013200 construction progress documentation.pdf

PDF 30 KB Posted

Attached to
CONSTRUCT USPFO WAREHOUSE
Solicitation number
W91364-09-B-0003
Issued by

About this file

013200 construction progress documentation.pdf

View the file

Other files

File Type Posted
Bid Abstract 09-B-0003.pdf PDF
SF30Amendment2 09-B-0003.pdf PDF
ADDENDUM NO 03 USPFO Narrative.pdf PDF
ADDENDUM NO 02 USPFO Narrative SENT.pdf PDF
SF30Amendment3 09-B-0003.pdf PDF
09-B-0003 Amendment 3.pdf PDF
ADDENDUM NO 03 CSMS PH II Narrative.pdf PDF
ADDENDUM NO 02 CSMS PH II Narrative SENT.pdf PDF
USPFO WH Addendum.pdf PDF
Bid Questions USPFO WAREHOUSE JACOBS RESPONSES JFK.doc DOC document
e2c23100.PDF PDF
OHARNG-USPFO-G-130W .pdf PDF
OHARNG-USPFO-A-820W .pdf PDF
083730 high speed rolling door.pdf PDF
220523 general duty valves for plumbing piping.pdf PDF
092900 gypsum board.pdf PDF
102113 toilet compartments.pdf PDF
OHARNG-USPFO-A-723W .pdf PDF
270500 common work results for communications.pdf PDF
081113 hollow metal doors and frames.pdf PDF
052100 steel joist framing.pdf PDF
017329 cutting and patching.pdf PDF
220516 expansion fittings and loops for plumbing piping.pdf PDF
104413 fire extinguishing cabinets.pdf PDF
102800 toilet bath and laundry accessories.pdf PDF
077100 roof specialties.pdf PDF
061000 rough carpentry.pdf PDF
USPFO_FA501W.pdf PDF
USPFO_M501W.pdf PDF
USPFO_S252W.pdf PDF
E802.pdf PDF
E104.pdf PDF
055000 metal fabrications.pdf PDF
USPFO_M301W.pdf PDF
OHARNG-USPFO-A-806W .pdf PDF
OHARNG-USPFO-A-213bW .pdf PDF
C603.pdf PDF
263600 transfer switches.pdf PDF
017839 project record documents.pdf PDF
230811 pre-functional checklists mechanical.pdf PDF
093000 tiling.pdf PDF
E401.pdf PDF
260533 raceway and boxes for electrical systems.pdf PDF
OHARNG-USPFO-A-320W .pdf PDF
311000 clearing grubbing.pdf PDF
262413 switchboards.pdf PDF
221319 sanitary waste piping specialties.pdf PDF
USPFO_FA301W.pdf PDF
260500 common work results for electrical.pdf PDF
USPFO_S002W.pdf PDF
Show 40 more

Latest 50 of 373 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Preliminary Construction Schedule.

2. Contractor's Construction Schedule.

3. Submittals Schedule.

4. Construction Progress Report.

5. Daily construction reports.

6. Material location reports.

7. Field condition reports.

8. Special reports.

B. Related Sections include the following:

1. Section 013100 "Project Management and Coordination" for submitting and dis-tributing meeting and conference minutes.

2. Section 013300 "Submittal Procedures" for submitting schedules and reports.

3. Section 014000 "Quality Requirements" for submitting a schedule of tests and in-spections.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construc-tion schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activ-ity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construc-tion project where activities are arranged based on activity relationships. Network cal-culations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 2

E. Event: The starting or ending point of an activity.

F. Float: The measure of leeway in starting and completing an activity.

1. Float time belongs to Government.

2. Free float is the amount of time an activity can be delayed without adversely affect-ing the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

G. Fragment: A partial or fragmentary network that breaks down activities into smaller ac-tivities for greater detail.

H. Major Area: A story of construction, a separate building, or a similar significant con-struction element.

I. Milestone: A key or critical point in time for reference or measurement.

J. Network Diagram: A graphic diagram of a network schedule, showing activities and activity relationships.

K. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

1.3 SUBMITTALS

A. Submittals Schedule: Submit five copies of schedule. Quantities of copies to be sub-mitted are for bidding purposes only. Number of copies will be discussed at Pre- Scheduling Conference. Arrange the following information in a tabular format:

1. Scheduled date for first submittal.

2. Specification Section number and title.

3. Submittal category (action or informational).

4. Name of subcontractor.

5. Description of the Work covered.

6. Scheduled date for Contracting Officer's final release or approval.

7. Approval of cost-loaded preliminary construction schedule will not constitute ap-proval of Schedule of Values for cost-loaded activities.

B. Preliminary Network Diagram: Submit three hard copies, large enough to show entire network for entire construction period. Show logic ties for activities.

C. Preliminary Construction Schedule: Submit five copies.

1. Approval of cost-loaded preliminary construction schedule will not constitute ap-proval of Schedule of Values for cost-loaded activities.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 3

D. Preliminary Network Diagram: Submit five copies, large enough to show entire net-work for entire construction period. Show logic ties for activities.

E. Contractor's Construction Schedule: Submit five copies of initial schedule, large enough to show entire schedule for entire construction period.

1. Submit an electronic copy of schedule, using software indicated, on CD-R, and la-beled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label.

F. CPM Reports: Concurrent with CPM schedule, submit five copies of each of the fol-lowing computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, re-maining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

4. Earnings Report: Compilation of Contractor's total earnings from the Notice to

Proceed until most recent Application for Payment.

G. Daily Construction Reports: Submit five copies at weekly intervals.

H. Material Location Reports: Submit five copies at weekly intervals.

I. Field Condition Reports: Submit five copies at time of discovery of differing conditions.

J. Special Reports: Submit five copies at time of unusual event.

1.4 QUALITY ASSURANCE

A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Contracting Officer's request. Scheduling Consultant may be either Contractor em-ployee or subconsultant and shall be approved by Contracting Officer.

B. Prescheduling Conference: Conduct conference at Project site to comply with re-quirements in Section 013100 "Project Management and Coordination." Review meth-ods and procedures related to the Preliminary Construction Schedule and Contractor's Construction Schedule, including, but not limited to, the following:

1. Review software limitations and content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including work stages area separations interim milestones.

4. Review delivery dates for Government-furnished products.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 4

5. Review schedule for work of Government's separate contracts.

6. Review time required for review of submittals and resubmittals.

7. Review requirements for tests and inspections by independent testing and inspect-ing agencies.

8. Review time required for completion and startup procedures.

9. Review and finalize list of construction activities to be included in schedule.

10. Review submittal requirements and procedures.

11. Review procedures for updating schedule.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other re-quired schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SUBMITTALS SCHEDULE

A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, order-ing, manufacturing, fabrication, and delivery when establishing dates.

1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's Construction Schedule.

2. Initial Submittal: Submit concurrently with preliminary network diagram. Include submittals required during the first 60 days of construction. List those required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contrac-tor's Construction Schedule.

2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Procedures: Comply with procedures contained in AGC's "Construction Planning & Scheduling."

B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion and acceptance by the Government.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 5

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Contracting Officer.

2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as sepa-rate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

a. Major or Critical Submittals are identified on Submittal Register found at the end of Section 013300 "Submittal Procedures."

3. Submittal Review Time: Include review and resubmittal times indicated in Section 013300 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.

4. Startup and Testing Time: Include not less than 15 days for startup and testing.

5. Final Completion and Acceptance by the Government: Indicate completion in ad-vance of date established for Final Completion, and allow time for Contracting Of-ficers administrative procedures necessary for certification of Final Completion and Acceptance by the Government.

D. Constraints: Include constraints and work restrictions indicated in the Contract Docu-ments and as follows in schedule, and show how the sequence of the Work is affected.

1. Work under More Than One Contract: Include a separate activity for each con-tract.

2. Work by Government: Include a separate activity for each portion of the Work per-formed by Government.

3. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Limitations of continued occupancies.

c. Uninterruptible services.

d. Partial occupancy before Substantial Completion.

e. Use of premises restrictions.

f. Provisions for future construction.

g. Seasonal variations.

h. Environmental control.

4. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:

a. Subcontract awards.

b. Submittals.

c. Purchases.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 6

d. Mockups.

e. Fabrication.

f. Sample testing.

g. Deliveries.

h. Installation.

i. Tests and inspections.

j. Adjusting.

k. Curing.

l. Startup and placement into final use and operation.

5. Area Separations: Identify each major area of construction for each major portion of the Work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities to provide for the follow-ing:

a. Structural completion.

b. Permanent space enclosure.

c. Completion of mechanical installation.

d. Completion of electrical installation.

e. Substantial Completion.

E. Milestones: Include milestones indicated in the Contract Documents in schedule, in-cluding, but not limited to, the Notice to Proceed, Work accepted by the Contracting Of-ficer prior to Final Completion, and Final Completion and acceptance by the Govern-ment. Interim milestones shall be discussed in the pre-construction meeting.

F. Cost Correlation: At the head of schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of the Work performed as of dates used for preparation of payment requests.

1. Cost reporting and payment procedures shall be discussed at the Pre-Construction meeting.

2. Contractor shall assign cost to construction activities on the CPM schedule. Costs shall not be assigned to submittal activities unless specified otherwise but may, with Architect's approval, be assigned to fabrication and delivery activities. Costs shall be under required principal subcontracts for testing and commissioning activi-ties, operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training (if applicable), in the amount of 5 per-cent of the Contract Sum.

3. Each activity cost shall reflect an accurate value subject to approval by Contracting Officer.

4. Total cost assigned to activities shall equal the total Contract Sum.

G. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.

H. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 7

2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)

A. General: Prepare network diagrams using AON (activity-on-node) format.

B. Preliminary Network Diagram: Submit diagram within 14 days of date established for the Notice to Proceed. Outline significant construction activities for the first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash re-quirement prediction based on indicated activities.

C. CPM Schedule: Prepare Contractor's Construction Schedule using a computer-ized, cost- and resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use no later than 30 days after date of Contract award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable com-pletion dates, regardless of Contracting Officer's approval of the schedule.

2. Conduct educational workshops to train and inform key Project personnel, includ-ing subcontractors' personnel, in proper methods of providing data and using CPM schedule information.

3. Establish procedures for monitoring and updating CPM schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

4. Use "one workday" as the unit of time. Include list of nonworking days and holi-days incorporated into the schedule.

D. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated time duration, sequence requirements, and rela-tionship of each activity in relation to other activities. Include estimated time frames for the following activities:

a. Preparation and processing of submittals.

b. Mobilization and demobilization.

c. Purchase of materials.

d. Delivery.

e. Fabrication.

f. Utility interruptions.

g. Installation.

h. Work by Government that may affect or be affected by Contractor's activi-ties.

i. Testing and commissioning.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 8

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as of-ten as necessary to produce the CPM schedule within the limitations of the Con-tract Time.

4. Format: Mark the critical path. Locate the critical path near center of network; lo-cate paths with most float near the edges.

a. Subnetworks on separate sheets are permissible for activities clearly off the critical path.

E. Initial Issue of Schedule: Prepare initial network diagram from a list of straight "early start-total float" sort. Identify critical activities. Prepare tabulated reports showing the following:

1. Contractor or subcontractor and the Work or activity.

2. Description of activity.

3. Principal events of activity.

4. Immediate preceding and succeeding activities.

5. Early and late start dates.

6. Early and late finish dates.

7. Activity duration in workdays.

8. Total float or slack time.

9. Average size of workforce.

10. Dollar value of activity (coordinated with the Schedule of Values).

F. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:

1. Identification of activities that have changed.

2. Changes in early and late start dates.

3. Changes in early and late finish dates.

4. Changes in activity durations in workdays.

5. Changes in the critical path.

6. Changes in total float or slack time.

7. Changes in the Contract Performance Period.

G. Value Summaries: Prepare two cumulative value lists, sorted by finish dates.

1. In first list, tabulate activity number, early finish date, dollar value, and cumulative dollar value.

2. In second list, tabulate activity number, late finish date, dollar value, and cumula-tive dollar value.

3. In subsequent issues of both lists, substitute actual finish dates for activities com-pleted as of list date.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 9

4. Prepare list for ease of comparison with payment requests; coordinate timing with progress meetings.

a. In both value summary lists, tabulate "actual percent complete" and "cumula-tive value completed" with total at bottom.

b. Submit value summary printouts one week before each regularly scheduled progress meeting.

2.4 REPORTS

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. List of separate contractors at Project site.

3. Approximate count of personnel at Project site.

4. Equipment at Project site.

5. Material deliveries.

6. High and low temperatures and general weather conditions.

7. Accidents.

8. Meetings and significant decisions.

9. Unusual events (refer to special reports).

10. Stoppages, delays, shortages, and losses.

11. Meter readings and similar recordings.

12. Emergency procedures.

13. Orders and requests of authorities having jurisdiction.

14. Change Orders received and implemented.

15. Construction Change Directives received and implemented.

16. Services connected and disconnected.

17. Equipment or system tests and startups.

18. Partial Completions and occupancies.

19. Work accepted by Contracting Officer prior to Final Completion.

B. Material Location Reports: At monthly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, show-ing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabri-cated or stored away from Project site.

C. Field Condition Reports: Immediately on discovery of a difference between field condi-tions and the Contract Documents, prepare and submit a detailed report. Include de-tailed description of differing conditions, together with recommendations for changing the Contract Documents. Provide information on form acceptable to Contracting Offi-cer.

2.5 SPECIAL REPORTS

A. General: Submit special reports directly to Contracting Officer within one day(s) of an occurrence. Distribute copies of report to parties affected by the occurrence.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

CONSTRUCTION PROGRESS DOCUMENTATION 013200 – 10

B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Contracting Officer in advance when these events are known or predictable.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Scheduling Consultant: Engage a consultant, acceptable to Contracting Officer, to provide planning, evaluation, and reporting using CPM scheduling.

1. In-House Option: Government may waive the requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and re-porting techniques. Submit qualifications to Contracting Officer.

2. Meetings: Scheduling consultant shall attend all meetings related to Project pro-gress, alleged delays, and time impact.

B. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

2. As the Work progresses, indicate Actual Completion percentage for each activity.

C. Distribution: Distribute copies of approved schedule to Contracting Officer, Contracting Officer's Representative, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have com-pleted their assigned portion of the Work and are no longer involved in perform-ance of construction activities.

END OF SECTION 013200