This federal contract opportunity announcement provides details for the construction of a new VA medical center campus in Louisville, KY. The project involves relocating medical facility operations to a 34-acre site to accommodate construction of a new 104-bed hospital, parking for 2,600 cars, campus infrastructure including underground utilities, a new central utility plant, laundry facility, roadways, and landscaping. The contract will be a firm-fixed-price contract awarded using best value tradeoff procedures. The solicitation is anticipated for release on December 3, 2020 and will include evaluation of past performance, management, key subcontractor experience, schedule, and small business participation, in addition to price. The project includes options for additional facilities and has a contract duration of 1,554 calendar days. The target contract ceiling is $705 million.
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Construction of the New VA Medical Center (VAMC) Project in Louisville, KY
P2: 453413
Design-Bid-Build RFP
Specifications
Certified Final Design
03 December 2020
W912QR21R0008
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR21R0008_Specs_CT-0000
Section SF 30 - Block 14 Continuation Page (SF 30)
SF1442 CONTINUATION PAGE
Technical inquiries and questions relating to the proposal procedures or bonds are to be submitted via Bidder Inquiry in Projnet at http://www.projnet.org/projnet. Please see Section 00 21 00, PROJNET INSTRUCTIONS for additional information.
Please see FAR 52.236-27 ALT I for Site Visit Information.
The terms bid and proposal are used interchageably in industry and may be used interchangeably throughout this solicitation.
Please note, page numbering in this document may not be accurate.
Section 00 10 00 - Solicitation
PRICE BREAKOUT SCHEDULE
SECTION 00 10 00
PRICE BREAKOUT SCHEDULE
PROJECT: Replacement VA Medical Center
LOCATION: Louisville, KY
PROJECT NUMBER: P2 453413 / VA PN 603-320
OFFEROR:
Item No.
Description Quantity Unit Unit
Price Amount
BASE PROPOSAL
0001 Sitework 1 Job NA $ All costs associated with work beyond a line five feet outside of the exterior walls of the project structures to include, but not limited to, grading, site utilities, site improvements, etc., as indicated in Phase A Volume 10 and Phase B Volume 10 of the plans, unless otherwise not necessary due to combining of the Phases into one project. This Item also is exclusive of all costs associated with the indicated portion of Option D (Salt and Mulch Storage), the indicated portion of Option E (Fencing and Gates), and all of Option F (Landscaping). This Item also is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also includes all costs to grade and permanently seed stabilize areas in lieu of the structures and features associated with all of Option A (Laundry), all of Option B (South Parking Structure), the indicated portion of Option E (Guard Houses), and all of Option F (Landscaping). This Item also includes all costs to grade and place vehicular concrete in lieu of the structures associated with Option D (Maintenance Building, Salt and Mulch Storage, and Fuel Island). This Item also includes all costs to extend and merge the concrete curb and gutter along the Boulevard and the concrete integral curb along the West Service Drive, in lieu of the entrances to Option B (South Parking Structure).
0002 Drilled Piers in Unclassified
Excavations 1 Job NA $
All costs associated with the installation of the drilled pier foundations in unclassified excavations for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.
a 24” Diameter 480 VLF $ $ b 30” Diameter 1,050 VLF $ $ c 36” Diameter 1,810 VLF $ $ d 42” Diameter 700 VLF $ $ e 48” Diameter 1,130 VLF $ $ f 54” Diameter 820 VLF $ $ g 60” Diameter 540 VLF $ $ h 72” Diameter 40 VLF $ $
No.
Description Quantity Unit Unit
0003 Drilled Piers in Rock 1 Job NA $ All costs associated with the installation of the drilled pier foundations in rock for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0004. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.
a 24” Diameter 100 VLF $ $ b 30” Diameter 270 VLF $ $ c 36” Diameter 1,130 VLF $ $ d 42” Diameter 350 VLF $ $ e 48” Diameter 470 VLF $ $ f 54” Diameter 610 VLF $ $ g 60” Diameter 120 VLF $ $ h 72” Diameter 10 VLF $ $
0004 Drilled Pier Test Probe Holes 786 EA $ $ All costs associated with the installation of the estimated quantity of test probe holes in drilled piers for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase B.
0005 Open Excavation Rock Removal 19,670 CY $ $ All costs associated with removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with open excavations. For purposes of this Item, open excavation rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phases A and B, as appropriate. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.
0006 Trench and Pit Rock Removal 3,190 CY $ $ All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with trenches and pits. For purposes of this Item, trench and pit rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phases A and B, as appropriate. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.
0007 Hospital Building 1 Job NA $ All costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase B Volumes 30 through 37 and, as appropriate, Phase B Volume 00 of the plans. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal.
0008 Dock / Central Utility Plant (CUP) 1 Job NA $ structures as indicated in Phase B Volume 40 and, as appropriate, Phase B Volume 00 of the plans. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also is exclusive of all costs associated with Option A (Laundry), with the exception of the Connector area with the CUP.
0009 North Parking Structure 1 Job NA $ structure as indicated in Phase B Volume 50 and, as appropriate, Phase B Volume 00 of
Description Quantity Unit Unit the plans. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also is exclusive of all costs associated with Option G (Photovoltaic (PV) Panel at North Parking Structure), to include the PV panels and support framing, with the exception of any associated utility conduits to connect to the overall structure utilities.
0010 Outbuildings and Miscellaneous
Structures 1 Job NA $
All costs associated with work within a line five feet outside of the exterior wall of the structures as indicated in Phase B Volume 70 of the plans. This Item is exclusive of all costs associated with the indicated portions of Option D (Maintenance Building and Fuel Island), the indicated portions of Option E (Guard Houses), and all of Option H (Water Tower and Water Tank). This Item also includes all work required to re-route water lines to, from, and within the Pump House, due to the absence of the Water Tower and Water Tank.
0011 Government Field Office 1 Job NA $ All costs associated with providing a Government Field Office, to include facility and all associated furniture and equipment, as specified in Section 01 50 00, Paragraph 3.6 (including associated subparagraphs).
0012 Utility Provider Fees 1 Job NA $ 1,080,000 All fees associated with permanent utilities to be paid directly to the indicated utility providers.
a Louisville/Jefferson County
Metropolitan Sewer District (MSD) Connection fee, capacity charge, and inflow and infiltration (I/I) surcharge for connection to the sanitary sewer system.
1 Job NA $ 850,000 b Louisville Water Company (LWC)
System development charge, service installation fee, and tapping fee for four eight inch connections: two fire and two domestic.
1 Job NA $ 130,000 c Louisville Gas and Electric Company
(LG&E)
Connection fee for natural gas and electric.
1 Job NA $ 100,000
TOTAL BASE PROPOSAL $
OPTIONS
0013 Option A1 – Laundry 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the
Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase B Volume 40 and, as appropriate, Phase B Volume 00 of the plans. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structure are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place. This Item is exclusive of all costs associated with “Option A2 – Laundry – Drilled Piers in Unclassified Excavations”, “Option A3 – Laundry – Drilled Piers in Rock”, and “Option A4 – Drilled Pier Test Probe Holes”.
Description Quantity Unit Unit
***This Option must be exercised in conjunction with “Option A2 – Laundry – Drilled Piers in Unclassified Excavations”, “Option A3 – Laundry – Drilled Piers in Rock”, and “Option A4 – Laundry – Drilled Pier Test Probe Holes”.
***This Option may be exercised within 800 calendar days after Notice to Proceed.
0014 Option A2 – Laundry – Drilled Piers in Unclassified Excavations 1 Job NA $
All costs associated with the installation of the drilled pier foundations in unclassified excavations associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified a 24” Diameter 90 VLF $ $ b 30” Diameter 80 VLF $ $
***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A3 –
Laundry – Drilled Piers in Rock”, “Option A4 – Laundry – Drilled Pier Test Probe Holes”.
0015 Option A3 – Laundry – Drilled Piers in Rock 1 Job NA $
All costs associated with the installation of the drilled pier foundations in rock associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0016. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.
a 24” Diameter 30 VLF $ $ b 30” Diameter 70 VLF $ $
***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A2 –
Laundry – Unclassified Excavations”, and “Option A4 – Drilled Pier Test Probe Holes”.
0016 Option A4 – Laundry – Drilled Pier
Test Probe Holes
22 EA $ $
All costs associated with the installation of the estimated quantity of test probe holes in drilled piers associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase B.
***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A2 –
Laundry – Unclassified Excavations”, and “Option A3 – Laundry – Drilled Piers in Rock”.
0017 Option B1 – South Parking
Structure 1 Job NA $
Description Quantity Unit Unit
This Item includes all work required in lieu of or in addition to that work included in the
Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase A Volume 60, Phase B Volume 60, and, as appropriate, Phase B Volume 00 of the plans, unless otherwise not necessary due to combining of the Phases into one project. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structure are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place. This Item is exclusive of all costs associated with “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.
NOTE: This Option will not be exercised if “Option C – South Parking Lot” is exercised.
***This Option must be exercised in conjunction with “Option B2 – South Parking Structure
– Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.
0018 Option B2 – South Parking
Structure – Drilled Piers in Unclassified Excavations
1 Job NA $
All costs associated with the installation of the drilled pier foundations in unclassified excavations associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase A. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified a 30” Diameter 60 VLF $ $ b 36” Diameter 70 VLF $ $ c 42” Diameter 20 VLF $ $ d 48” Diameter 350 VLF $ $ e 54” Diameter 60 VLF $ $
***This Option must be exercised in conjunction with “Option B1 – South Parking
Structure”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.
0019 Option B3 – South Parking
Structure – Drilled Piers in Rock 1 Job NA $
All costs associated with the installation of the drilled pier foundations in rock associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0020. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase A. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified
Description Quantity Unit Unit a 30” Diameter 30 VLF $ $ b 36” Diameter 80 VLF $ $ c 42” Diameter 10 VLF $ $ d 48” Diameter 440 VLF $ $ e 54” Diameter 60 VLF $ $
Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.
0020 Option B4 – South Parking
Structure – Drilled Pier Test Probe Holes
138 EA $ $
All costs associated with the installation of the estimated quantity of test probe holes in drilled piers associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase A.
Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.
0021 Option B5 – South Parking
Structure – Trench and Pit Rock Removal
140 CY $ $
All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with trenches and pits. For purposes of this Item, trench and pit rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phase A. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.
Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, and “Option B3 – South Parking Structure – Drilled Piers in Rock”, and “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”.
0022 Option C – South Parking Lot 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the
Base Proposal. All additional costs associated with a South Parking Lot in the location indicated for the South Parking Structure. Construction details are to be per Phase B Volume 10 of the plans for the North Parking Lot, to include storm drainage. The layout of the South Parking Lot is to be similar to that on Sheet CS130 of Phase B Volume 10 of the plans, to include a total of approximately 200 spaces.
Description Quantity Unit Unit
NOTE: This Option will not be exercised if “Option B – South Parking Structure” and its associated Items are exercised.
0023 Option D1 – Maintenance Building, Salt and Mulch Storage, and Fuel Island
1 Job NA $
This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the identified structures as indicated in Phase B Volume 70 of the plans for the Maintenance Building and Phase B Volume 10 of the plans for Salt and Mulch Storage. In addition, all additional costs associated with the Fuel Island as indicated in Phase B Volume 70 of the plans, to include the associated underground fuel tanks, but exclusive of all costs associated with “Option D2 – Fuel Storage Tanks – Open Excavation Rock Removal”. Phase B Volume 00 of the plans is applicable, as appropriate. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structures are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place.
***This Option must be exercised in conjunction with “Option D2 – Fuel Storage Tanks –
Open Excavation Rock Removal”.
0024 Option D2 – Fuel Storage Tanks –
Open Excavation Rock Removal
380 CY $ $
All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with open excavations. For purposes of this Item, open excavation rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phase B. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.
***This Option must be exercised in conjunction with “Option D1 – Maintenance Building, Salt and Mulch Storage, and Fuel Island”.
0025 Option E – Fencing, Gates, and
Guard Houses 1 Job NA $
This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with fencing and gates as indicated in Phase B Volume 10 of the plans (exclusive of temporary construction and silt fences which are to be included in the Base Proposal Item 0001 – Sitework) and all additional costs within a line five feet outside of the exterior wall of the Guard Houses as indicated in Phase B Volume 70 of the plans. Phase B Volume 00 of the plans is applicable, as appropriate. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structures are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place.
0026 Option F – Landscaping 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the
Base Proposal. All additional costs associated planting beds, plantings, and irrigation, as indicated in Phase B Volume 10 of the plans.
Description Quantity Unit Unit
0027 Option G – Photovoltaic (PV) Panel at North Parking Structure 1 Job NA $
This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with the structure as indicated in Phase B Volume 50 of the plans, to include the support framing. All costs associated with any associated utility conduits to connect to the overall structure utilities are to be included in the Base Proposal Item 0009 (North Parking Structure).
0028 Option H – Water Tower and Water
Tank 1 Job NA $
This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with the Water Tower and Water Tank as indicated in Phase B Volume 70 of the plans. Phase B Volume 00 of the plans is applicable, as appropriate.
TOTAL ALL OPTIONS $
TOTAL BASE PROPOSAL
AND ALL OPTIONS
– END OF PRICE BREAKOUT SCHEDULE –
Section 00 21 00 - Instructions
PROJNET INSTRUCTIONS
OFFEROR'S QUESTIONS AND COMMENTS
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.
To submit and review bid inquiry items, bidders will need to be a current registered user or selfregister into system.
The Solicitation Number is: W912QR21R0008 The Bidder Inquiry Key is: HDMIY2-J4SG9F Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret
Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Select Continue. A page will then open asking you to enter the answer to your
SecretQuestion.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
From this page you may view all bidder inquiries or add an inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
NOTES:
1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.
2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.
The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled ten (10) calendar days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within five (5) calendar days prior to the closing date stated in the solicitation.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.211-6 Brand Name or Equal AUG 1999 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.217-5 Evaluation Of Options JUL 1990 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
(a) Definitions. As used in this provision--
Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
Federal contracts and grants with total value greater than $10,000,000 means--
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror ( ) has ( ) does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked “has” in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in--
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE, Louisville District Misty D. Bock, Contracting Officer 600 Dr. Martin Luther King Jr. Place, Room 821 Louisville, KY 40202
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) A virtual Pre-proposal Conference has been scheduled for Thursday, 17 December 2020 at 1:00 PM (Eastern).
To attend the virtual conference please go to https://usace1.webex.com/meet/michael.d.hutchens and type in your name and email address when prompted. You will also need to have the Webex application call you using the instructions below.
Click the "Call Me" button and input a phone number which will be called with the audio component of the meeting.
Participants will be muted throughout presentations to manage sound control.
The conference will begin promptly at 1:00 PM (Eastern), however the Webex application will open for participants to log in at 12:30 PM (Eastern).
No questions will be accepted via the chat feature, during the meeting. Questions submitted via Projnet Bidder Inquiries prior to the meeting may be addressed at the meeting.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
FAR provisions (52.XXX-XX) – https://acquisition.gov/browse/index/far DFARS provisions (252.XXX-XX) - https://www.acq.osd.mil/dpap/dars/dfarspgi/current/
Section 00 22 00 - Supplementary Instructions
EVALUATION CRITERIA
SECTION 00 22 12 - PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION
CRITERIA
1. Overview.
1.1 The intent of this solicitation is to select one contractor for the New Veterans Affairs Medical Center, in Louisville, Kentucky. The Government will evaluate the proposals in accordance with the criteria described herein, and award a firm fixed price contract to the responsible offeror, whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government.
1.2 The basis of award is the Tradeoff Process. The Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source Selection Authority (SSA) determines conforms to the solicitation, is fair and reasonable in price, and offers the best overall value to the Government. The Government reserves the right to award to other than the lowest priced offeror or to other than the highest technically rated offeror, or to reject all offers.
2. Submittal of offers.
2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein.
The proposals must include information sufficiently detailed to clearly describe the offeror's past performance, technical approach, and management capabilities necessary for successful completion of the project. Requirements stated in this Request for Proposal (RFP) are minimums. Innovative, creative or cost-saving proposals that meet or exceed the requirements are encouraged and will be rated accordingly.
2.2 Offerors shall submit their proposals to the US Army Corps of Engineers, 600 Dr. Martin Luther King, Jr.
Place, Room 821, Louisville, KY 40202-2267 no later than the time and date specified in Block 13 of Standard Form 1442. NOTE: The Louisville District is in the Eastern Time Zone.
2.3 Offerors are required to submit a proposal made up of Past Performance, Management, Key Subcontractor Experience, Schedule, Small Business Participation Plan, and Price and Pro Forma. All proposal materials shall be submitted in binders with a table of contents and tabbed section dividers. The sections should parallel the submission requirements identified below. Volume I shall be submitted in original and 7 (seven) paper copies and one electronic copy on CD/DVD*. Volume II shall be submitted in original and 1 CD/DVD* only and shall be placed in a separate envelope. Failure to place the required submission information under the appropriate tab (factor or subfactor) may result in a lower rating if the evaluators cannot readily find the appropriate information.
*NOTE: Provide the complete Volume I proposal submittal including text, renderings, drawings, photographs, etc on CD/DVD (one copy). Provide the complete Volume II proposal submittal on a separate CD/DVD (one copy), including the final price breakout schedule if the final price breakout schedule(s) are available electronically. The paper copy of the proposal shall be used for evaluation and will control any conflicts or discrepancies between the two media. Offeror is responsible for ensuring the paper copy is consistent with the electronic copy of the proposal.
There is a total limit of 200 pages for Volume I (excluding dividers; double sided pages count as two pages) using a minimum font size of 11 and a minimum margin size of one-half inch on all sides. Page size must be 8.5” x 11” for all pages unless otherwise stated/allowed. Please see the submission requirements below for additional page limitations for individual evaluation factors. Format restrictions will be strictly adhered to and enforced.
Information submitted which exceeds the specified total limit or individual limits will not be evaluated.
2.4 The target ceiling for contract award is $705,000,000, exclusive of the Government Field Office, based on funds currently made available for this project. The Government cannot guarantee that additional funds will become available for award. Offerors are under no obligation to approach this ceiling.
3. Proposal Evaluation Process.
3.1 A Source Selection Evaluation Board (SSEB) comprised of representatives of the U.S. Army Corps of Engineers (USACE), User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. The number and identities of offerors are not revealed to anyone who is not involved in the evaluation and award process or to other offerors.
Proposals will be evaluated based on the factors described herein, and the basis of award is the Tradeoff Process.
3.2 The evaluation process essentially consists of five parts: proposal compliance review, technical evaluation, Source Selection Advisory Council review, price evaluation, and price/technical trade-off analysis.
3.2.1 Proposal Compliance Review: This is an initial review to ensure that all required forms and certifications are complete and that both a technical and price proposal were received.
3.2.2 Technical Evaluation: The SSEB will evaluate and rate the technical proposals (i.e., Volume I) against the RFP requirements. Factor I – Past Performance will be rated using Tables 1 and 2 below. The rating will be based on overall confidence in performance, with the final confidence assessment rating based on the extent of recent, relevant past experience, and how well the offeror performed on that experience. Factors II-IV (Management, Key Subcontractor Experience, Schedule), including all subfactors, will be rated using Table 3 below. Factor V – Small Business Participation Plan will be rated using Table 4 below.
3.2.3 Source Selection Advisory Council (SSAC) Review: The SSAC will review the evaluation results of the SSEB to ensure the evaluation process follows the evaluation criteria, and the ratings are appropriately and consistently applied. The SSAC will consolidate their advice and recommendations into a written comparative analysis and recommendation for use by the SSA in selecting the offeror who represents the best value to the Government.
3.2.4 Price Evaluation: The SSEB, SSAC and SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation of the original proposals.
3.2.5 Price/Technical Trade-off Analysis: After all above evaluations are complete, the SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The SSA will then consider all factors to select the proposal offering the best value to the Government.
4. Proposal Information and Related Evaluation Factors.
4.1 Proposals will be evaluated in accordance with the factors and subfactors below, listed in relative order of importance. NOTE: To be eligible for award, Factor I, Past Performance, must be rated at least Satisfactory Confidence, and Factors II through V, including subfactors, must be rated at least “Acceptable.” All non-priced factors, when combined, are approximately equal to price. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in Federal Acquisition Regulation (FAR) 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
4.2 Volume I – Factor I – Past Performance (Prime Contractor) 1st
4.3 Volume I - Factor II – Management 2nd
Subfactor A – Management Plan Equal to Subfactor B Subfactor B – Individual Key Personnel Experience Equal to Subfactor A
4.4 Volume I – Factor III – Key Subcontractor Experience 3rd
4.5 Volume I – Factor IV – Schedule 4th
4.6 Volume I - Factor V – Small Business Participation Plan 5th
4.7 Volume II - Price and Pro Forma Information (Sealed Envelope)
Tab A Standard Form 1442 and Price Breakout Schedule Not Rated
Tab B Subcontracting Plan Not Rated
Tab C Joint Venture and Mentor-Protégé Agreements Not Rated
Tab D Evidence of Ability to Obtain Bonding and Not Rated
Proof of Financial Ability
Tab E Pre-Award Information Not Rated
4.8 Ratings
Evaluators will apply the adjectival rating for the definition that most closely matches the evaluation.
Table 1 - Past Performance Relevancy Ratings Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
Table 2 - Past Performance Confidence Assessments Ratings
Rating Definition Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.
Table 3 – Technical/Risk Assessment Ratings Adjectival Rating Definition
Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements and/or risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable.
Proposal is unawardable.
Table 4 - Small Business Participation Plan Ratings Adjectival Rating Definition Outstanding Proposal indicates an exceptional approach and understanding of the small business objectives.
Good Proposal indicates a thorough approach and understanding of the small business objectives.
Acceptable
Proposal indicates an adequate approach and understanding of the small business objectives.
Marginal Proposal has not demonstrated an adequate approach and understanding of the small business objectives.
Unacceptable Proposal does not meet the small business objectives.
4.9 Definitions
1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
2. Strength. An aspect of an offerors’ proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
3. Significant Strength. An aspect of an offerors’ proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See
FAR 15.001.
5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret…
This is the start of the file's text. The full file is on GovTribe.