHHOLDING OF PAYMENT

01 33 00-3

7.1 Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

7.2 Failure to complete close-out documents shall result in 10% of the contract cost being withheld until all documents are approved.

END OF SECTION 01 33 00

01 35 29-1

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

1.1 REFERENCES

1.1.1 The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only. Unless otherwise noted, the latest published version and/or revision shall be used.

1.1.1.1 AMERICAN SOCIETY OF SAFETY ENGINEERING (ASSE)

a. ASSE A10.32 Personal Fall Protection - Safety Requirements for

Construction and Demolition Operations

b. ASSE A10.34 Protection of the Public on or Adjacent to Construction

Sites

c. ASSE Z359.1 Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components

1.1.1.2 ASME INTERNATIONAL (ASME)

a. ASME B30.22 Articulating Boom Cranes

b. ASME B30.3 Construction Tower Cranes

c. ASME B30.5 Mobile and Locomotive Cranes

1.1.1.3 NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

a. NFPA 10 Standard for Portable Fire Extinguishers

b. NFPA 241 Safeguarding Construction, Alteration, and Demolition

Operations

c. NFPA 51B Fire Prevention During Welding, Cutting, and Other Hot Work

d. NFPA 70 National Electrical Code

e. NFPA 70E Electrical Safety in the Workplace

1.1.1.4 U.S. ARMY CORPS OF ENGINEERS (USACE)

a. EM 385-1-1 Safety -- Safety and Health Requirements

1.1.1.5 U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

a. 29 CFR 1910 Occupational Safety and Health Standards (OSHA)

b. 29 CFR 1910.146 Permit-required Confined Spaces

c. 29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous

Atmospheres in Shipyard Employment

01 35 29-2

d. 29 CFR 1926 Safety and Health Regulations for Construction

e. 29 CFR 1926.500 Fall Protection

1.1.1.6 DANISH WORKING ENVIRONMENT AUTHORITY (WEA)

a. WEA Workplace Denmark - Health and Safety

1.2 SUBMITTALS

1.2.1 Government approval may be required on any of the following items. Items requiring submittals will be listed on the Submittal Register. Provide copies of all submittals per the requirements in Section 01 33 00, Submittal Procedures, or as listed on the Submittal Register.

1.2.1.1 SD-01 Preconstruction Submittals

a. Accident Prevention Plan (APP)

b. Activity Hazard Analysis (AHA)

c. Crane Critical Lift Plan

d. Proof of qualification for Crane Operators

1.2.1.2 SD-06 Test Reports

a. Reports

(1) Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports"

b. Accident Reports

c. Monthly Exposure Reports

d. Crane Reports

e. Regulatory Citations and Violations

1.2.1.3 SD-07 Certificates

a. Confined Space Entry Permit

b. Hot work permit

c. Contractor Safety Self-Evaluation Checklist

d. Submit one copy of each permit/certificate attached to each Daily Report.

1.3 DEFINITIONS

1.3.1 Competent Person for Fall Protection. A person who is capable of identifying hazardous or dangerous conditions in the personal fall arrest system or any component thereof, as well as their application and use with related equipment, and

01 35 29-3 has the authority to take prompt corrective measures to eliminate the hazards of falling.

1.3.2 High Visibility Accident. Any mishap which may generate publicity and/or high visibility.

1.3.3 Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even though provided by a physician or registered personnel.

1.3.4 Operating Envelope. The area surrounding any crane. Inside this "envelope" is the crane, the operator, riggers and crane walkers, rigging gear between the hook and the load, the load and the crane's supporting structure (ground, rail, etc.).

1.3.5 Qualified Person for Fall Protection. A person with a recognized degree or professional certificate and with extensive knowledge, training and experience in the field of fall protection; who is capable of performing design, analysis, and evaluation of fall protection systems and equipment.

1.3.6 Recordable Injuries or Illnesses. Any work-related injury or illness that results in:

1.3.6.1 Death, regardless of the time between the injury and death, or the length of the illness;

1.3.6.2 Days away from work (any time lost after day of injury/illness onset);

1.3.6.3 Restricted work;

1.3.6.4 Transfer to another job;

1.3.6.5 Medical treatment greater than first aid;

1.3.6.6 Loss of consciousness; or

1.3.6.7 A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.

1.3.7 U.S. Army Corps of Engineers (USACE) property and equipment specified in USACE EM 385- 1-1 should be interpreted as Government property and equipment.

1.3.8 Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the six elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;

two-blocking; overload; and/or collision, including unplanned contact between the load, crane, and/or other objects. A dropped load, derailment, two-blocking, overload

01 35 29-4 and collision are considered accidents even though no material damage or injury occur. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.).

1.4 CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST

1.4.1 Contracting Officer will provide a "Contractor Safety Self-Evaluation checklist" to the Contractor at the pre-construction conference. The checklist will be completed monthly by the Contractor and submitted with each request for payment voucher. An acceptable score of 90 or greater is required. Failure to submit the completed safety self-evaluation checklist or achieve a score of at least 90 will result in retention of up to 10 percent of the voucher.

1.5 REGULATORY REQUIREMENTS

1.5.1 In addition to the detailed requirements included in the provisions of this contract, work performed shall comply with Danish WEA, USACE EM 385-1-1, and federal, state, and local, laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply.

1.6 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.6.1 Personnel Qualifications

1.6.1.1 Site Safety and Health Officer (SSHO)

a. Site Safety and Health Officer (SSHO) shall be provided at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety…