262713 electricity metering.pdf

PDF 13 KB Posted

Attached to
CONSTRUCT USPFO WAREHOUSE
Solicitation number
W91364-09-B-0003
Issued by

About this file

262713 electricity metering.pdf

View the file

Other files

File Type Posted
Bid Abstract 09-B-0003.pdf PDF
SF30Amendment2 09-B-0003.pdf PDF
ADDENDUM NO 03 USPFO Narrative.pdf PDF
ADDENDUM NO 02 USPFO Narrative SENT.pdf PDF
SF30Amendment3 09-B-0003.pdf PDF
09-B-0003 Amendment 3.pdf PDF
ADDENDUM NO 03 CSMS PH II Narrative.pdf PDF
ADDENDUM NO 02 CSMS PH II Narrative SENT.pdf PDF
USPFO WH Addendum.pdf PDF
Bid Questions USPFO WAREHOUSE JACOBS RESPONSES JFK.doc DOC document
e2c23100.PDF PDF
OHARNG-USPFO-G-130W .pdf PDF
OHARNG-USPFO-A-820W .pdf PDF
083730 high speed rolling door.pdf PDF
220523 general duty valves for plumbing piping.pdf PDF
092900 gypsum board.pdf PDF
102113 toilet compartments.pdf PDF
OHARNG-USPFO-A-723W .pdf PDF
270500 common work results for communications.pdf PDF
081113 hollow metal doors and frames.pdf PDF
052100 steel joist framing.pdf PDF
017329 cutting and patching.pdf PDF
220516 expansion fittings and loops for plumbing piping.pdf PDF
104413 fire extinguishing cabinets.pdf PDF
102800 toilet bath and laundry accessories.pdf PDF
077100 roof specialties.pdf PDF
061000 rough carpentry.pdf PDF
USPFO_FA501W.pdf PDF
USPFO_M501W.pdf PDF
USPFO_S252W.pdf PDF
E802.pdf PDF
E104.pdf PDF
055000 metal fabrications.pdf PDF
USPFO_M301W.pdf PDF
OHARNG-USPFO-A-806W .pdf PDF
OHARNG-USPFO-A-213bW .pdf PDF
C603.pdf PDF
263600 transfer switches.pdf PDF
017839 project record documents.pdf PDF
230811 pre-functional checklists mechanical.pdf PDF
093000 tiling.pdf PDF
E401.pdf PDF
013200 construction progress documentation.pdf PDF
260533 raceway and boxes for electrical systems.pdf PDF
OHARNG-USPFO-A-320W .pdf PDF
311000 clearing grubbing.pdf PDF
262413 switchboards.pdf PDF
221319 sanitary waste piping specialties.pdf PDF
USPFO_FA301W.pdf PDF
260500 common work results for electrical.pdf PDF
Show 40 more

Latest 50 of 373 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

ELECTRICITY METERING 262713 - 1

SECTION 262713 - ELECTRICITY METERING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes equipment for electricity metering by Owner.

1.3 DEFINITIONS

A. KY Pulse: Term used by the metering industry to describe a method of measuring consumption of electricity that is based on a relay opening and closing in response to the rotation of the disk in the meter.

B. PC: Personal computer.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: For electricity-metering equipment.

1. Dimensioned plans and sections or elevation layouts.

2. Wiring Diagrams: For power, signal, and control wiring. Identify terminals and wiring designations and color-codes to facilitate installation, operation, and maintenance. Indicate recommended types, wire sizes, and circuiting arrangements for field-installed wiring, and show circuit protection features.

C. Field quality-control reports.

D. Operation and Maintenance Data. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following:

1. Application and operating software documentation.

2. Software licenses.

3. Software service agreement.

4. Hard copies of manufacturer's operating specifications, design user's guides for software and hardware, and PDF files on CD-ROM of the hard-copy Submittal.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

ELECTRICITY METERING 262713 - 2

1.5 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Receive, store, and handle modular meter center according to NECA 400.

1.7 PROJECT CONDITIONS

A. Interruption of Existing Electrical Service: Do not interrupt electrical service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electrical service according to requirements indicated:

1. Notify Construction Manager no fewer than seven days in advance of proposed interruption of electrical service.

2. Do not proceed with interruption of electrical service without Construction Manager's written permission.

1.8 COORDINATION

A. Electrical Service Connections: Coordinate with utility companies and components they furnish as follows:

1. Comply with requirements of utilities providing electrical power services.

2. Coordinate installation and connection of utilities and services, including provision for electricity-metering components.

PART 2 - PRODUCTS

2.1 EQUIPMENT FOR ELECTRICITY METERING BY OWNER

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. E-Mon; a division of Hunt Power.

2. National Meter Industries.

3. Osaki Meter Sales, Inc.

4. Square D; a brand of Schneider Electric.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

ELECTRICITY METERING 262713 - 3

B. General Requirements for Owner's Meters:

1. Comply with UL 1244.

2. Meters used for billing shall have an accuracy of 0.2 percent of reading, complying with requirements in ANSI C12.20.

3. Enclosure: NEMA 250, Type 3R minimum, with hasp for padlocking or sealing.

4. Identification: Comply with requirements in Division 26 Section "Identification for Electrical Systems."

5. Memory Backup: Self-contained to maintain memory throughout power outages of 72 hours, minimum.

6. Sensors: Current-sensing type, with current or voltage output, selected for optimum range and accuracy for meters indicated for this application.

a. Type: Split core.

7. Current-Transformer Cabinet: Listed or recommended by metering equipment manufacturer for use with sensors indicated.

8. Building Automation System (BAS) Interface: One digital KY pulse to a user-definable increment of energy measurement. Match signal to BAS input and arrange to convey the instantaneous, integrated, demand level measured by meter to provide data for processing and possible programmed demand control action by destination system.

C. Kilowatt-hour Meter: Electronic single- and three-phase meters, measuring electricity used.

1. Voltage and Phase Configuration: Meter shall be designed for use on circuits with voltage rating and phase configuration indicated for its application.

2. Display: LCD with characters not less than 0.25 inch high, indicating accumulative kilowatt-hours and current kilowatt load. Retain accumulated kilowatt-hour in a nonvolatile memory, until reset.

3. Display: Digital electromechanical counter, indicating accumulative kilowatt-hours.

D. Kilowatt-hour/Demand Meter: Electronic single- and three-phase meters, measuring electricity use and demand. Demand shall be integrated over a 15-minute interval.

1. Voltage and Phase Configuration: Meter shall be designed for use on circuits with voltage rating and phase configuration indicated for its application.

2. Display: LCD with characters not less than 0.25 inch high, indicating accumulative kilowatt-hours, current time and date, current demand, and historic peak demand. Retain accumulated kilowatt-hour and historic peak demand in a nonvolatile memory, until reset.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

ELECTRICITY METERING 262713 - 4

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with equipment installation requirements in NECA 1.

B. Install meters furnished by utility company. Install raceways and equipment according to utility company's written requirements. Provide empty conduits for metering leads and extend grounding connections as required by utility company.

C. Install modular meter center according to NECA 400 switchboard installation requirements.

3.2 IDENTIFICATION

A. Comply with requirements for identification specified in Division 26 Section "Identification for Electrical Systems."

1. Series Combination Warning Label: Self-adhesive type, with text as required by NFPA 70.

2. Equipment Identification Labels: Adhesive film labels with clear protective overlay. For residential meters, provide an additional card holder suitable for printed, weather-resistant card with occupant's name.

3.3 FIELD QUALITY CONTROL

A. Perform tests and inspections.

1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing.

B. Tests and Inspections:

1. Connect a load of known kilowatt rating, 1.5 kW minimum, to a circuit supplied by metered feeder.

2. Turn off circuits supplied by metered feeder and secure them in off condition.

3. Run test load continuously for eight hours minimum, or longer, to obtain a measurable meter indication. Use test-load placement and setting that ensures continuous, safe operation.

4. Check and record meter reading at end of test period and compare with actual electricity used, based on test-load rating, duration of test, and sample measurements of supply voltage at test-load connection. Record test results.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

ELECTRICITY METERING 262713 - 5

C. Electricity metering will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

END OF SECTION 262713