AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above referenced solicitation is hereby amended to address requests for information. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-May-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ18B0010

X 9B. DATED (SEE ITEM 11)

04-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-May-2018

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ18B0010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

Requests for Information

1. The prints for building 131 show 1 ¼” Natural gas Piping on MP -101 are we just changing the piping and it shows no point of use. Are we just refeeding something that is existing?? No new units of some kind???

[Answer] Scope of work is indicated by keyed note 9, provide seismic bracing on existing natural gas piping. Existing piping to remain.

2. Questions on the building # 130 bid documents; Drawing CD101, what is the thickness of the existing concrete that is being demolished, as noted by keyed note # 1 ( ? ) [Answer] Refer to Demolition Note 7.

3. Questions on building # 160 bid documents; Drawing CD101, what is the thickness of the existing asphalt and concrete that is being demolished as noted ( ? ) [Answer] Assume 2.5” asphalt / 8” aggregate.

4. Questions on building # 160 bid documents; Drawing CD101, keyed note # 1, what is the extent of the noted “existing floor coating shall be stripped down over entire floor” ( ? ) Does this mean the interior building concrete floor area in its entirety ( ? ) [Answer] All surfaces shall be prepped as required for new floor finishes per the room finish schedule A- 701.

5. Questions on building # 160 bid documents; Drawing CS101, is the bulk of the new paving work shown to be asphalt or concrete ( ? ) The legend items do not match the drawing plan information.

[Answer] Asphalt pavement and sidewalk are shown per the legend. All airfield pavement inside Building 160 shall be “Interior Hangar Slab” and all exterior apron pavement, not shown as asphalt or sidewalk, shall be “Portland Cement Concrete.”

6. Questions on building # 160 bid documents; Drawing SD100, SD101 and SD102, what is the thickness of the existing concrete slabs that are indicated to be removed ( ? ) [Answer] Refer to attached as-built drawings, file entitled “RFI 17 Response Attachment_160 Existing Structural Drawings.pdf”

7. Questions on building # 160 bid documents; Drawing A112, lead lined drywall is there a specification for this lead lined drywall ( ? ) [Answer] Lead lined gypsum board is specified in specification 13 49 00 X-Ray Shielding.

8. Questions on building # 160 bid documents; Drawing A113, general floor plan note # 17. This states to “fill any misc. caps created or existing in existing thermal barrier with spray polyurethane foam insulation” and “if spray polyurethane foam insulation has exposed surface, it will shall be coated with a thermal barrier”. The extent of this work is not detailed within the drawings and we are unable to determine a quantity of work. This filling work and then the application of a thermal barrier should be handled by a defined “allowance” or by a “unit price”. The same note is used at building # 360, drawing A011, at general floor plan note # 18.

[Answer] Contractor shall coordinate new openings/gaps created by new work required by the project.

For existing openings not shown on the drawing, contractor shall assume 250 board feet for each building.

9. Questions on building # 160 bid documents; Drawing A301, section “D1”, a new vertical stair lift is indicated and further detailed on drawing A411. There is a short specification noted on drawing A411.

Should a specification section be added within the specification book ( ? ) [Answer] Basis of design for Vertical Stair Lift is on drawing A-411, specification not required.

10. Questions on building # 160 bid documents; Drawing A301, section “D1”, a new vertical stair lift is indicated and further detailed on drawing A411. There is a short specification noted on drawing A411.

Should a specification section be added within the specification book ( ? ) [Answer] See response to Amendment 0005, Question 9.

11. Questions on building # 360 bid documents; Drawing CD101, what is the thickness of the existing asphalt roadways, asphalt walks and concrete slabs that are indicated to be removed ( ? ) [Answer] Assume 2.5” asphalt / 8” aggregate.

12. Questions on building # 360 bid documents; Drawing SD100, what are the details of the existing concrete trenches that are indicated to be demolished and where are the areas of “concrete trench infill”, noted as “where it occurs” ( ? ) [Answer] All existing concrete trenches shown on drawing SD100 shall be demolished. Refer to attached as-built for additional information on the existing trenches, file entitled “RFI 12 Response Attachment_360 Existing Structural Drawings.pdf”

13. Questions on building # 360 bid documents; Drawing AD001, the notes regarding the existing vertical lift hanger door upgrade work. The basis of design on drawing A201 is noted as “Scantarp”. As they seem to be a European manufacturer for the door fabric material, can you provide the name of the U.S. company that manufactured and possibly installed these fabric doors ( ? ) [Answer] Mega-Door. Contact information provided below:

Kitty Duckett: Kitty.duckett@assaabloy.com Zach Kearney: Zach.kearney@assaabloy.com

ASSA ABLOY Entrance Systems Office: 678-782-4781 Fax: 770-631-5721 PO BOX 2957 - 350 Dividend Drive Peachtree City, Georgia 30269

14. Questions on building # 360 bid documents; Drawing A351, section”A1”, new damproofing work is indicated at the existing exterior foundation frost walls. This damproofing work is not noted on the structural or architectural drawings. Please clarify if the contractor is required to dig around the existing building, apply this new damproofing, backfill the frost walls with a defined material and restore the perimeter area that is disturbed.

[Answer] Damp proofing not required on existing foundations.

15. Questions on building # 360 bid documents; What is the material specification for the “plastic lumber” indicated on drawing A313, A351 and other sheets ( ? ) This material seems to be at the roof edges of the building.

[Answer] Plastic lumber specified in specification 06 10 00 Rough Carpentry, paragraph 2.1.2.

16. Does all the existing exposed structural steel, secondary structural steel, metal roof decking get field painted at buildings # 130, 131, 132, 160 and 360 ( ? ) [Answer] All exposed structural steel, secondary structure (including beams, plates, etc) and metal roof decking shall be painted in spaces with no ceiling.

17. Within specification section 01 33 29, a LEED’s checklist has been included and is noted as “Not in Pursuit of LEED”. What is the contractor’s responsibility in regards to LEED and why is the LEED score sheet included in the bid documents ( ? ) As it seems the owner is “Not in Pursuit of LEED”.

[Answer] This project is not in pursuit of LEED certification. The included Air National Guard Sustainable Design and Energy Conservation Score Sheets for each building serve as a reference and document the compliance through design with the federal requirements for High Performance and Sustainable Buildings (HPSB) Guiding Principles. The project is to be constructed and documented in accordance with the HPSB Guiding Principles as outlined in Section 01 33 29. Please follow the specifications of Section 01 33 29, Sustainability Reporting.

18. Who is responsible for paying the expenses for field quality testing of soils, soil compaction, concrete work, masonry work, structural steel and other work that is defined in the specifications ( ? ) [Answer] The contractor is responsible for all such testing as defined in the specifications and drawings.

19. Who is responsible for paying the expenses for the “special inspection work” that is noted within the drawings ( ? ) [Answer] The contractor is responsible for all such “special inspection work” as defined in the specifications and drawings.

20. The bid solicitation is a total of fifty eight ( 58 ) pages. Is the entire bid solicitation to be part of the bid forms that are to be delivered to the bid opening place specified on June 05 2018 ( ? ) [Answer] The offeror may submit the entire solicitation packet or they may submit just the essential pages, as outlined in the solicitation.

21. The bid solicitation, page 29 of 58, section “52.219-28”, are we correct to believe, as we are not a “small business” that the small business plan is not required unless we are the possible low bidder and that the small business plan would be a “post bid” and “post award” requirement [Answer] Small business subcontracting plans are only applicable to large businesses. If the apparent low bidder is other than a small business, it will be required to submit a small business subcontracting plan prior, which must be approved prior to award of the contract.

22. Please advise whether the AT Level I training certificate will be required for all construction labor force accessing site in addition to the badge applications.

[Answer] Yes, all contractor employees shall complete AT Level I awareness training and follow the base access/badging procedures as outlined in the “AT OPSEC” portion of the solicitation.

23. On Spec Section 01 11 00, para 1.13 requires only one set of full size contract drawings for as-builts, however on Section 01 78 00, para 3.3 is requiring two hard copies of as builts and also requiring "Monthly review of working as-built CAD drawing", please specify the number of required copies and clarify whether CAD as-builts are required on not? If the CAD as-builts are required, please clarify whether CAD as-builts are required to be update monthly during construction or only at the completion of construction?

[Answer] Spec Section 01 11 00, para 1.13 is deleted. Please follow Section 01 78 00, para 3.1 through 3.3 for specific guidance. Provide and maintain 2 hard copies of working as-built drawings. Per para 3.3, transfer the approved working as-built markup drawings to the CAD files monthly and provide 2 copies.

At the completion of construction, follow the final record drawing package requirements detailed in para 3.3.1.

24. Please advise whether Microsoft Project is acceptable to government for schedule preparation? Also advise whether schedule must be cost and labor loaded or not necessary?

[Answer] The government default scheduling software is Primavera P6. Please reference Section 01 32

01, para 2.1.2.2 for requirements for using software other than Primavera. The schedule must be cost loaded but not labor loaded.

25. Is this project to be LEED certified? If not, should we ignore the requirement on some of the specification sections to submit LEED data for products?

[Answer] Please see response to Amendment 0005, Question 17.

26. Can the superintendent or the QC have a dual hat role and be the safety officer?

[Answer] No, the Contractor Quality Control (CQC) Manager, Site Safety and Health Officer (SSHO), and the Project Superintendent roles must be filled be three separate people.

27. Is temporary perimeter construction fences required for each of the buildings on this project? If so, please conform that temporary fencing supported with concrete bases is acceptable around building 130, 131 & 132.

[Answer] Temporary perimeter construction fences are required. The intent of the construction perimeter fence is to delineate appropriate laydown area necessary for successful completion of the contractor work in cooperation with adjacent contract sites and government access. Temporary fencing must be able to support and withstand winds. Concrete or other weighted bases are acceptable around any buildings and are encouraged to allow flexibility to modify the fence layout if needed. Final laydown and fence coordination must be accomplished with the VT ANG through the Contracting Officer Representative. The Government will require access to the north ramp area around building 385 and building 360 either between these buildings (current lane of travel) or other access points for flight line vehicles. This shall be coordinated with all fence placement to maximize laydown area and allow traffic between these two buildings.

28. Para 3.7 of Section 01 50 00 requires GC to Provide a field office for the Government personnel with Cable

Internet service, however, this base as far as we know is not served with commercial internet and the wireless service signal is slow, please advise whether a cellular hotspot service would be acceptable.

[Answer] Cellular hotspot service is acceptable as long as it provides internet service with the highest speeds available to each work station for computer internet capability in accordance with Section 01 50 00, paragraph 3.7.

29. Drawing M-106-D & Drawing M-108-D indicate in Note #4 that the vertical 1 ¼” piping is SDR 11 HDPE, however the BLDG 360 spec and the BLDG 160 spec both state “ pipe in vertical bores greater than 350 feet deep with a SDR of 9.0”. Do we quote SDR 9 or SDR 11?

[Answer] Drawing M-106-D & Drawing M-108-D: Note #4 to is updated to require the vertical 1 ¼” bore piping to be SDR 9 HDPE. All horizontal underground piping shall be SDR 11.

30. We didn’t find any test bore log for geothermal within specs, is the geothermal contractor required to perform testing of the field location for site subsurface conditions? Is there any rock excavation or rock drilling expected?

[Answer] Contractor shall install one test well for verification of design soil characteristics prior to installation of full well field. Test well shall be installed so it can become part of well field. Reference drill log below taken from a test well located near the project site.

31. Drawings E-401/ E402 on all buildings depict Aircraft Position Elevations which include 100 Amp Carts.

Please provide specifications for these devices.

[Answer] Refer to attached basis of design cutsheet, file entitled “RFI 31 Response Attachment_100AMP

CART.pdf”

32. Paragraph 2.2 of specification section 25 10 10 requires specific testing to satisfy cyber security requirements, please advise whether this paragraph is applicable to this project or not. Also confirm that existing VTANG BAS systems has an ATO.

[Answer] The system does not presently have an ATO (Authorization to Operate), but the cybersecurity testing requirements are to ensure that the system provided is a Risk Management Framework (RMF) compliant product that will satisfy the future ATO certification effort. System shall be a homogenous expansion of the existing Schneider Electric Smart Structure BAS (Building Automation System).

(End of Summary of Changes)