This document provides details regarding a forthcoming federal contract solicitation for construction of a new VA Medical Center campus in Louisville, KY. The U.S. Army Corps of Engineers Louisville District plans to issue a Request for Proposal W912QR21R0008 for design and construction of a new 104-bed hospital, parking structures for 2,600 cars, campus infrastructure, and other site improvements. The estimated contract value is over $500 million, with an anticipated ceiling of approximately $705 million. The solicitation is expected to be released on December 3, 2020 as a single-phase, best-value procurement utilizing a tradeoff source selection method. Technical evaluation factors will include past performance, management, key subcontractor experience, schedule, and small business participation, deemed approximately equal to price. The contract duration is 1,554 calendar days from notice to proceed.

View the file

Other files

File Type Posted
W912QR21R0008_Plans_PhaseA-0008.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0008.xlsx XLSX spreadsheet
W912QR21R0008_Plans_PhaseB-0008.pdf PDF
W912QR21R0008_Specs_PhaseA-0008.pdf PDF
W912QR21R0008_CT-0008.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0008.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110000_Part2-0008.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110000_Part1-0008.pdf PDF
W912QR21R0008_Specs_PhaseB-0008.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0007..xlsx XLSX spreadsheet
W912QR21R0008_Specs_PhaseA-0007.pdf PDF
W912QR21R0008_Specs_CT-0007.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0007.pdf PDF
W912QR21R0008_Plans_PhaseB_Part2-0007.pdf PDF
W912QR21R0008_Plans_PhaseA-0007.pdf PDF
W912QR21R0008_Plans_PhaseB_Part1-0007.pdf PDF
W912QR21R0008_Specs_PhaseB-0007.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110000_Part1-0007.pdf PDF
W912QR21R0008-0006.pdf PDF
W912QR21R0008_Plans-0005.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0005.xlsx XLSX spreadsheet
W912QR21R0008_Specs_PhaseB_Vol3_110000_Part2-0004.pdf PDF
W912QR21R0008_Plans-0004.pdf PDF
W912QR21R0008_Specs-0004.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110000_Part1-0004.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol3_110601-0003.xlsx XLSX spreadsheet
W912QR21R0008_Specs-0003.pdf PDF
W912QR21R0008_Plans-0003.pdf PDF
W912QR21R0008Plans-0002.pdf PDF
W912QR21R0008Specs-0002.pdf PDF
W912QR21R0008_Specs_CT-0001.pdf PDF
W912QR21R0008_Specs_CT-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol2-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol36-0000.pdf PDF
W912QR21R0008_Plans_PhaseA_Vol10-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol32-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol70-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol33-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol31_Part1-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol1_00800004a06-0000.xlsx XLSX spreadsheet
W912QR21R0008_Plans_PhaseA_Vol60-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol31_Part2-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol34-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol60-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol6-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol50-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol5-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol1-0000.pdf PDF
W912QR21R0008_Specs_PhaseB_Vol7-0000.pdf PDF
W912QR21R0008_Plans_PhaseB_Vol30-0000.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912QR21R0008

MILITARY/RESERVE BRANCH

ATTN: MICHAEL HUTCHENS

600 DR M L KING JR PL, RM 821

LOUISVILLE KY 40202-2236

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation number W912QR21R0008 for the Construction of the Veterans Affairs (VA) Medical Center (VAMC) in Louisville, KY is hereby amended as follow s:

SEE THE ATTACHED SUMMARY OF CHANGES

1. CONTRACT ID CODE PAGE OF PAGES

1 58

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR21R0008

X 9B. DATED (SEE ITEM 11)

03-Dec-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3.EFFECTIVE DATE

03-Feb-2021

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE 964859

FACILITY CODECODE

EMAIL:TEL:

W912QR21R0008_Specs-0005

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDT 0005 - SUMMARY OF CHANGES

AMENDMENT 0005 – SUMMARY OF CHANGES

1. The following specification sections have been replaced in their entirety:

Volume No. Section No. Section Title CT 00 10 00 Price Breakout Schedule CT 00 22 12 Procedures for Submittal of Offers and

Proposal Evaluation Criteria

Phase A 03 30 01 Cast-in-Place Concrete for Garage Structures Phase A 05 40 00 Cold-Formed Metal Framing

PHASE B

1-7* 00 01 10 Table of Contents *Only issued once via this amendment.

1 00 80 00.02 06 Communication Systems Matrix 1 01 57 19.00 06 Temporary Environmental Controls and

Permits 1 03 30 00 Cast-in-Place Concrete 1 03 30 01 Cast-in-Place Concrete for Garage

1 05 40 00 Cold-Formed Metal Framing

2 09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard and Block

CMU (RES-W1)

3 11 06 00 Medical Equipment Schedule 3 11 06 01 Project Room Contents Report 3 11 71 00 Healthcare Equipment

6 26 05 13 Medium Voltage Cables 6 26 05 19 Low-Voltage Electrical Power Conductors and Cables 6 26 22 00 Low-Voltage Transformers 6 26 32 13 Engine Generators 6 27 52 23 Nurse Call and Code Blue 6 28 05 00 Common Work Results for Electronic Safety and Security 6 28 13 53 Security Access Detection 6 28 23 00 Video Surveillance 6 28 26 00 Electronic Personal Protection System

7 32 05 23 Cement and Concrete for Exterior

Improvements

2. The following specification sections are added in their entirety.

Volume No. Section No. Section Title

PHASE B

1 01 57 19.05 06 Adjacent Property Encroachments 1 03 35 11 Concrete Finishing – Colored Hardener

3. The following specification file is replaced in its entirety.

3 11 06 01 Project Room Contents Report - Excel file

4. The following drawings have been replaced in their entirety:

**Drawings listed as being included in more than one Volume are only issued once via this amendment.

Volume No. Drawing No. Drawing Title

PHASE A

10 ES2007 VAMC Site Electrical and Telecommunications

Plan Area 6

60 AE100F South Parking Ground Level Floor Plan 60 AE101F South Parking Level 1 Floor Plan 60 AE102F South Parking Level 2 Floor Plan 60 AE103F South Parking Level 3 Floor Plan 60 AE104F South Parking Level 4 Floor Plan 60 AE105F South Parking Level 5 Floor Plan 60 AE106F South Parking Level 6 Floor Plan 60 AE107F South Parking Roof Plan 60 AE201F South Parking Elevations 60 AE202F South Parking Elevations 60 AE211F South Parking Enlarged Elevations 60 AE212F South Parking Enlarged Elevations 60 AE213F South Parking Enlarged Elevations 60 AE214F South Parking Enlarged Elevations 60 AE301F South Parking Building Sections 60 AE306F South Parking Combination Wall Sections 60 AE307F South Parking Combination Wall Sections 60 AE308F South Parking Combination Wall Sections 60 AE309F South Parking Combination Wall Sections 60 AE310F South Parking Combination Wall Sections 60 AE310.1F South Parking Combination Wall Sections 60 AE311F South Parking Stair Sections N/W Core 60 AE312F South Parking Stair Sections S/E Core 60 AE313F South Parking Elevator Sections 60 AE401F South Parking Ground Level Enlarged Floor

Plans and RCP

60 AE402F South Parking Level 1 Enlarged Floor Plans and

RCP

60 AE403F South Parking Levels 2-5 Typ Enlarged Floor Plan and RCP

60 AE404F South Parking Enlarged Floor Plans Level 6 60 AE405F South Parking Elevator Machine Room Floor Plan and RCP 60 AE410F South Parking - Enlarged Roof Plans 60 AE501F South Parking Large Sections 60 AE504F South Parking Details 60 AE520F South Parking Enlarged Plan Details 60 AE521F South Parking Enlarged Plan Details 60 AE522F South Parking Enlarged Plan Details 60 AE523F South Parking Enlarged Plan Details and

Sections at Elevator Lobby 60 AE524F South Parking Curtain Wall Enlarged Details 60 AE531F South Parking Roof Details

00 GI01310** Index of Drawings Volume 31 00 AI51001 Partition Systems 00 AE6001B Exterior Material Finish, Louver Legends and

Paver/Landscape Layout 00 EE002** Electrical Symbols and Abbreviations, Part 2 00 EE003** Electrical Symbols and Abbreviations, Part 3 00 EE501 Site Electrical Underground Details 00 TC001** Technology Symbols Legend

10 CS404 VAMC Main Entry 10 CS502 Perimeter Fence Details 10 EE002** Electrical Symbols and Abbreviations, Part 2 10 EE003** Electrical Symbols and Abbreviations, Part 3 10 ES1002 VAMC Site Lighting Plan Area 1 10 ES1003 VAMC Site Lighting Plan Area 2 10 ES2002 VAMC Site Electrical and Telecommunications

Plan Area 1 10 ES2003 VAMC Site Electrical and Telecommunications

Plan Area 2 10 ES2004 VAMC Site Electrical and Telecommunications

Plan Area 3 10 ES2006 VAMC Site Electrical and Telecommunications

Plan Area 5 10 ES2007b VAMC Site Electrical and Telecommunications

Plan Area 6 10 ES5002 Duct Bank Details 10 TC001** Technology Symbols Legend

30 SF001B VAMC Structural General Notes 30 SF402B VAMC Level 5 Partial Framing Plan 30 SF631B VAMC Schedules - Foundations & Framing

31 GI01310** Index of Drawings Volume 31 31 AI100B0 VAMC Ground Level Composite Floor Plan 31 AI100B4 VAMC Ground Level Floor Plan Area 4 31 AI100B5 VAMC Ground Level Floor Plan Area 5 31 AI100B6 VAMC Ground Level Floor Plan Area 6 31 AI101B0 VAMC Level 1 Composite Floor Plan 31 AI101B1 VAMC Level 1 Floor Plan Area 1 31 AI101B2 VAMC Level 1 Floor Plan Area 2 31 AI101B3 VAMC Level 1 Floor Plan Area 3 31 AI101B4 VAMC Level 1 Floor Plan Area 4 31 AI101B5 VAMC Level 1 Floor Plan Area 5 31 AI101B6 VAMC Level 1 Floor Plan Area 6 31 AI101iB4 VAMC Level 1i Floor Plan Area 4 31 AI101iB6 VAMC Level 1i Floor Plan Area 6 31 AI102B0 VAMC Level 2 Composite Floor Plan 31 AI102B3 VAMC Level 2 Floor Plan Area 3 31 AI103B0 VAMC Level 3 Composite Floor Plan 31 AI103B1 VAMC Level 3 Floor Plan Area 1 31 AI103B2 VAMC Level 3 Floor Plan Area 2 31 AI103B3 VAMC Level 3 Floor Plan Area 3 31 AI103B4 VAMC Level 3 Floor Plan Area 4 31 AI103B5 VAMC Level 3 Floor Plan Area 5 31 AI104B0 VAMC Level 4 Composite Floor Plan 31 AI104B1 VAMC Level 4 Floor Plan Area 1 31 AI104B2 VAMC Level 4 Floor Plan Area 2 31 AI104B3 VAMC Level 4 Floor Plan Area 3 31 AI104B4 VAMC Level 4 Floor Plan Area 4 31 AI104B5 VAMC Level 4 Floor Plan Area 5 31 AI104B6 VAMC Level 4 Floor Plan Area 6 31 AI104iB4 VAMC Level 4i Floor Plan Area 4 31 AI104iB6 VAMC Level 4i Floor Plan Area 6 31 AI105B0 VAMC Level 5 and Penthouse Composite Floor

Plan 31 AI105B4 VAMC Level 5 Floor Plan Area 4 31 AI105B5 VAMC Level 5 Floor Plan Area 5 31 AI105B6 VAMC Level 5 Floor Plan Area 6 31 AI1C2B4 VAMC Level 2 Reflected Ceiling Plan Area 4 31 AI1C2B5 VAMC Level 2 Reflected Ceiling Plan Area 5 31 AI1C2B6 VAMC Level 2 Reflected Ceiling Plan Area 6 31 AI1C3B6 VAMC Level 3 Reflected Ceiling Plan Area 6 31 AI1C4B3 VAMC Level 4 Reflected Ceiling Plan Area 3 31 AI4015B VMAC Level 1 Area B7E Enlarged Floor Plan 31 AI4106B VAMC Nurse Stations 31 AI4107B VAMC Nurse Stations 31 AI4108B VAMC Nurse Stations 31 AI4121B VAMC Toilet Rooms 31 AI4143B VAMC Mechanical Closets and Exam Room 1B4414 31 AI4151B VAMC Level 1 1B1622 Waiting 31 AI4155B VAMC Level 2 2B4202 Waiting 31 AI4156B VAMC Level 2 2B4604 Waiting 31 AI4157B VAMC Level 2 2B5103 Waiting 31 AI4158B VAMC Level 2 2B5502, 2B6103 Waiting 31 AI4159B VAMC Level 2 2B6103 Waiting 31 AI4160B VAMC Level 2 2B6501 Waiting 31 AI4163B VAMC Level 3 3B5501, 3B6101 Waiting

31 AI4164B VAMC Level 3 3B6501 Waiting 31 AI4181B VAMC Level 1 Typical Displacement Grilles 31 AI7600B VAMC Stair Details 31 AI7601B VAMC Stair Details 31 AI7602B VAMC Stair Details 31 AF100B5 VAMC Ground Level Finish Plan Area 5 31 AF100B6 VAMC Ground Level Finish Plan Area 6 31 AF101B1 VAMC Level 1 Finish Plan Area 1 31 AF101B2 VAMC Level 1 Finish Plan Area 2 31 AF101B3 VAMC Level 1 Finish Plan Area 3 31 AF101B6 VAMC Level 1 Finish Plan Area 6 31 AF102B2 VAMC Level 2 Finish Plan Area 2 31 AF102B6 VAMC Level 2 Finish Plan Area 6 31 AF103B2 VAMC Level 3 Finish Plan Area 2 31 AF103B5 VAMC Level 3 Finish Plan Area 5 31 AF104B1 VAMC Level 4 Finish Plan Area 1 31 AF104B2 VAMC Level 4 Finish Plan Area 2 31 AF104B3 VAMC Level 4 Finish Plan Area 3 31 AF105B4 VAMC Level 5 Finish Plan Area 4 31 AF105B5 VAMC Level 5 Finish Plan Area 5 31 AF105B6 VAMC Level 5 Finish Plan Area 6 31 AF21001 VAMC Departmental Entry Design 31 AF600B1 VAMC Ground Level Room Finish Schedule Areas

1-5 31 AF601B2 VAMC Level 1 Room Finish Schedule Areas 2-4 31 AF602B2 VAMC Level 2 Room Finish Schedule Areas 2-4 31 AF602B3 VAMC Level 2 Room Finish Schedule Areas 4-5 31 AF602B4 VAMC Level 2 Room Finish Schedule Areas 5-6 31 AF603B3 VAMC Level 3 Room Finish Schedule Areas 4-5 31 AF603B4 VAMC Level 3 Room Finish Schedule Area 6 31 AF605B2 VAMC Level 5 Room Finish Schedule Area 5 31 AF60000 VAMC Interior Finish Material Schedule 31 AF60001 VAMC Interior Finish Material Schedule 31 EM102B VAMC EMI Shielding 31 T100B VAMC Plans and Section Elevators S1-S2,(Elevs, S5-S6 SIM)

31 QT100B VAMC Ground Level PTS Plan 31 QT101iB VAMC Level 1i PTS Plan 31 QT102B VAMC Level 2 PTS Plan 31 QT103B VAMC Level 3 PTS Plan 31 QT104B VAMC Level 4 PTS Plan 31 QT104iB VAMC Level 4i PTS Plan 31 QT105B VAMC Level 5 PTS Plan

32 AE100B1 VAMC Ground Level Floor Plan Area 1 32 AE100B4 VAMC Ground Level Floor Plan Area 4 32 AE101B3 VAMC Level 1 Floor Plan Area 3 32 AE101iB4 VAMC Level 1i Floor Plan Interstitial Area 4 32 AE101iB6 VAMC Level 1i Floor Plan Interstitial Area 6 32 AE104B1 VAMC Level 4 Floor Plan Area 1 32 AE104iB4 VAMC Level 4i Floor Plan Interstitial Area 4 32 AE104iB6 VAMC Level 4i Floor Plan Interstitial Area 6 32 AE105B1 VAMC Level 5 Penthouse Floor Plan Area 1 32 AE105B2 VAMC Level 5 Penthouse Floor Plan Area 2

32 AE105B3 VAMC Level 5 Penthouse Floor Plan Area 3 32 AE2014B VAMC Partial Exterior Elevation Concourse Area

32 AE2015B VAMC Partial Exterior Elevation Concourse Area

32 AE2016B VAMC Partial Exterior Elevation Concourse Area

32 AE2025B VAMC Exterior Elevation East Bar Terraces 32 AE2043B VAMC (East Bar Terrace) Enlarged

Elevation/Sections 32 AE2044B VAMC (East Bar) S. East Enlarged Partial

Elevation/Sections/Plans 32 AE2046B VAMC (East Bar) S. West Concourse Enlarged

West Elevation/Sections/Plans 32 AE2052B VAMC South Entrance Enlarged

Elevation/Sections 32 AE3017B VAMC Concourse Sections 32 AE3201B VAMC Wall Sections East Bar 32 AE5623B VAMC Section Details Air Intake

33 QS100B5 VAMC SPS Ground Level Floor Plan Area B5

36 EE002** Electrical Symbols and Abbreviations, Part 2 36 EE003** Electrical Symbols and Abbreviations, Part 3 36 EE200B4 VAMC Ground Level Power Plan Area 4 36 EE200B6 VAMC Ground Level Power Plan Area 6 36 EE201B3 VAMC Level 1 Power Plan Area 3 36 EE201B5 VAMC Level 1 Power Plan Area 5 36 EE201B6 VAMC Level 1 Power Plan Area 6 36 EE203B4 VAMC Level 3 Power Plan Area 5 36 EE203B5 VAMC Level 3 Power Plan Area 5 36 EE203B6 VAMC Level 3 Power Plan Area 6 36 EE204B4 VAMC Level 4 Power Plan Area 4 36 EE204B5 VAMC Level 4 Power Plan Area 5 36 EE204B6 VAMC Level 4 Power Plan Area 6 36 EE205B4 VAMC Level 5 Power Plan Area 4 36 EE205B5 VAMC Level 5 Power Plan Area 5 36 EE205B6 VAMC Level 5 Power Plan Area 6 36 EE600B6 VAMC Level 0 Panel Schedules URP 36 EE620B Motor Schedule 36 EE621B Motor Schedule 36 EE622B Motor Schedule 36 EE623B Transformer Schedule 36 EE721B VAMC Emergency Power One Line East Bar Part 1 36 EE725B VAMC Life Safety Power One Line East Bar Part

36 EE726B VAMC CR1, CR2, CR3 Critical Busways East Bar 36 EE727B VAMC EQ1 Busway Emergency Power East Bar 36 EE743B VAMC Emergency Power One Line West Bar Part 2 36 EE744B VAMC N4 Busway Normal Power West Bar 36 EE745B VAMC N5 Busway Normal Power West Bar 36 EE747B VAMC N7 Busway Normal Power West Bar 36 EE748B VAMC Emergency Power One Line West Bar Part 4

36 EE749B VAMC Life Safety One Line West Bar Part 1 36 EE754B VAMC Emergency Power One Line West Bar Part 3 36 EE759B VAMC Emergency Power One Line West Bar Part 4 36 EE760B VAMC Emergency Power One Line West Bar Part 5

37 TC001** Technology Symbols Legend 37 TC203B1 VAMC Level 3 FMS Floor Plan Area B1 37 TC204B4 VAMC Level 4 FMS Floor Plan Area B4 37 TC204B5 VAMC Level 4 FMS Floor Plan Area B5 37 TC204B6 VAMC Level 4 FMS Floor Plan Area B6 37 TC205B6 VAMC Level 5 FMS Floor Plan Area B6 37 TC514 Clinical Intercom Typical 37 TC701 VAMC Telecommunications Fiber Backbone Riser

Diagram

40 AF601D Central Utility Plant Door & Room Finish

Schedule 40 QD100C1 Truck Dock Ground Level Floor Plan Area C1 40 QD200C1 Truck Dock Ground Level Elevations Area C1 40 QL410C2 Laundry Ground level Soiled Linen Equipment

Plan 40 EE002** Electrical Symbols and Abbreviations, Part 2 40 EE003** Electrical Symbols and Abbreviations, Part 3 40 TC001** Technology Symbols Legend 40 EE601D Central Utility Plant First Floor Panel

Schedules 40 EE602D Central Utility Plan/Laundry Lighting Panel

Schedules ground and First Floor 40 EE603D Laundry Ground Level Panel and Relay Schedules 40 EE701 Medium Voltage Emergency One Line Diagram 40 EE712D Central Utility Plant Emergency One Line

Diagram 40 EE713D Central Utility Plant Emergency One Line

Diagram 40 EE714D Central Utility Plant Emergency One Line

40 TC001** Technology Symbols Legend

50 SF003E North Parking Structural General Notes 50 AE101E North Parking Level 1 Floor Plan 50 AE102E North Parking Level 2 Floor Plan 50 AE103E North Parking Level 3 Floor Plan 50 AE104E North Parking Level 4 Floor Plan 50 AE105E North Parking Level 5 Floor Plan 50 AE106E North Parking Level 6 Floor Plan 50 AE107E North Parking Roof Plan 50 AE201E North Parking Elevations 50 AE202E North Parking Elevations 50 AE211E North Parking Enlarged Elevations 50 AE212E North Parking Enlarged Elevations 50 AE213E North Parking Enlarged Elevations 50 AE214E North Parking Enlarged Elevations

50 AE220E North Parking Garage Enlarged Elevations Elevator Lobbies

50 AE301E North Parking Building Sections 50 AE302E North Parking Combination Wall Sections 50 AE303E North Parking Combination Wall Sections 50 AE304E North Parking Combination Wall Sections 50 AE306E North Parking Combination Wall Sections 50 AE307.1E North Parking Combination Wall Sections 50 AE308E North Parking Combination Wall Sections 50 AE308.1E North Parking Combination Wall Sections 50 AE309.1E North Parking Combination Wall Sections 50 AE310E North Parking Combination Wall Sections 50 AE311E North Parking S/E Stair Sections 50 AE312E North Parking N/W Stair Sections 50 AE313E North Parking Elevator Sections 50 AE401E North Parking Level 1 Enlarged Floor Plans and

RCP

50 AE402E North Parking Level 2 Enlarged Floor Plans and

RCP

50 AE403E North Parking Typical and Level 6 Enlarged

Floor Plans and RCP 50 AE404E North Parking Level 6 And Elevator Machine

Room Enlarged Floor Plans and RCP 50 AE405E North Parking Misc - Room and Enlarged Roof

Plans 50 AE501E North Parking Large Sections 50 AE504E North Parking Details 50 AE505E North Parking Large Sections 50 AE506E North Parking Large Sections 50 AE520E North Parking Enlarged Plan Details Southeast

Core 50 AE521E North Parking Enlarged Plan Details Southeast

Core 50 AE522E North Parking Enlarged Plan Details Southeast

Core 50 AE524E North Parking Enlarged Plan Details Northwest

Core 50 AE525E North Parking Curtain Wall Enlarged Details 50 AE531E North Parking Roof Details 50 EE002** Electrical Symbols and Abbreviations, Part 2 50 EE003** Electrical Symbols and Abbreviations, Part 3 50 EE701E North Parking Electrical One Line Diagram 50 TC001** Technology Symbols Legend

60 EE002** Electrical Symbols and Abbreviations, Part 2 60 EE003** Electrical Symbols and Abbreviations, Part 3 60 EE705Fb Site and Storm Water Pump Station One Line

60 TC001** Technology Symbols Legend

70 EE002** Electrical Symbols and Abbreviations, Part 2 70 EE003** Electrical Symbols and Abbreviations, Part 3 70 TC001** Technology Symbols Legend

70 EE100K1 Water Tower Electrical Plan 70 EE701L1 Electrical Service Buildings East and West

Single Line Diagrams

- - - END OF SUMMARY OF CHANGES - - -

SECTION 00 10 00 - SOLICITATION

The following have been modified:

PRICE BREAKOUT SCHEDULE

SECTION 00 10 00

PRICE BREAKOUT SCHEDULE

Amendment 0005

PROJECT: Replacement VA Medical Center

LOCATION: Louisville, KY

PROJECT NUMBER: P2 453413 / VA PN 603-320

OFFEROR:

Item No.

Description Quantity Unit Unit

Price Amount

BASE PROPOSAL

Amendment 0003************************************************************************************************ 0001 Sitework 1 Job NA $ All costs associated with work beyond a line five feet outside of the exterior walls of the project structures to include, but not limited to, grading, site utilities, site improvements, etc., as indicated in Phase A Volume 10 and Phase B Volume 10 of the plans, unless otherwise not necessary due to combining of the Phases into one project. This Item also is exclusive of all costs associated with the indicated portion of Option D (Salt and Mulch Storage), the indicated portion of Option E (Fencing and Gates), all of Option F (Landscaping), and the indicated portion of Option H (piping and paving). This Item also is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also includes all costs to grade and permanently seed stabilize areas in lieu of the structures and features associated with all of Option A (Laundry), all of Option B (South Parking Structure), the indicated portion of Option E (Guard Houses), all of Option F (Landscaping), and all of Option H (Water Tower, Water Tank, and Pump House). This Item also includes all costs to grade and place vehicular concrete in lieu of the structures associated with Option D (Maintenance Building, Salt and Mulch Storage, and Fuel Island). This Item also includes all costs to extend and merge the concrete curb and gutter along the Boulevard and the concrete integral curb along the West Service Drive, in lieu of the entrances to Option B (South Parking Structure).

************************************************************************************************Amendment 0003

0002 Drilled Piers in Unclassified

Excavations 1 Job NA $

All costs associated with the installation of the drilled pier foundations in unclassified excavations for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.

a 24” Diameter 480 VLF $ $ b 30” Diameter 1,050 VLF $ $ c 36” Diameter 1,810 VLF $ $

Description Quantity Unit Unit d 42” Diameter 700 VLF $ $ e 48” Diameter 1,130 VLF $ $ f 54” Diameter 820 VLF $ $ g 60” Diameter 540 VLF $ $ h 72” Diameter 40 VLF $ $

0003 Drilled Piers in Rock 1 Job NA $ All costs associated with the installation of the drilled pier foundations in rock for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0004. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.

a 24” Diameter 100 VLF $ $ b 30” Diameter 270 VLF $ $ c 36” Diameter 1,130 VLF $ $ d 42” Diameter 350 VLF $ $ e 48” Diameter 470 VLF $ $ f 54” Diameter 610 VLF $ $ g 60” Diameter 120 VLF $ $ h 72” Diameter 10 VLF $ $

0004 Drilled Pier Test Probe Holes 786 EA $ $ All costs associated with the installation of the estimated quantity of test probe holes in drilled piers for the project structures included in the Base Proposal, to include the South Covered Walkway as indicated in Phase B Volume 10. This Item includes, but is not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase B.

0005 Open Excavation Rock Removal 19,670 CY $ $ All costs associated with removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with open excavations. For purposes of this Item, open excavation rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phases A and B, as appropriate. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.

0006 Trench and Pit Rock Removal 3,190 CY $ $ All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with trenches and pits. For purposes of this Item, trench and pit rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phases A and B, as appropriate. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.

0007 Hospital Building 1 Job NA $ All costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase B Volumes 30 through 37 and, as appropriate, Phase B Volume 00 of the plans. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal.

Amendment 0003************************************************************************************************ 0008 Dock / Central Utility Plant (CUP) 1 Job NA $

Description Quantity Unit Unit structures as indicated in Phase B Volume 40 and, as appropriate, Phase B Volume 00 of the plans. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also is exclusive of all costs associated with Option A (Laundry), with the exception of the Connector area with the CUP. This Item is inclusive of the insulated wall construction with four-inch wythe of ground faced CMU above the roof of the laundry on the CUP indicated on Phase B Volume 40 Sheet AE312D Wall Section F6 extending down to the foundation of the north wall of the CUP. This item is exclusive of the eight-inch wythe of CMU on the Laundry side of the north wall of the CUP indicated on Phase B Volume 40 Sheet AE312D Wall Section F6.

0009 North Parking Structure 1 Job NA $ structure as indicated in Phase B Volume 50 and, as appropriate, Phase B Volume 00 of the plans. This Item is inclusive of all structural steel shown on Phase B Volume 50 Sheet SF107E. This Item is exclusive of all costs associated with Items 0002 through 0006 related to drilled piers and rock removal. This Item also is exclusive of all costs associated with Option G (Photovoltaic (PV) Panel at North Parking Structure), to include the PV panels and support framing, with the exception of any associated utility conduits to connect to the overall structure utilities.

0010 Outbuildings and Miscellaneous

1 Job NA $

All costs associated with work within a line five feet outside of the exterior wall of the structures as indicated in Phase B Volume 70 of the plans. This Item is exclusive of all costs associated with the indicated portions of Option D (Maintenance Building and Fuel Island), the indicated portions of Option E (Guard Houses), and the indicated portions of Option H (Water Tower, Water Tank, and Pump House).

************************************************************************************************Amendment 0003

0011 Government Field Office 1 Job NA $ All costs associated with providing a Government Field Office, to include facility and all associated furniture and equipment, as specified in Section 01 50 00, Paragraph 3.6 (including associated subparagraphs).

Amendment 0003************************************************************************************************ 0012 Utility Provider Fees 1 Job NA $ 1,080,000 All fees associated with permanent utilities to be paid directly to the indicated utility providers. The fees are totaled under this Item and are itemized below by utility provider for reference. Only the Item total is to be included in the Total Base Proposal (i.e., do not include the itemized totals also).

a Louisville/Jefferson County

Metropolitan Sewer District (MSD) Connection fee, capacity charge, and inflow and infiltration (I/I) surcharge for connection to the sanitary sewer system.

1 Job NA $ 850,000 b Louisville Water Company (LWC)

System development charge, service installation fee, and tapping fee for four eight inch connections: two fire and two domestic.

1 Job NA $ 130,000 c Louisville Gas and Electric Company

(LG&E)

Connection fee for natural gas and electric.

1 Job NA $ 100,000

Description Quantity Unit Unit

TOTAL BASE PROPOSAL $

OPTIONS

0013 Option A1 – Laundry 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the

Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase B Volume 40 and, as appropriate, Phase B Volume 00 of the plans. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structure are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place. This Item is inclusive of all additional costs to construct the north wall of the CUP in accordance with Phase B Volume 40 Sheet AE312D Wall Section F6 in lieu of or in addition to the wall construction included in the Base Proposal Item 0008 – Dock / Central Utility Plant (CUP). This Item is exclusive of all costs associated with “Option A2 – Laundry – Drilled Piers in Unclassified Excavations”, “Option A3 – Laundry – Drilled Piers in Rock”, and “Option A4 – Drilled Pier Test Probe Holes”.

***This Option must be exercised in conjunction with “Option A2 – Laundry – Drilled Piers in Unclassified Excavations”, “Option A3 – Laundry – Drilled Piers in Rock”, and “Option A4 – Laundry – Drilled Pier Test Probe Holes”.

***This Option may be exercised within 400 calendar days after Notice to Proceed.

0014 Option A2 – Laundry – Drilled Piers in Unclassified Excavations 1 Job NA $

All costs associated with the installation of the drilled pier foundations in unclassified excavations associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified a 24” Diameter 90 VLF $ $ b 30” Diameter 80 VLF $ $

***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A3 –

Laundry – Drilled Piers in Rock”, “Option A4 – Laundry – Drilled Pier Test Probe Holes”.

0015 Option A3 – Laundry – Drilled Piers in Rock 1 Job NA $

All costs associated with the installation of the drilled pier foundations in rock associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0016. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase B. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified diameter, which shall sum to the total amount for this Item.

a 24” Diameter 30 VLF $ $ b 30” Diameter 70 VLF $ $

Description Quantity Unit Unit

***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A2 –

Laundry – Unclassified Excavations”, and “Option A4 – Drilled Pier Test Probe Holes”.

0016 Option A4 – Laundry – Drilled Pier

Test Probe Holes

22 EA $ $

All costs associated with the installation of the estimated quantity of test probe holes in drilled piers associated with “Option A1 – Laundry”, to include, but not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase B.

***This Option must be exercised in conjunction with “Option A1 – Laundry”, “Option A2 –

Laundry – Unclassified Excavations”, and “Option A3 – Laundry – Drilled Piers in Rock”.

Amendment 0001************************************************************************************************ 0017 Option B1 – South Parking

Structure 1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the structure as indicated in Phase A Volume 60, Phase B Volume 60, and, as appropriate, Phase B Volume 00 of the plans, unless otherwise not necessary due to combining of the Phases into one project. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structure are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place. This Item is inclusive of all structural steel shown on Phase A Volume 60 Sheet SF107F. This Item is exclusive of all costs associated with “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”. This Item also is exclusive of all costs associated with “Option J – Photovoltaic (PV) Panel at South Parking Structure”. All costs associated with any associated utility conduits to connect to the overall structure utilities to “Option J – Photovoltaic (PV) Panel at South Parking Structure” are to be included in the Base Proposal.

NOTE: This Option will not be exercised if “Option C – South Parking Lot” is exercised.

***This Option must be exercised in conjunction with “Option B2 – South Parking Structure

– Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.

************************************************************************************************Amendment 0001

0018 Option B2 – South Parking

Structure – Drilled Piers in Unclassified Excavations

1 Job NA $

All costs associated with the installation of the drilled pier foundations in unclassified excavations associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, and disposal of any associated spoils. For purposes of this Item, unclassified excavations are as defined in SECTION 31 63 26 DRILLED PIER for Phase A. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified

Description Quantity Unit Unit a 30” Diameter 60 VLF $ $ b 36” Diameter 70 VLF $ $ c 42” Diameter 20 VLF $ $ d 48” Diameter 350 VLF $ $ e 54” Diameter 60 VLF $ $

***This Option must be exercised in conjunction with “Option B1 – South Parking

Structure”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.

0019 Option B3 – South Parking

Structure – Drilled Piers in Rock 1 Job NA $

All costs associated with the installation of the drilled pier foundations in rock associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, casings, concrete, reinforcing, rock sockets, and disposal of any associated spoils. This Item is exclusive of all costs associated with any required test probe holes, which are covered under Item 0020. For purposes of this Item, rock is as defined in SECTION 31 63 26 DRILLED PIER for Phase A. The drilled pier unit prices and subtotals shall be provided below for the estimated quantities listed for each specified a 30” Diameter 30 VLF $ $ b 36” Diameter 80 VLF $ $ c 42” Diameter 10 VLF $ $ d 48” Diameter 440 VLF $ $ e 54” Diameter 60 VLF $ $

Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.

0020 Option B4 – South Parking

Structure – Drilled Pier Test Probe Holes

138 EA $ $

All costs associated with the installation of the estimated quantity of test probe holes in drilled piers associated with “Option B1 – South Parking Structure”, to include, but not limited to, associated mobilization, labor, equipment, and disposal of any associated spoils, as required per SECTION 31 63 26 DRILLED PIER for Phase A.

Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, “Option B3 – South Parking Structure – Drilled Piers in Rock”, and “Option B5 – South Parking Structure – Trench and Pit Rock Removal”.

Description Quantity Unit Unit

0021 Option B5 – South Parking

Structure – Trench and Pit Rock Removal

140 CY $ $

All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with trenches and pits. For purposes of this Item, trench and pit rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phase A. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.

Structure”, “Option B2 – South Parking Structure – Drilled Piers in Unclassified Excavations”, and “Option B3 – South Parking Structure – Drilled Piers in Rock”, and “Option B4 – South Parking Structure – Drilled Pier Test Probe Holes”.

Amendment 0004************************************************************************************************ 0022 Option C – South Parking Lot 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the

Base Proposal. All additional costs associated with any associated delegated design required and construction of a South Parking Lot in the location indicated for the South Parking Structure. Construction details are to be per Phase B Volume 10 of the plans for the North Parking Lot, to include storm drainage and site lighting. The layout of the South Parking Lot is to be similar to that on Sheet CS130 of Phase B Volume 10 of the plans, to include a total of approximately 200 spaces.

NOTE: This Option will not be exercised if “Option B – South Parking Structure” and its associated Items are exercised.

************************************************************************************************Amendment 0004

Amendment 0005************************************************************************************************ 0023 Option D1 – Maintenance Building, Salt and Mulch Storage, and Fuel Island

1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with work within a line five feet outside of the exterior wall of the identified structures as indicated in Phase B Volume 70 of the plans for the Maintenance Building and Phase B Volume 10 of the plans for Salt and Mulch Storage. In addition, all additional costs associated with the Fuel Island as indicated in Phase B Volume 70 of the plans, to include the associated underground fuel tanks, but exclusive of all costs associated with “Option D2 – Fuel Storage Tanks – Open Excavation Rock Removal”. Phase B Volume 00 of the plans is applicable, as appropriate. All costs associated with utilities beyond a line five feet outside of the exterior walls of the Maintenance Building are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place. This Item includes all costs associated with electrical and telecommunications conduits shown in Phase B Volume 10 of the plans specific to the Fuel Island.

***This Option must be exercised in conjunction with “Option D2 – Fuel Storage Tanks –

Open Excavation Rock Removal”.

Description Quantity Unit Unit

************************************************************************************************Amendment 0005

0024 Option D2 – Fuel Storage Tanks –

Open Excavation Rock Removal

380 CY $ $

All costs associated with the removal and off-site disposal of the estimated quantity of rock encountered during earthwork associated with open excavations. For purposes of this Item, open excavation rock removal is as defined in and quantity is as calculated per SECTION 31 20 00 EARTHWORK for Phase B. The definitions in the specification do not preclude rock removal via blasting so long as all contract requirements are met.

***This Option must be exercised in conjunction with “Option D1 – Maintenance Building, Salt and Mulch Storage, and Fuel Island”.

0025 Option E – Fencing, Gates, and Guard Houses

1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with fencing and gates as indicated in Phase B Volume 10 of the plans (exclusive of temporary construction and silt fences which are to be included in the Base Proposal Item 0001 – Sitework) and all additional costs within a line five feet outside of the exterior wall of the Guard Houses as indicated in Phase B Volume 70 of the plans. Phase B Volume 00 of the plans is applicable, as appropriate. All costs associated with utilities beyond a line five feet outside of the exterior walls of the structures are to be included in the Base Proposal Item 0001 (Sitework), to include cutting and capping in place.

0026 Option F – Landscaping 1 Job NA $ This Item includes all work required in lieu of or in addition to that work included in the

Base Proposal. All additional costs associated planting beds, plantings, and irrigation, as indicated in Phase B Volume 10 of the plans.

Amendment 0005************************************************************************************************ 0027 Option G – Photovoltaic (PV) Panel at North Parking Structure 1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with the structure as indicated in Phase B Volume 50 of the plans, to include the additional support framing required by the delegated design indicated in Phase B Volume 50 Sheet SF107E Plan Note 1. This Item also includes all costs associated with electrical wiring and panels specific to the PV system per Phase B Volume 50 Sheets EE207E and EE702E. All costs associated with any associated utility conduits to connect to the overall structure utilities are to be included in the Base Proposal Item 0009 (North Parking Structure).

************************************************************************************************Amendment 0005

0028 Option H – Water Tower, Water

Tank, and Pump House 1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in the Base Proposal. All additional costs associated with the Water Tower, Water Tank, and Pump House as indicated in Phase B Volume 70 of the plans for the redundant water supply for the mission critical facility. Phase B Volume 00 of the plans is applicable, as

Description Quantity Unit Unit appropriate. This Item is inclusive of all equipment within the Pump House. This Item also is inclusive of the piping between the water tower and the water main, from the water tower to the water tank and pump house, from the water tank to the pump house , and from the pump house to the water main and fire main as indicated on Phase B Volume 10 Sheet CU104b of the plans. This Item also is inclusive of any associated paving and stone in the area, exclusive of the frost slab at the doorway of the West Electrical Building as indicated on Phase B Volume 10 Sheet CS134.

Amendment 0005************************************************************************************************ Amendment 0001************************************************************************************************ 0029 Option J – Photovoltaic (PV) Panel at South Parking Structure 1 Job NA $

This Item includes all work required in lieu of or in addition to that work included in “Option B1 – South Parking Structure”. All additional costs associated with the structure as indicated in Volume 60 of the plans for both Phase A and Phase B, to include the additional support framing required by the delegated design indicated in Phase A Volume 60 Sheet SF107F Plan Note 1. This Item also includes all costs associated with electrical wiring and panels specific to the PV system per Phase B Volume 60 Sheets EE206Fb and EE702Fb. All costs associated with any associated utility conduits to connect to the overall structure utilities are to be included in “Option B1 – South Parking Structure”.

Structure”.

************************************************************************************************Amendment 0001 ************************************************************************************************Amendment 0005 ************************************************************************************************Amendment 0003

TOTAL ALL OPTIONS $

TOTAL BASE PROPOSAL

AND ALL OPTIONS

– END OF PRICE BREAKOUT SCHEDULE –

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

The following have been modified:

EVALUATION CRITERIA

SECTION 00 22 12 - PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION

CRITERIA

1. Overview.

1.1 The intent of this solicitation is to select one contractor for the New Veterans Affairs Medical Center, in Louisville, Kentucky. The Government will evaluate the proposals in accordance with the criteria described herein, and award a firm fixed price contract to the responsible offeror, whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government.

1.2 The basis of award is the Tradeoff Process. The Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source Selection Authority (SSA) determines conforms to the solicitation, is fair and reasonable in price, and offers the best overall value to the Government. The Government reserves the right to award to other than the lowest priced offeror or to other than the highest technically rated offeror, or to reject all offers.

2. Submittal of offers.

2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein.

The proposals must include information sufficiently detailed to clearly describe the offeror's past performance, technical approach, and management capabilities necessary for successful completion of the project. Requirements stated in this Request for Proposal (RFP) are minimums. Innovative, creative or cost-saving proposals that meet or exceed the requirements are encouraged and will be rated accordingly.

2.2 Offerors shall submit their proposals to the US Army Corps of Engineers, 600 Dr. Martin Luther King, Jr.

Place, Room 821, Louisville, KY 40202-2267 no later than the time and date specified in Block 13 of Standard Form 1442. NOTE: The Louisville District is in the Eastern Time Zone.

2.3 Offerors are required to submit a proposal made up of Past Performance, Management, Key Subcontractor Experience, Schedule, Small Business Participation Plan, and Price and Pro Forma. All proposal materials shall be submitted in binders with a table of contents and tabbed section dividers. The sections should parallel the submission requirements identified below. Volume I shall be submitted in original and 7 (seven) paper copies and one electronic copy on CD/DVD*. Volume II shall be submitted in original and 1 CD/DVD* only and shall be placed in a separate envelope. Failure to place the required submission information under the appropriate tab (factor or subfactor) may result in a lower rating if the evaluators cannot readily find the appropriate information.

*NOTE: Provide the complete Volume I proposal submittal including text, renderings, drawings, photographs, etc on CD/DVD (one copy). Provide the complete Volume II proposal submittal on a separate CD/DVD (one copy), including the final price breakout schedule if the final price breakout schedule(s) are available electronically. The paper copy of the proposal shall be used for evaluation and will control any conflicts or discrepancies between the two media. Offeror is responsible for ensuring the paper copy is consistent with the electronic copy of the proposal.

There is a total limit of 200 pages for Volume I (excluding dividers; double sided pages count as two pages) using a minimum font size of 11 and a minimum margin size of one-half inch on all sides. Page size must be 8.5” x 11” for all pages unless otherwise stated/allowed. Please see the submission requirements below for additional page limitations for individual evaluation factors. Format restrictions will be strictly adhered to and enforced.

Information submitted which exceeds the specified total limit or individual limits will not be evaluated.

2.4 The target ceiling for contract award is $705,000,000, exclusive of the Government Field Office, based on funds currently made available for this project. The Government cannot guarantee that additional funds will become available for award. Offerors are under no obligation to approach this ceiling.

3. Proposal Evaluation Process.

3.1 A Source Selection Evaluation Board (SSEB) comprised of representatives of the U.S.