This Statement of Work (SOW) details an interior painting project for Building 622 at the Presidio of Monterey, California, for the Directorate of Public Works, U.S. Army Garrison. The project involves painting interior walls and ceilings on floors 1 through 4, excluding laundry rooms, with staircase walls to be painted but not their ceilings. The building, constructed in 1971, currently serves as military barracks and administrative offices with deteriorated interior conditions.

Key requirements include conducting lead paint surveys, preparing surfaces through scraping and caulking, relocating furniture, maintaining a clean work site, and completing the project in three phases while the building remains occupied. The contractor must provide all personnel, equipment, and materials, perform work to industry standards, and comply with environmental and safety regulations. Specific floor areas to be painted include 20,161 sq ft on the 2nd and 3rd floors, 11,201 sq ft on the 1st floor, and 9,625 sq ft on the 4th floor. The contract will be a Firm Fixed Price, with multiple submittal requirements including a site-specific safety plan, construction schedule, and environmental protection plan.

View the file

Other files for this federal contract opportunity

Other files attached to Amend-05-Bldg 622 Interior Paint, newest first.
File Type Posted
Solicitation Amendment - W91QF425BA0080005.pdf PDF
Solicitation Amendment W91QF425BA0080005 SF 30.pdf PDF
Attch-1-SOW Bldg 622 Paint Interior Walls and celling-20250825.pdf PDF
Solicitation Amendment W91QF425BA0080002 SF 30.pdf PDF
Attch 6_POM Installation Planning Standards.pdf PDF
Attch 7_POM_ENV_2025.pdf PDF
Attch-8-UPDATED-Questions_Answer-W91QF4-25-B-A008_B-622.pdf PDF
Attch-10-CA20250018.pdf PDF
Solicitation Amendment - W91QF425BA0080004.pdf PDF
Solicitation Amendment W91QF425BA0080001 SF 30.pdf PDF
Solicitation Amendment W91QF425BA0080004 SF 30.pdf PDF
Attch 2_Drawings_20250821.pdf PDF
Attch 3_REVISED-Specifications_Paint_20250821.pdf PDF
Attch 4_ Laydown Area Options.png PNG image
Attch 5_Facility Dashboard_B622.pdf PDF
Solicitation Amendment W91QF425BA0080003 SF 30.pdf PDF
Solicitation Amendment W91QF425BA0080003 SF 30.pdf PDF
Attch 1_SOW_20250821.pdf PDF
Attch 2_Drawings_20250821.pdf PDF
CA20250018.pdf PDF
B630 Rubber Flooring 3.jpg JPG image
Attch 8_Questions_Answers_W91QF425BA008_B622.docx DOCX document
Solicitation Amendment - W91QF425BA0080003.pdf PDF
Attch 3_Specifications_Flooring_Paint_20250821.pdf PDF
Attch 4_ Laydown Area Options.png PNG image
Attch 6_POM Installation Planning Standards.pdf PDF
Attch 5_Facility Dashboard_B622.pdf PDF
Attch 7_POM_ENV_2025.pdf PDF
Solicitation Amendment W91QF425BA0080002 SF 30.pdf PDF
Attch-5-UPDATED-POM SITE VISIT Meeting Location Bldg 326.pdf PDF
Solicitation Amendment W91QF425BA0080001 SF 30.pdf PDF
Attch-5-Site Visit Information.pdf PDF
Solicitation - W91QF425BA008.pdf PDF
Attch-4-CA20250018.pdf PDF
Attch-2-B622 Drawings Repair Flooring-Paint Interior Walls.pptx PPTX presentation
Attch-3-B630 Rubber Flooring 3.jpg JPG image
Attch-1-SOW Bldg 622 Paint Interior Walls-Flooring-REV-2.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

For

Directorate of Public Works, Paint Interior Walls and Ceilings for

Building 622, Presidio of Monterey, California

8 September 2025

Project description: This project of DPW, U.S. Army Garrison is to Paint Interior Walls and Celling on the 1st floor, 2nd floor, 3rd and 4th floor of B622.

1. General:

a. Work to be Done: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to complete all work on painting of all interior walls and cellings, and to do furniture removal, as described below scope of work. The contractor shall perform to the standards in this contract and all works shall comply to the current editions of all applicable codes and standards.

b. Building 622 currently serves as a military barracks and administrative offices for the U.S.

Army. The interior hallways and bedrooms exhibit staining, dirt, and unsanitary conditions.

This project aims to improve the living and working environment for U.S. Army personnel, directly impacting their well-being. Building 622 was constructed in 1971

c. This project aims to improve the interior conditions of Building 622 by applying new paint to the walls, ceilings, and door frames on floors 1 through 4, excluding laundry rooms.

Painting will be completed on staircase walls, but not ceilings.

Building 622 has a unique floor configuration: some sections contain floors 1, 2, and 3, while others contain floors 2, 3, and 4. A 1st and 4th floor are never present in the same section.

This results in the following approximate areas:

2nd Floor: 20,161 sq ft

3rd Floor: 20,161 sq ft

1st Floor: 11,201 sq ft

4th Floor: 9,625 sq ft

2. Scope of Work:

Preparation and Construction are not limited of the following:

Contractor shall perform to the best construction management practice industry standards to paint the interior walls to include but not limited of the following:

a) Contractor shall conduct Interior Paint on all 4 floors of building 622 except laundry rooms. Painting will be completed on staircase walls, but not ceilings within of the staircase.

b) Contractor shall coordinate for furniture relocation. The relocation will be the contractor’s responsibility.

c) Contractor shall conduct painting of the interior walls of all rooms, ceilings to include the hallways on the 1st floor, 2nd floor, 3rd floor and 4th floor except laundry rooms. Painting will be completed on staircase walls, but not the ceilings located in the stairwells. Prior to the commencement of painting, the contactor shall include scraping, caulking, and priming of the walls.

d) Contractor shall conduct lead paint survey test and analysis reports for interior walls. - If paint will be removed, sanded, etc. it will need to be sampled to confirm present or non-

Prescence of lead paint. If lead is present, then a certified contractor must perform the abatement. If paint will not be removed or sanded, and just painted over, then sampling is not required or a certified contractor.

Lead Testing will be required in areas exhibiting any of the following conditions:

Loose, flaking, or peeling paint.

Excessive buildup of old paint creating an uneven surface.

Minor surface imperfections such as dried glue or caulk remnants.

Blistering paint, indicating a potential moisture issue (please note: any moisture issues must be addressed separately).

Additionally, sanding will be required in the following situations:

Following scraping to feather edges for a smooth transition.

On glossy surfaces to “de-gloss” them for improved adhesion.

Over patched areas (spackle or joint compound) to ensure a level surface.

To smooth rough textures (to a degree).

To address minor imperfections like bumps or ridges.

Even on matte surfaces, for light sanding to improve “tooth” and paint adhesion.

Therefore, due to the presence of conditions requiring both scraping and sanding, Lead

Testing is mandatory before commencing any work in the affected areas.

e) Contractor shall provide workmanship warranty of all interior wall paintings.

f) The contractor is responsible for maintaining a clean and debris-free work site at the end of each workday, including the proper movement of all furniture to its original location.

All construction debris and rubbish must be disposed of at an off-post site at no additional cost to the government. Use of government dumpsters for construction material disposal is prohibited.

g) Contractor shall conduct asbestos survey and testing. Asbestos survey and testing minimum of two sections in the hallway and in the conference room flooring.

h) Contractor responsible on furniture relocation.

i) Building 622 will be occupied by the User during interior walls painting work. The contractor shall divide the work at least into three phases. Upon completion of each phase, DPW will receive it from the contractor and hand it over to the unit occupying the building before proceeding to the next phase.

3. Submittal: The contractor shall provide at a minimum the following submittals for review by the Government. The government has ten days to review and return submittals once they approved. Submittals shall be coordinated with COR/Contracting officer to their emails.

a. Site Specific Safety Plan

b. Construction Payment/Performance Bonds

c. Construction project schedule in phases.

d. Materials sample and or cut sheets of paint color design and manufacture’s product.

e. Provide warranties that shall cover all material and labor for repair and replacement.

f. Construction Payrolls

Submittals and Construction Payrolls shall be submitted to the following e-mail address – usarmy.leavenworth.acc-micc.mbx.construction@army.mil

4. Environmental Considerations:

a. General: Project must operate in full compliance with the most recent Federal, State, and local environmental laws, regulations, and programs.

ii. Lead paint and asbestos containing materials shall be handled according to applicable laws and regulations with a lead paint certified contractor.

iii. Prior to commencement of the project, copies of survey results, abatement plans, and contractor certifications shall be submitted to and reviewed by Presidio of Monterey

Environmental Division.

iv. At the completion of the project, copies of air monitoring results and completion reports shall be submitted to the Presidio Environmental Division.

v. All ACM related submittals must be sent to DPW Engineering and DPW

Environmental.

mailto:usarmy.leavenworth.acc-micc.mbx.construction@army.mil

c. Volatile Organic Compounds - Monterey Bay Air Resources District Rule 426 provides volatile organic compound (VOC) content limits for a range of coatings that are applied at the site of the structure and its appurtenances. These limits do not apply to coatings used in shops. Coatings covered under this rule include typical primers, sealers, and topcoats for building floors, walls, ceilings, and roofs; antenna coatings; and curb and pavement coatings. The application or solicitation for application of coatings that exceed the VOC limits is prohibited. Coating containers must be closed when not in use. Thinning of coatings must not cause the applicable VOC limit to be exceeded.

d. Aesthetics/Installation Design Guide: For non-historic buildings and/or buildings outside of the historic district, coordination with Presidio Master Planning Division is required to ensure flooring and other materials are consistent with the Installation Design Guide.

e. Avoidance of Sensitive Habitat: All laydown, equipment, and access will be on paved areas. Any laydown, equipment, and access that needs to be off pavement shall be coordinated with the Presidio Environmental Division prior to initiation of work.

f. Land Restoration: Ensure minimal disturbance to current landscaped and unpaved areas by locating temporary storage, laydown yards, and parking of equipment on pavement/hardscape where possible. Any disturbance or damage to vegetation or surrounding soil, must be restored to its original condition or better using Presidio of

Monterey, Integrated Natural Resource Management Plan (INRMP) approved plants or seed mix. Contact the Presidio Natural Resources Manager (julie.a.parish3@army.mil, 831-242-6736) for assistance with approved plants or seeds.

g. Hazardous Waste: If ACM, LBP, treated wood, oil-based paints, paint thinners, or other hazardous wastes are generated by the project, they shall be handled by a certified contractor in accordance with applicable laws and regulations. The contractor will prepare hazardous waste manifests to be signed by Presidio of Monterey, Hazardous Waste Office

(831-242-7204 or 831-887-8878 with 3 working days prior notice).

5. Contractor requirements after award – Contractor shall brief the COR bi-weekly as to progress schedule. Coordinate with COR on format of meetings (i.e. in person/by e-mail/etc)

6. Period of Performance: See schedule.

7. General Information:

a. Federal Observed Holidays: The Contractor shall not be required to perform repairs or enhancement work on Federal Holidays. Below is the observed holiday’s schedule:

New Year’s Day 1st day of January

Martin Luther King, Jr. Day 3rd Monday of January

President’s Day 3rd Monday of February mailto:julie.a.parish3@army.mil

Memorial Day Last Monday of May

Juneteenth Day 19th day of June

Independence Day 4th day of July

Labor Day 1st Monday of September

Columbus Day 2nd Monday of October

Veteran’s Day 11th day of November

Thanksgiving Day 4th Thursday of November

Christmas Day 25th day of December

b. Hours of Operation: The Contractor is responsible for conducting business, between the hours of 0800 – 1630 Monday thru Friday except Federal Holidays or when the

Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the workforce are essential.

c. Place of Performance: The work to be performed under this contract is at building 622

Presidio of Monterey (POM), California.

d. Quality Control Plan (QCP): The Contractor shall develop and maintain an effective QCP to ensure services are performed in accordance with this SOW. The Contractor shall develop, implement and maintain an effective Quality Control System which includes a written Quality Control Plan (QCP). The QCP shall implement standardized procedure/methodology for monitoring and documenting contract performance to ensure all contract requirements are met. The Contractors’ QCP must contain a systematic approach to monitor operations to ensure acceptable services/products are provided to the

Government. The QCP, as a minimum, shall address continuous process improvement;

procedures for scheduling, conducting and documentation of inspection; discrepancy identification and correction; corrective action procedures to include procedures for addressing Government discovered non-conformances; procedures for root cause analysis to identify the root cause and root cause corrective action to prevent re-occurrence of discrepancies; procedures for trend analysis; procedures for collecting and addressing customer feedback/complaints. The contractor shall upon request provide to the

Government their quality control documentation. After acceptance of the quality control plan the contractor shall receive the Contracting Officer’s acceptance in writing of any proposed change to their QC system.

e. Type of Contract: The Government will award a Firm Fixed Price contract.

f. Security Requirements: The Contractor shall submit a list of employees to the Contracting

Officer Representative (COR) for security access processing and approval. The list shall contain the employee’s full name, state driver’s license number, social security number, and date of birth. Contractor personnel shall be prepared to be searched by the installation security guard force.

g. Physical Security: The contractor shall be responsible for safeguarding all Government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment and materials shall be secured.

h. Inspection and Acceptance: The contractor shall coordinate with the COR for completion inspection on each phase of construction and final close-out inspection and acceptance at each of the project.

i. Safety Requirements: No person shall be subjected to work in an unsafe or dangerous environment. Contractor safety will be governed by AR 385-10, paragraphs 3-5, 3-8, and

Chapter 4. AR 385-10 may be made available through the COR upon request.

j. Contracting Officer Representative (COR): The COR will be identified by separate letter.

The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the

Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, and specifications; monitor Contractor's performance and notify both the

Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property; and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially about changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

k. The Contractor shall develop and provide an Environmental Protection Plan (EPP):

The EPP shall clearly demonstrate how the contractor will adhere to environmental compliance requirements, including (but not limited to): air quality; biological resources

(special status species, migratory birds, invasive species, etc.); cultural resources (historic buildings, archaeological sites, Native American sacred sites); hazardous materials and waste (including hazardous materials mitigation plan); noise, non-hazardous solid waste

(including solid waste minimization and diversion plan); spill response; storm water management; traffic; and water resources. The EPP shall be submitted for approval to the

Directorate of Public Works, ATTN: NEPA POC (lauren.r.sullivan.civ@army.mil), Environmental Division, Presidio of Monterey, not later than (NLT) 15 business days following the issuance of the notice to proceed. The EPP does not relieve the Contractor from the requirements of environmental laws and regulations

l. AT Level I Training: All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete

AT Level I awareness training NLT 15 calendar days after contract award start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http//jko.jten.mil.

m. Access and General Protection/Security Policy and Procedure: Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation

Provost Marshall, Director of Emergency Services or Security Office. Contractor workforce shall comply with all personal identity verification requirements (FAR clause

52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

n. Contractors that do not require CAC but require access to a DoD Facility or

Installation: Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center

Interstate Identification Index (NCIC-III) and Terrorist Screening Data Base (TSDB)

(Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or at OCONUS locations, in accordance with status of forces agreement and other regulations.

o. iWATCH Training. The contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the

COR. This training shall be completed NLT 30 calendar days of contract award and NLT

5 calendar days of new employees commencing performance. The results shall be reported to the COR on/or before the timelines stipulated.

p. OPSEC Training: Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees shall complete training within 30 calendar days (if applicable) after their report of duty date and annually thereafter.

q. Personal Identity Verification of Contractor Personnel (Jan 2011) - Clause:

a. The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12

( HSPD-12 ), Office of Management and Budget (OMB) guidance M-05-24, and Federal

Information Processing Standards Publication (FIPS PUB) Number 201.

b. The Contractor shall account for all forms of Government-provided identification issued to the Contractor employees in connection with performance under this contract. The

Contractor shall return such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government.

i. When no longer needed for contract performance.

ii. Upon completion of the Contractor employee’s employment.

iii. Upon contract completion or termination.

v. The Contracting Officer may delay final payment under a contract if the Contractor fails to comply with these requirements.

vi. The Contractor shall insert the substance of clause, including this paragraph, in all subcontracts when the subcontractor’s employees are required to have routine physical access to a Federally controlled facility and/or routine access to a Federally controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the

Contracting Officer.