Attch-2-B622 Drawings Repair Flooring-Paint Interior Walls.pptx

PPTX presentation 263 KB Posted

Attached to
Amend-05-Bldg 622 Interior Paint Federal contract opportunity
Solicitation number
W91QF425BA008
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis

View the file

Other files for this federal contract opportunity

Other files attached to Amend-05-Bldg 622 Interior Paint, newest first.
File Type Posted
Solicitation Amendment W91QF425BA0080005 SF 30.pdf PDF
Attch-1_SOW-Bldg 622 Interior Paint-20250908.pdf PDF
Solicitation Amendment - W91QF425BA0080005.pdf PDF
Solicitation Amendment W91QF425BA0080003 SF 30.pdf PDF
Solicitation Amendment W91QF425BA0080002 SF 30.pdf PDF
Attch 6_POM Installation Planning Standards.pdf PDF
Attch 7_POM_ENV_2025.pdf PDF
Attch-8-UPDATED-Questions_Answer-W91QF4-25-B-A008_B-622.pdf PDF
Attch-10-CA20250018.pdf PDF
Solicitation Amendment - W91QF425BA0080004.pdf PDF
Solicitation Amendment W91QF425BA0080001 SF 30.pdf PDF
Solicitation Amendment W91QF425BA0080004 SF 30.pdf PDF
Attch 2_Drawings_20250821.pdf PDF
Attch 3_REVISED-Specifications_Paint_20250821.pdf PDF
Attch 4_ Laydown Area Options.png PNG image
Attch 5_Facility Dashboard_B622.pdf PDF
Attch-1-SOW Bldg 622 Paint Interior Walls and celling-20250825.pdf PDF
Attch 5_Facility Dashboard_B622.pdf PDF
Attch 7_POM_ENV_2025.pdf PDF
Attch 8_Questions_Answers_W91QF425BA008_B622.docx DOCX document
Solicitation Amendment - W91QF425BA0080003.pdf PDF
Attch 3_Specifications_Flooring_Paint_20250821.pdf PDF
Attch 4_ Laydown Area Options.png PNG image
Attch 6_POM Installation Planning Standards.pdf PDF
Solicitation Amendment W91QF425BA0080003 SF 30.pdf PDF
Attch 1_SOW_20250821.pdf PDF
Attch 2_Drawings_20250821.pdf PDF
CA20250018.pdf PDF
B630 Rubber Flooring 3.jpg JPG image
Attch-5-UPDATED-POM SITE VISIT Meeting Location Bldg 326.pdf PDF
Solicitation Amendment W91QF425BA0080002 SF 30.pdf PDF
Attch-5-Site Visit Information.pdf PDF
Solicitation Amendment W91QF425BA0080001 SF 30.pdf PDF
Attch-1-SOW Bldg 622 Paint Interior Walls-Flooring-REV-2.pdf PDF
Attch-3-B630 Rubber Flooring 3.jpg JPG image
Solicitation - W91QF425BA008.pdf PDF
Attch-4-CA20250018.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Flooring on the 1st floor, 2nd floor, and 3rd floor. Contractor shall remove existing carpets, baseboards and VCTs in the bedrooms, hallways, dayrooms and administration rooms. Contractor shall install new rubber flooring and baseboards in the bedrooms, hallways, dayrooms and administration rooms on the 1st, 2nd, 3rd floors. Contractor shall conduct hazmat test two sections on each floor. Contractor shall field verify dimensions.

Interior Painting on the basement, 1st floor, 2nd floor, and 3rd floor. Contractor shall conduct interior paint on the walls of 1st, 2nd and 3rd floors. Contractor shall conduct lead paint test two sections on each floor. Contractor shall field verify dimensions.

image1.tmp