Wanoka Campground_Special Provisions_220222.docx
DOCX document 29 KB Posted
- Solicitation number
- 12445523R0006
- Issued by
-
Department of Agriculture Forest Service
About this file
This federal contract opportunity solicitation requests proposals for recreation site improvements projects located at various sites within the Chequamegon-Nicollet National Forests in Minnesota. The scope of work includes trail realignments, road and parking area construction, fencing, signage, vault toilet replacements, campground and road repairs, electrical and wastewater infrastructure, and erosion control. Estimated value is between $1 million and $2 million. The solicitation is a total small business set-aside under NAICS code 237310 for heavy and civil engineering construction, with a size standard of $40.5 million. The federal agency is the US Department of Agriculture Forest Service.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Provisions
Section 633 – Permanent Traffic Control
Add the following paragraph to Subsection 633.05:
633.05 Sign Panels.
Sign panels shall be provided by one of the following pre-approved Forest Service vendors:
| Company Location |
| Comments |
P&M Signs, Inc http://www.pmsignsinc.com 200 E. Broadway, Mountainair, NM 87036 505-847-2850 Fax 844-278-5445 Road signs (Al & plywood), Routed signs (oak, cedar & MDO plywood) and recycled plastic, Pink Rollup and hard side
Wood Products Signs http://www.woodproductsigns.com 4890 County Road 76, Parlin, CO 81239 970-641-1675 Fax 970-641-8107 Road signs (Al & plywood), Routed signs (oak, cedar & MDO plywood) and recycled plastic
Rockart, Inc. Signs & Markers http://www.rockartsigns.com 3006 N Maple St, Mesa, AZ 85215 480-854-3400 Fax 480-832-6390 Flexible markers, decals, recreation symbols, snow poles
Stonehouse Signs, Inc http://www.stonehousesigns.com 521 N. Great Southwest Pkwy., Arlington, TX 76011 1-817-640-0992 Fax 1-817-633-3131 Industrial Safety, Traffic/Parking and Facility Signs
DICKE Safety Products http://www.dicketool.com 1845 Anunsen Street NE, Salem, OR 97303 1-800-333-5641 Fax 503-364-0340 All signs, vests, flagging sets Pink Rollup vinyl signs w/portable stands
Zumar http://www.zumartraffic.com/ 7833 N. 106th Avenue, Glendale, AZ 85307 623 -931-7446 Fax 623-877-7446 Traffic signs, sign hardware, letters & numbers, recreation symbols
Safe-T-Lite https://www.facebook.com/safetlite 1051 N Emerald Ave, Modesto, CA 95351 209-522-8913 Fax 209-522-6935 All signs
Carsonite Composites, LLC http://www.carsonite.com 19845 U.S. Highway 76 Newberry, SC 29108 803-321-1185 Fax 803-276-8940 Flexible fiberglass sign, direct print, and decals, reflective sheeting, sign installation tools
Newman Traffic Signs https://www.newmansigns.com/ 1606 6th Ave SW, Jamestown, ND 58401 1-800-337-9770 Fax 701-952-2405 Metal traffic signs, U channel posts, construction signs
67001 – Vault Toilet Chamber
Description
670.01 This work consists of furnishing and installing a vault toilet chamber for a Gunnison style vault toilet building constructed by CXT Precast Products, bedding material, structure backfill, butyl adhesive sealant tape, and all associated work, materials, and equipment to complete the item. The vault toilet chamber shall be manufactured by:
CXT Incorporated 6701 E. Flamingo Avenue, Building 300 Nampa, ID 83687 CXT Regional Sales Representative: Rich Edwards Phone: 262-321-1421 Email: redwards@lbfoster.com
Material
670.02 Conform to the following Sections as applicable:
| Bedding material | 704.02 |
| Structural backfill | 704.04 |
607.03 General. Precast vault chamber materials shall conform to manufacturer’s requirements for:
a) concrete,
b) reinforcement,
c) caulking, grout, adhesive, and sealer,
d) sealers and curing compounds,
e) polyethylene vault liner.
Construction Requirements
670.04 Conform to the following Sections as applicable:
Structural backfill 208.09, 208.10, 208.11
670.05 General.
a) Bedding. Place and compact the bedding material with at least three passes of a lightweight mechanical tamper, roller, or vibratory system.
b) Precast vault chamber. Conform to the vault toilet chamber manufacturer’s requirements for manufacture, finish, and fabrication.
c) Caulking. Install butyl adhesive sealant tape per manufacturer’s requirements.
670.06 Lifting. Obtain recommended lifting/rigging arrangement information from the vault toilet chamber manufacturer.
The manufacturer recommends providing:
a) Crane of appropriate capacity to lift and place the vault (17,000 lbs.) onto designated site.
b) Four equal lengths of cable or nylon leads for a minimum of 25-feet each.
Measurement
Measure Vault Toilet Chamber pay item by the lump sum.
Payment
The accepted quantity will be paid at the contract price per unit of measurement for Vault Toilet Chamber. Payment will be full compensation for the work prescribed in this Section.
67002 – Remove and Reset Vault Toilet Building
Description
670.01 This work consists of salvaging, transporting, and reinstalling a precast concrete vault toilet building originally constructed by CXT Precast Products, and all associated work, materials, and equipment to complete the item.
Material
Not used.
Construction Requirements
670.01 Salvaging Material. Salvage with reasonable care the building designated to be salvaged. Salvage in readily transportable sections or pieces in accordance with the original manufacturer’s recommendations. Replace or repair members, pins, nuts, plates, related hardware, and building damaged, lost, or destroyed during the salvage operation to the CO’s acceptance. Securely attach parts to adjacent members or pack them in sturdy boxes with the contents clearly marked. The vent stack above the roof may be removed and reinstalled as needed.
Contact the Forest Service Contracting Officer Representative (COR) a minimum of 7 calendar days before moving the vault toilet building to coordinate removal and replacement of the lock on the clean-out cover.
Cleanly remove all existing butyl sealant between the vault chamber and building.
670.02 Lifting. Obtain recommended lifting/rigging arrangement information from the original precast concrete vault toilet building manufacturer:
CXT Incorporated 6701 E. Flamingo Avenue, Building 300 Nampa, ID 83687 CXT Regional Sales Representative: Rich Edwards Phone: 262-321-1421 Email: redwards@lbfoster.com
Inspect the four existing integral lift connections located at each building corner for cracks or other defects in the concrete prior to lifting the building. Break the existing butyl adhesive seal around the entire building perimeter prior to lifting operations.
Utilize the four existing integral lift connections with four lifting plates and four 6-inch long 3/4” coil bolts recommended by the manufacturer. The manufacturer may have lifting plates and coil bolts available for rent. The manufacturer recommends providing:
a) Crane of appropriate capacity to lift and place the building (26,000 lbs.) onto designated site.
b) Four equal lengths of cable or nylon leads for a minimum of 25-feet each.
c) Four softeners (wood or plastic) to protect roof edge where leads make contact if cable is used.
d) Four lifting plates and four 3/4” coil bolts 6-inches long (contact the manufacturer).
670.03 Transporting. Place the building on a trailer with sufficient capacity and secure the load to safely transport to the designated site. Obey all transportation regulations and requirements.
670.04 Placement. Install the butyl adhesive sealant tape (incidental to Vault Toilet Chamber item) on the vault toilet chamber according to the manufacturer’s recommendations. Line up the rear corners of the vault (the containment portion) and floor (by the clean-out and vent stack). Allow the screen section and sidewalks to overhang the vault by several inches.
Check the seal of the containment portion of the vault. Access the vault through the clean-out cover in the back of the building after building placement. Visually verify that there is no light leaking through, except for the riser and vent stack holes. Fill any holes at concrete interfaces from the inside with remaining butyl adhesive sealant tape and press or hammer into cracks.
Measurement
Measure Remove and Reset Vault Toilet Building pay item by the lump sum and includes any rental fees for coil bolts or other equipment.
Payment
The accepted quantity will be paid at the contract price per unit of measurement for Remove and Reset Vault Toilet Building. Payment will be full compensation for the work prescribed in this Section.
Special Provisions Page 3