This solicitation requests proposals for a construction project to replace and construct a Type III hydrant fuel system at Wright Patterson Air Force Base in Ohio. The project scope includes constructing new aboveground storage tanks, a pump house, hydrant piping loop, and truck offload and hydrant checkout stands. It will also involve demolishing underground storage tanks and a pumphouse.
The solicitation is for a firm-fixed-price construction contract with a magnitude between $10-25 million. The selected contractor will be chosen through a best value tradeoff process evaluating past performance, technical, and price factors. The North American Industry Classification System code is 237120. This is a full and open competition with a HUBZone 10% price evaluation set-aside. The point of contact is Miriaha Sigmon at the Department of the Army Corps of Engineers Engineering District Louisville.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Fuel Hydrant Replacement Wright-Patterson AFB, OH
P2: 471113
Design Bid Build
Specifications Vol. 3 of 3 Certified Final Submittal
20 November 2020
W912QR21R0006
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR21R0006-0000
Specifications Certified Final Submittal
Volume 3 of 3 FY 21 Replace Hydrant Fuel System
Project No. DESC1907
Wright-Patterson AFB
USACE LOUISVILLE DISTRICT
B&McD No. 107620
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
00 80 00.00 06-A CONSTRUCTION PROJECT SIGN DETAILS
DIVISION 01 - GENERAL REQUIREMENTS
01 02 20 GENERAL ENVIRONMENTAL PROTECTION REQUIREMENTS (WPAFB)
01 04 10 AIRFIELD PROJECT REQUIREMENTS (WPAFB)
01 11 00 SUMMARY OF WORK
01 32 01.00 06 PROJECT SCHEDULE
01 33 00.00 06 SUBMITTAL PROCEDURES
01 33 00.00 06-A SUBMITTAL REGISTER
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 23.33 OPERATION AND MAINTENANCE MANUALS FOR AVIATION FUEL
SYSTEMS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 83 00 LEAD REMEDIATION
02 83 13.00 06 LEAD IN CONSTRUCTION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 BITUMINOUS DAMPPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 61 14.00.20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 51 23 STEEL WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 77 20 DECORATIVE FIBERGLASS REINFORCED WALL PANELS
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL PETROLEUM
FUEL TANKS
PETROLEUM FUEL TANKS
09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR/EXTERIOR SIGNAGE
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 METAL BUILDING SYSTEMS
13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
00.00
DIRECT DIGITAL CONTROL (DDC) FOR HVAC AND OTHER LOCAL BUILDING
SYSTEMS (WPAFB)
20 UNITARY AIR CONDITIONING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH AUXILIARIES
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 17.01 10 CATHODIC PROTECTION SYSTEM (IMPRESSED CURRENT – FUEL PIPELINES)
26 42 17.02 10 CATHODIC PROTECTION SYSTEM (IMPRESSED CURRENT – FUEL TANKS)
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 63 29 DRILLED CONCRETE PIERS AND SHAFTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 01 50.60 CLEANING OF PETROLEUM STORAGE TANKS
33 08 53 AVIATION FUEL DISTRIBUTION SYSTEM START-UP
33 09 53 AVIATION FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE AND CONTAINMENT DRAINS
33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING
33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS
33 40 00 STORM DRAINAGE UTILITIES
33 52 23.15 POL SERVICE PIPING WELDING
33 52 43.11 AVIATION FUEL MECHANICAL EQUIPMENT
33 52 43.13 AVIATION FUEL PIPING
33 52 43.14 AVIATION FUEL CONTROL VALVES
33 52 43.23 AVIATION FUEL PUMPS
33 52 43.28 FILTER SEPARATOR, AVIATION FUELING SYSTEM
33 52 80 LIQUID FUELS PIPELINE COATING SYSTEMS
33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS
33 56 19 FUEL IMPERMEABLE LINER SYSTEM
33 56 21.17 SINGLE WALL ABOVEGROUND FIXED ROOF STEEL POL STORAGE TANK
33 56 21.18 SINGLE WALL POL TANK UNDERTANK INTERSTITIAL SPACE
33 58 00 LEAK DETECTION FOR FUELING SYSTEMS
33 60 02 ABOVEGROUND HEAT DISTRIBUTION SYSTEM
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.15 BRIDGE CRANES, OVERHEAD MANUAL, UNDER RUNNING
AMERICAN WATER SPECIFICATIONS
01 33 00 SUBMITTALS
01 77 00 PROJECT CLOSEOUT
01 78 29 AS-BUILT DOCUMENTATION
03 30 00 CAST-IN CONCRETE
03 48 10 PRECAST CONCRETE MANHOLES
03 48 20 VALVE BOXES AND METER VAULTS
22 11 16.11 WATER TAP AND SERVICE INSTALLATION
22 11 16.13 BACKFLOW PREVENTION
31 11 00 CLEANING AND GRUBBING
31 23 23 EXCAVATION BACKFILL AND COMPACTION FOR UTILITIES
32 92 00 TURF AND GRASSES – AP HILL
33 01 10.13 PRESSURE AND LEAKAGE TESTS
33 01 10.15 DISINFECTING PIPELINE
33 01 30.13 ACCEPTANCE TESTING FOR SANITARY SEWERS
33 01 30.51 PUMPING AND BYPASSING
33 05 27 TRACER WIRE (GENERAL)
33 11 00 PIPING – GENERAL PROVISIONS
33 11 00.11 POLYVINYL CHLORIDE (PVC)PIPE
33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE)PIPE
33 11 00.15 DUCTILE IRON PIPE & FITTINGS
33 11 00.17 POLYETHYLENE WRAP
33 12 16.11 GATE VALVES
33 12 16.17 TAPPING SLEEVES AND VALVES
33 12 16.19 AIR RELEASE VALVES
33 12 19 FIRE HYDRANTS
33 31 00.11 GRAVITY SANITARY SEWERS
33 31 00.15 SANITARY SEWER LATERALS
UTILITY SPECIFICATIONS
EC-32-120
EC-35-090
16465 260513-1.2 16192-1
EC-37-190.5
EC-37-310
EC-37-250
EC-37-200
TRANSFORMER PAD FOR 750-1500 Kva 30 TRANSFORMERS
INSTALLATION DETAILS FOR THREE PHASE PADMOUNTED TRANSFORMER
THREE PHASE PAD-MOUNTED TRANSFORMERS 75 THROUGH 2500 Kva
CUTOUT FUSE
3/C PLEX OKONITE
AES ELECTRICAL MATERIAL SPECIFICATION
DAYTON POWER AND LIGHT COMPANY MATERIAL SPECIFICATION
TERMINATOR CABLE
DPL CONDUIT INSTALLATION
ALUMA-FORM THREE PHASE POTHEAD BRACKET
RISE ARRESTER
THREE PHASE MOUNTING BRACKET
THREE PHASE APITONG TANGENT URD PRIMARY RISER
U-GUARD RISER
-- End of Project Table of Contents --
FY21 REPLACE HYDRANT FUEL SYSTEM Project# DESC1907 BMcD - 107620 P2# 471113
SECTION 33 01 50.60
CLEANING OF PETROLEUM STORAGE TANKS
11/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this Specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API)
API RP 1604 (1996; R 2010) Closure of Underground Petroleum Storage Tanks
API RP 2003 (2015; 8th Ed) Protection Against Ignitions Arising out of Static, Lightning, and Stray Currents
API RP 2207 (2017; 7th Ed) Preparing Tank Bottoms for Hot Work
API RP 500 (2012; Errata 2014) Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Division and Division 2
API Std 2015 (2018) Requirements for Safe Entry and Cleaning of Petroleum Storage Tanks
API Std 521 (2014; 6th Ed) Pressure-relieving and Depressuring Systems
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.48 (2015) Line Blanks
ASME B16.5 (2017) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 326 (2015) Standard for Safeguarding of Tanks and Containers for Entry, Cleaning, or Repair
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
SECTION 33 01 50.60 Page 1
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH 99-109 (Latest) Certified Equipment List
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-A-22262 (1993; Rev B; Am 2 1996) Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-PRF-680 (2010; Rev C; Notice 1 2015) Degreasing Solvent
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS O-D-1276 (Rev B; Notice 1) Disinfectant-Detergent, General Purpose (Pine Oil)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.1025 Lead
29 CFR 1910.1028 Benzene
29 CFR 1910.120 Hazardous Waste Operations and Emergency Response
29 CFR 1910.1200 Hazard Communication
29 CFR 1910.134 Respiratory Protection
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists
40 CFR 260 Hazardous Waste Management System: General
40 CFR 261 Identification and Listing of Hazardous Waste
40 CFR 262 Standards Applicable to Generators of Hazardous Waste
40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities
40 CFR 266 Standards for the Management of Specific
SECTION 33 01 50.60 Page 2
Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities
UNDERWRITERS LABORATORIES (UL)
UL 844 (2012; Reprint Oct 2017) UL Standard for Safety Luminaires for Use in Hazardous (Classified) Locations
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Cleaning Agents
Abrasive for Blasting
Gasoline-Oil-Resisting Rubber Gloves and Boots
Cotton Coveralls and Hard Hat
Respiratory Protective Equipment
Disinfectant
SD-06 Test Reports
Blasting Abrasive Test
Tank Contents Tests
Cleaning Test Panel Results
Monitoring Results; G
SD-07 Certificates
Qualifications of Certified Industrial Hygienist (CIH)
Testing Laboratory
Safety Plan
Training Certification
Work Plan
Hazardous Waste Disposal Plan
Tank Certification of Safety
Tank Exhaust Blower
SECTION 33 01 50.60 Page 3
Respiratory Protective Equipment
Breathing-Air Supply Source
Combustible Gas Indicator
Hydrogen-Sulfide (H2S) Indicator
Benzene Indicator Oxygen Meter
Velometers
Lighting
First Aid Kit
Tank Exhaust Blower
SD-08 Manufacturer's Instructions
Tank Cleaning Agents
SD-11 Closeout Submittals
Safety Permits
1.3 DEFINITIONS
1.3.1 Certified Industrial Hygienist (CIH)
As used in this Section, refers to an Industrial Hygienist employed by the Contractor and is certified by the American Board of Industrial Hygiene in comprehensive practice.
1.3.2 Hazardous Areas
Hazardous areas must be defined as any area within 100 feet of active aboveground storage tanks, areas within 100 feet of leaking sections of fuel pipelines or other vapor sources, areas within 200 feet of the downwind side of potential vapor emission sources (i.e., pressure-vacuum vents or open vents on active tanks, leaking sections of pipelines), areas within existing tanks, and areas within a dike.
1.3.3 Hot Work Operations
Hot work, for work covered by this Section, includes: Flame heating, welding, torch cutting, brazing, carbon arc gouging, or any work which produces heat, by any means, of 400 degrees F or more; or in the presence of flammables or flammable atmospheres, other ignition sources such as spark or arc producing tools (except steel hand tools) or equipment, static discharges, friction, impact, open flames or embers, non-explosion-proof lights, fixtures, motors or equipment. Prepare tankbottoms for hot work in accordance with API RP 2207 .
1.3.4 Reproductive Hazard
A reproductive hazard is defined as any occupational stressor (biological, chemical, or physical) that has the potential to adversely affect the
SECTION 33 01 50.60 Page 4 human reproductive process. For example, it is well known that central nervous system problems often occur in the offspring of mothers exposed to organic mercury during pregnancy. Therefore, based on the example cited, organic mercury can be classified as a reproductive stressor. Many reproductive hazards also cause other adverse health effects; for example, ethylene oxide is also known to be a carcinogen (i.e., produces cancer).
Certain reproductive stressors can also have adverse effects on the male reproductive system. (If requested by the Contractor, the Contracting Officer will make available the Navy's standard on reproductive hazards.)
1.3.5 Flammable Liquid
Any liquid having a flash point below 100 degrees F and a vapor pressure not exceeding 40 psia at 100 degrees F.
1.3.6 Combustible Liquid
Any liquid having a flash point at or above 100 degrees F.
1.4 QUALIFICATIONS
a. To Be Considered Qualified: Show proof of having completed work on three previous projects.
b. See certificate requirements for personnel as specified in Paragraph "Certificates".
1.5 QUALITY ASSURANCE
1.5.1 Modification of References
Except as modified herein, the Work must conform with the recommendations of NFPA 326 , API RP 500 , API RP 1604 , API RP 2003 , and API Std 2015 .
Where the word "should" appears in these publications, substitute "must."
1.5.2 Copies of Standards
Furnish four copies of NFPA 326 , API RP 500 , API RP 1604 , API RP 2003 , and API Std 2015 .
1.5.3 Safety Permits and Equipment
Acquire safety permits (specified by the facility safety authorities) and necessary safety equipment.
1.5.4 Regulatory Requirements
a. Obtain permits required to comply with local, State, and Federal regulations.
b. Submit copies of permits required to comply with local, State, and Federal regulations.
c. Hazardous wastes, such as water, sediment, and sludge, must be packaged, labeled, stored, transported, treated and disposed of in accordance with 40 CFR 260 through 40 CFR 266 and State and local regulations. Transporters, sorters, treaters and disposers must be certified and have EPA ID numbers. Payment for disposal of hazardous waste will not be made until a completed hazardous waste manifest from
SECTION 33 01 50.60 Page 5 the treatment or disposal facility is returned, and a copy furnished to the Government.
1.5.5 Medical Examinations
Before exposure to lead-contaminated fuel tank and at the completion of the Work, provide workers with a comprehensive medical examination as required by 29 CFR 1910.1200 . The initial examination will not be required if adequate records show that employees have been examined as required by 29 CFR 1910.1025 within the last year and the blood lead levels did not exceed 30 micrograms per 100 grams of whole blood.
1.5.6 Medical Records
Maintain complete and accurate medical records of employees for a period of at least 40-years or for the duration of employment plus 20-years, whichever is longer.
1.5.7 CIH Responsibilities
a. Certify training.
b. Review and approve Safety Plans and Work Plan for conformance to the applicable referenced standards.
c. Inspect tank cleaning work for conformance with the approved Safety and Work Plans.
d. Direct monitoring.
e. Ensure Work is performed in strict accordance with Specifications at all times.
f. Ensure hazardous exposure to personnel and to the environment are adequately controlled at all times.
1.5.8 Training
Train each employee performing tank cleaning, waste disposal, and air sampling operations prior to the time of initial Job assignment, in accordance with API Std 2015 , 29 CFR 1910.120 , 29 CFR 1910.134 , and 29 CFR 1910.1200 . The training must also include counseling of each employee on reproductive hazards involved in the Work.
1.5.9 Respiratory Protection Program
a. Furnish each employee required to wear a negative pressure respirator or other appropriate type with a respirator fit test at the time of initial fitting and at least every 6 months thereafter as required by 29 CFR 1910.1025 where lead exposure is involved. Fit testing is not required for positive pressure respirators.
b. Establish and implement a respiratory protection program as required by 29 CFR 1910.134 , and 29 CFR 1926.55 .
1.5.10 Pre-Construction Conference
Along with the CIH, or gas-free engineer, meet with the Contracting Officer to discuss in detail the Tank Cleaning Work Plan, including Work
SECTION 33 01 50.60 Page 6 procedures and precautions for the Work Plan.
1.5.11 Certificates
Submit certificates for the items listed. Where equipment or materials are specified to conform with the standards of organizations, such as National Institute for Occupational Safety and Health (NIOSH), Underwriters Laboratories (UL), and American Petroleum Institute (API), include a label or listing indicating compliance. In lieu of the label or listing, the Contractor may submit a test report from an approved testing organization stating that the item has been tested in accordance with the specified organization's test methods and that the item conforms with the organization's standard or code.
1.5.11.1 Qualifications of Certified Industrial Hygienist (CIH)
Submit name, address, and telephone number of the CIH selected to perform responsibilities in Paragraph "CIH Responsibilities". Provide previous experience of the CIH. Submit proper documentation that the Industrial Hygienist is certified by the American Board of Industrial Hygiene in comprehensive practice, including certification number and date of certification/recertification. The CIH must be familiar with the hazards involved in fuel systems work.
1.5.11.2 Testing Laboratory
Submit the name, address, and telephone number of the testing laboratory selected to perform the monitoring, testing, and reporting of airborne concentrations of lead and other contaminants. Provide proper documentation that persons performing the analysis have been judged proficient by successful participation within the last year in the National Institute for Occupational Safety and Health (NIOSH) Proficiency Analytical Testing (PAT) Program. The laboratory must be accredited by the American Industrial Hygiene Association (AIHA). Provide AIHA documentation along with date of accreditation/reaccreditation.
1.5.11.3 Safety Plan
Submit a safety plan within 45 calendar days after Contract Award and 30 days prior to commencing Work. The Safety Plan must meet requirements of EM 385-1-1 , OSHA, and address the following:
a. Identification and evaluation of the hazards and risks associated with each site being studied, including reproductive hazards and precautionary measures to be followed by workers for all hazards.
b. Names and qualifications of each Contractor's representative in charge of the Work and present at the Job Site when tank cleaning and repair work will be performed.
c. Identification of supervisory personnel and alternates responsible for Site safety/response operations.
d. Determination of levels of personal protection to be worn for various Site operations.
e. List of equipment with adequate nomenclature by item, that will be used at the Job Site and the date and location where this equipment can be inspected by the Contracting Officer.
SECTION 33 01 50.60 Page 7
f. Establishment of work zones (exclusion area, contamination area, and support area).
g. Establishment of a tank entry and work permit program in accordance with 29 CFR 1910.146 , EM 385-1-1 , and NFPA 326 .
h. Establishment of decontamination methods and procedures.
i. Determination of the number of people required to enter the contamination zones during the initial entries and subsequent operations.
j. Establishment of emergency procedures, such as: Escape routes, fire protection, signals for withdrawing work parties from Site, emergency communications, wind indicators, including Navy notification.
k. Identification and arrangements with nearest medical facility for emergency medical care for both routine-type injuries and toxicological problems. Submit name, location, and telephone number of this medical facility.
l. Establishment of continual air and personnel monitoring procedures.
m. Establishment of procedures for obtaining and handling potentially contaminated samples.
n. Identification of medical monitoring program, including respirator medical qualification examination for each individual at the Work Site.
o. Identification of training plan to be instituted, including contents of 29 CFR 1910.1200 and 29 CFR 1910.134 ; its training contents; and instructor with appropriate training certification. Training plan must also include counseling to each employee on reproductive hazards.
p. Establishment of a respiratory protection program conforming to
29 CFR 1910.134 .
q. Establishment of a hazard communication program ( 29 CFR 1910.1200 ).
1.5.11.4 Work Plan
The shut down or interruption to normal operations or traffic must be listed on the progress schedule and submitted to the Contracting Officer.
1.5.11.5 Hazardous Waste Disposal Plan
Prepare a Hazardous Waste Disposal Plan and submit within 45 calendar days after Contract Award for approval by the Contracting Officer. The Hazardous Waste Disposal Plan must comply with applicable requirements of Federal, State, and local hazardous waste regulations and must address the following:
a. Identification of hazardous wastes associated with the Work, including a sampling and testing plan for each waste stream, the purpose of each test, and the rationale for evaluating the test results. Indicate the representative sampling and specific testing methods, number of samples, and the name and qualifications of the testing laboratory.
SECTION 33 01 50.60 Page 8
b. Estimated quantities of wastes to be disposed in the cleaning of each tank and a description of arrangements made for storage and disposal.
c. Names and qualifications of each Contractor that will be transporting, storing, treating, and disposing of the wastes. Include the facility location and a 24-hour point of contact. Furnish two copies of hazardous waste permit applications, permits, and EPA Identification numbers.
d. Names and qualifications (experience and training) of personnel who will be working on-site with hazardous wastes.
e. List of waste handling equipment to be used in performing the work, to include cleaning, treatment, volume reduction, and transport equipment.
f. Spill prevention, containment, and cleanup contingency measures to be implemented.
g. Work Plan and schedule for waste removal and disposal.
h. Cost for hazardous waste disposal according to this Plan.
1.5.11.6 Tank Certification of Safety
Submit certification, in accordance with NFPA 326 , from a CIH stating that tank is safe for hot work and that special precautionary measures have been taken for workers to enter the tank to perform the Work.
1.5.11.7 Training Certification
Submit certifications signed and dated by the CIH specified in the testing plan and by each employee stating that the employee has received training on work practices.
1.5.11.8 Hazardous Waste Permits
Submit copies of hazardous waste permit applications, permits, and EPA Identification numbers of the transporter, treatment, storage and disposal facility that will be accepting hazardous waste. Include the facility location and a 24-hour point of contact.
1.5.11.9 Non-Hazardous Waste Permits
Submit copies of permits for disposal site for non-hazardous residues and wastes.
1.5.12 Test Results
1.5.12.1 Required Test Reports
Submit test results required by MIL-A-22262 , for blasting abrasive.
Submit Contractor's independent tests of tank contents (water, sediment, and sludge). Submit tank cleaning test panel results, including water pressure and temperature and nozzle distances used during tank washing procedure.
1.5.12.2 Air Monitoring
Submit monitoring results to the Contracting Officer within 2 working days
SECTION 33 01 50.60 Page 9 after the samples are taken, signed by the testing laboratory employee performing the air monitoring, the employee that analyzed the sample, and the CIH.
1.6 DELIVERY AND STORAGE
Deliver equipment and materials to the Site in an undamaged condition bearing the manufacturer's name and brand designation. Store equipment and materials off the ground to provide proper ventilation, drainage, and protection against dampness. Replace defective and damaged equipment and materials.
1.7 JOB CONDITIONS
1.7.1 Ventilation
Maintain a vapor-free condition throughout the course of the work inside the tank. The air movers must be non-sparking, explosion-proof, electrically operated or air-driven exhaust type. A rate of one air change per hour must be the lowest acceptable rate, for tanks under 30,000 BBL. Air movers must be kept in operation whenever workers are in the tanks; except the air movers must be shut down 15 minutes before taking tests.
1.8 SCHEDULING AND SEQUENCING
1.8.1 Sequence of Primary Phases of the Cleaning Procedure
a. Planning the operations.
b. Preparation for cleaning.
c. Vapor-freeing of the tank.
d. Cleaning the tank.
e. Clean-up, residue disposal, inspection, and acceptance.
1.8.2 General Scheduling
Complete the Work specified in this Section before any other work in the tank is started. The Work includes the complete interior cleaning of the storage tanks.
PART 2 PRODUCTS
2.1 MATERIALS
Submit identification for the items by designated name, Specification number, Project contracting number, and intended use. Submit Safety Data Sheets for materials to be used at the Job Site, in accordance with
29 CFR 1910.1200 .
2.1.1 Cleaning Agents
a. Detergent: FS O-D-1276 .
b. Solvent: MIL-PRF-680 , Type II, minimum flashpoint of 140 degrees F.
SECTION 33 01 50.60 Page 10
c. Approved commercial cleaning agent.
2.2 EQUIPMENT
Furnish necessary clothing and equipment for the Work and protection of people entering the tank. Electrical equipment and wiring must be in accordance with NFPA 70 , Class 1, Group D, Division 1. Provide any item or items for the protection of these people including but not limited to the following:
a. Gasoline-Oil-Resisting Rubber Gloves and Boots: Gauntlet type and conductive type respectively (acid-proof rubber is an acceptable material); furnished for each person entering or working inside the tank or handling sludge materials on the exterior of the tank, plus one extra pair each for emergency use.
b. Cotton Coveralls and Hard Hat: Light colored; one change per person per day, and an adequate supply of chemical-resistant disposable coveralls to be worn over cotton coveralls.
c. Respiratory Protection: Provide one of the following types of NIOSH-approved respiratory protective equipment for each person working inside the tank, plus one extra for emergency use.
NIOSH 99-109 listing constitutes NIOSH approval.
(1) Self-contained breathing apparatus with a full facepiece operated in a positive pressure mode.
(2) A combination respirator which includes a Type C supplied-air respirator with a full facepiece operated in a positive pressure mode and an auxiliary positive pressure self-contained breathing apparatus. Provide and use two-way communication equipment when cleaning underground tanks larger than 50,000 gallons capacity or where manhole accesses are deeper than 10 feet from the working level.
(3) The CIH may specify air line (Type C) respirator in place of those specified above; however, the decision must be based on the results of personal monitoring.
(4) Use Type CE respirator for abrasive blasting inside the tank.
(5) CIH must specify respiratory protection if required for personnel handling sludge material outside of the tank.
d. Safety Harness: For each person working inside tank, plus one extra for outside the tank.
e. 1/2-inch Diameter Life Rope of Required Length: For each person working inside the tank.
f. Breathing-Air Supply Source: 29 CFR 1910.134 .
g. Combustible Gas Indicator, Hydrogen-Sulfide (H2S) Indicator, Benzene Indicator, and Oxygen Meter.
h. Shovels, Buckets, Brooms, Wrenches, Scrapers, Squeegees, Wire Brushes, Scrub-Brushes, Ladders, Staging, and Other Tools: Do not use brooms or brushes that have plastic or synthetic bristles.
SECTION 33 01 50.60 Page 11
i. Lighting: UL 844 , explosion-proof, minimum 50 footcandle, floodlight type, or Mining Enforcement and Safety Administration (MESA) approved, explosion-proof, portable battery-powered light.
j. Air Movers for Tank Ventilation: Explosion proof electrically operated or air driven. Non-ferrous fan blades. Use velometers for measuring velocity.
k. Disinfectant for Cleaning Face Masks: Cleaner-sanitizer for cleaning and disinfecting respirator facepieces as specified in 29 CFR 1910.134 , Appendix B-2.
l. Soap for Personnel Washing: Non-phosphate type.
m. A.B.C. Fire Extinguishers: UL listed 2A: 40B: C, 2A: 20B: C, or 4A: 30B: C; minimum 15 pound capacity.
n. First Aid Kit: One 16-unit kit for each 25 persons.
PART 3 EXECUTION
3.1 PREPARATION FOR ENTRY
Prepare the tank for entry in accordance with NFPA 326 . Isolate from sources of energy. Ensure vapors have been controlled or removed.
Identify potential hazards and apply control measures to mitigate the hazards. Test and monitor atmospheric conditions to ensure conditions of the Marine Chemist Certificate safety designations have been met.
3.1.1 Isolation From Piping
For tank cleaning prior to out-of-service inspection and minor cold repairs, close the double block and bleed isolation valves and remove the body cavity plugs from the valves. Monitor the body cavity for fuel and maintain the valves in this condition for the duration of the cleaning, inspection, or minor cold repairs, not to exceed one month. Secure the valves in the closed position with mechanical means. Perform lockout tagout procedures on the valves.
For ordinary cleaning prior to out-of-service inspection and hot work or when nozzles are not equipped with double block and bleed valves, or for outages lasting longer than one month, disconnect piping connected to the tank. Provide a solid-plate line blank between two flanges near the tank in accordance with ASME B16.48 , or remove a valve or piece of pipe and provide a blind flange compliant with ASME B16.5 to isolate tank. For underground tanks where connected pipelines are buried, blind off the pipelines at the nearest valve box. Isolation means must be of sufficient strength to withstand pressure which might be exerted by the product being blanked off, and must be gasketed on both sides if blind flange is inserted between two flanges. Do not disconnect piping or valves until it is certain the line has been defueled.
Isolate all piping connected to the tank. Perform lockout tagout procedures on any valve remaining connected to the tank.
3.1.1.1 Thermal Relief
Evaluate thermal relief capability on active facility piping isolated from
SECTION 33 01 50.60 Page 12 the tank. Should isolation means result in a segment of active piping unprotected from thermal overpressure, provide temporary means consistent with API Std 521 to relieve the overpressure. Consult with operators to determine existing relief pressures and set temporary relief means to ensure overpressure does not occur.
3.1.2 Lockout Tagout
Perform lockout tagout on all electrical circuits and sources of energy to the tank in accordance with EM 385-1-1 and NFPA 326 .
3.1.3 Removal of Ignition Sources
Remove sources of ignition from the cleaning area. Do not permit ignition producing devices, including matches, lighters or cigarettes, within 100 feet upwind and 200 feet downwind of a tank, or inside the tank farm, or within the tank firewall, whichever is farther.
3.1.4 Survey of Hazardous Areas
Carefully survey the entire area around the tank to be cleaned to ensure that there are no vapors present in the pit, low places, or hazardous areas and that all unauthorized personnel are cleared from the area.
Ensure that there is no possibility of anyone smoking in the immediate vicinity. Hazardous areas are defined as follows:
a. Interior of tanks.
b. Areas within 100 feet from points having flammable vapor emissions which, for example, are from the exhaust manholes of tanks under repair, open vents or pressure vacuum vents (breather valves) of active tanks in the vicinity of tanks under repairs or cleaning.
CAUTION: Allowance must be made for 4 or more miles per hour winds by increasing the size of the hazardous area to a minimum of 200 feet on the downward side.
3.2 PROJECT CONDITIONS
3.2.1 Permission for Each Entry Into a Tank
Obtain written permission from the Contracting Officer prior to each entry into a tank. Permission will be granted only under the following conditions:
a. The Contractor's qualified supervisor is present.
b. The Contractor's personnel have been briefed by the supervisor on the procedure and role of each employee in the event of an emergency.
c. Required equipment is approved and properly located.
d. Personnel are properly equipped with properly fitted protective equipment and have received adequate training from a qualified instructor.
e. The entire area adjacent to the tank is secured.
f. A minimum of two persons outside and two or more persons inside of each tank are provided at all times during cleaning operations.
SECTION 33 01 50.60 Page 13
g. Tank air is monitored and corrective action is taken to ensure that the vapor concentration is less than 10 percent of the lower flammable limit (LFL), hydrogen sulfide is less than 10 ppm permissible exposure level (PEL), benzene is less than 1 ppm PEL and oxygen content is a minimum of 19.5 percent.
h. An NFPA certified "Marine Chemist" or CIH has certified that the tank is safe for hot work, and that the required special precautionary measures have been taken due to the potential health hazard to the worker that still exists, even when the vapor concentration is well below the LFL. The Contractor must be responsible for reviewing the Record Drawing(s) of the tank to be cleaned.
i. People entering the area leave smoking materials such as cigarettes and flame-producing devices at a previously determined location.
j. When Work involves handling and disposal of hazardous waste, the Contractor has a copy of 40 CFR 260 , 40 CFR 261 , 40 CFR 262 , 40 CFR 263 , 40 CFR 264 , 40 CFR 265 , and 40 CFR 266 in his possession.
k. Permit only personnel authorized in the Safety Plan within 100 feet of the tank perimeter.
3.2.2 Traffic Control
Direct traffic minimum 200 feet away from the tank cleaning area. Set up road blocks and warning signs. Do not operate vehicles in hazardous areas.
3.2.3 Lavatory Facilities
Arrange for lavatory and toilet facilities.
3.2.4 Miscellaneous
Ensure that the manufacturers have labeled containers holding products involving hazards in use or storage, in accordance with 29 CFR 1910.1200 .
Label containers used to store, transport, or dispose of hazardous waste in accordance with 40 CFR 260 , 40 CFR 261 , 40 CFR 262 , 40 CFR 263 , 40 CFR 264 , 40 CFR 265 , and 40 CFR 266 and State Regulations. Remove small objects of ferrous metal within the working areas to prevent the accidental striking of a spark. Place equipment upwind of tank openings at highest elevation possible; do not place in a spot lower than the surrounding terrain. Review drawings of the tank to be cleaned and brief workers on the location of pits, sumps, piping, or other tank appurtenances which could be hazardous to personnel. Provide floodlights to illuminate the Work Area without the need for battery operated handlights. Provide scaffolding, platforms, and ladders for secure, safe accessibility to tank surfaces. Install electrical equipment in accordance with API RP 500 . Provide floodlights to illuminate the Work Area without the need for battery operated handlights. Do not use artificial lights inside tank until the tank is vapor-free.
3.2.4.1 Grounding and Bonding for Equipment
Provide grounding and bonding for equipment which may generate static electricity, including air hose to sandblast nozzle. Do not pass the air hose through an area where flammable vapors may exist.
SECTION 33 01 50.60 Page 14
3.2.4.2 Fire Extinguishers
Furnish two carbon-dioxide fire extinguishers of minimum 15 pounds capacity each, in the immediate vicinity of the work. Provide a continuous fire watch. CAUTION: Do not discharge high pressure carbon dioxide extinguishers where explosive vapors exist since the discharge can cause a spark which will ignite the vapors.
3.2.4.3 Disconnection of Pipelines
For normal tank cleaning prior to out-of-service (internal) inspection and minor cold repairs, close the double block and bleed valves on the tank nozzles connected to piping and remove the body cavity plugs from the bottoms of the valves and bleed the valves for the duration of the cleaning, inspection or minor cold repairs. Perform lock-out/tag-out procedures on the valves.
For cleaning prior to hot work or when nozzles are not equipped with double block and bleed valves, or for extended outages lasting longer than one month, disconnect pipelines connected to the tank. Provide a solid-plate blind flange between two flanges near the tank, or remove a valve or piece of pipe and provide a blind flange to prevent flammable material from entering the tank. For underground tanks where connected pipelines are buried, blind off the pipelines at the nearest valve box.
Blind flanges must be of sufficient strength to withstand pressure which might be exerted by the material being blanked off, and must be gasketed on both sides if blind flange is inserted between two flanges. CAUTION:
Do not disconnect piping or valves until it is certain the line has been emptied of fuel.
3.2.4.4 Removal of Ignition Sources
Remove sources of ignition from the cleaning area. Do not permit ignition producing devices, including matches, lighters or cigarettes, within 100 feet upwind and 200 feet downwind of a tank, or inside the tank farm, or within the tank firewall, whichever is farther.
3.2.4.5 Survey of Hazardous Areas
Carefully survey the entire area around the tank to be cleaned to ensure that there are no vapors present in the pit, low places, or hazardous areas and that all unauthorized personnel are cleared from the area.
Ensure that there is no possibility of anyone smoking in the immediate vicinity. Hazardous areas are defined as follows:
a. Interior of tanks.
b. Areas within 100 feet from points having flammable vapor emissions which, for example, are from the exhaust manholes of tanks under repair, open vents or pressure vacuum vents (breather valves) of active tanks in the vicinity of tanks under repairs or cleaning.
CAUTION: Allowance must be made for 4 or more miles per hour winds by increasing the size of the hazardous area to a minimum of 200 feet on the downwind side.
3.2.4.6 Exit from a Tank During Emergencies
To permit quick, free exit from a tank during emergencies, keep the area around the tank openings and emergency routes clear of obstructions.
SECTION 33 01 50.60 Page 15
3.3 INSPECTION
3.3.1 Inspection of Equipment
3.3.1.1 Respirators
Respirator users must inspect their respirators in strict accordance with the instructions provided by the manufacturer.
3.3.1.2 Air Hose from Breathing-Air Supply
If air line respirators are used, ensure that:
a. There are no breaks in outside covering;
b. Condition of gaskets is good;
c. Connections are tight; and
d. There are no restrictions in the hose.
3.3.1.3 Safety Harness and Life Line
Ensure that:
a. There is no frayed or weak material; and
b. Condition of harness is good.
3.3.1.4 Breathing-Air Supply Source
Ensure:
a. Good working condition;
b. Location in vapor-free area;
c. Compliance with 29 CFR 1910.134 for breathing air quality, frequency of air analysis, and presence of safety devices; and
d. Backup air supply source.
3.3.1.5 Monitoring Equipment
Calibrate each day before use:
a. Combustible gas indicator.
b. Oxygen meter.
c. H2S Indicator.
3.3.1.6 Other Equipment
Ensure:
a. Proper grounding and bonding;
SECTION 33 01 50.60 Page 16
b. Explosion-proof motors; and
c. Explosion-proof lighting.
3.3.2 Personnel Inspection
3.3.2.1 Clothing
Personnel for Proper Attire Commensurate with Hazards Involved: Check for:
a. Clean clothing in good condition (wear freshly laundered clothing at the beginning of the Job and at the start of each workday thereafter).
b. Boots and gloves of approved type and in good condition.
3.3.2.2 Breathing-Air Supply
If air line respirators are used, ensure that air is supplied to the facepiece at a rate of 4 to 15 cfm. If self-contained breathing apparatus are used, ensure sufficient number of full replacement cylinders are available to last the duration of the Job.
3.3.2.3 Harness and Lifeline
Harness and lifeline must be in good condition and properly attached.
3.3.2.4 Gum or Tobacco Chewing
Ensure that gum or tobacco chewing is prohibited.
3.3.2.5 Physical Defects or Injuries
Ensure that people have no physical defects or injuries which may prevent their wearing respirators or which may cause rescue to be difficult. No beards, sideburns, or large mustaches will be allowed on people who must wear respirators.
3.3.2.6 Alcoholic Beverages and Drugs
Ensure that people entering the tank are not under the influence of alcoholic beverages or drugs.
3.3.2.7 Counseling on Reproductive Hazards
Ensure that all employees have been counseled on and fully understand the reproductive hazards related to Work in contaminated areas or in leaded gasoline or chemically contaminated tanks since they may be seriously affected by organic lead compounds or other chemical contaminants.
3.3.2.8 Hazardous Areas
Check hazardous areas as defined in Paragraph "Survey of Hazardous Areas".
SECTION 33 01 50.60 Page 17
3.4 TABLE OF TANK HISTORY
TANK
NUMBER
TANK LOCATION TANK
NOMINAL
CAPACITY
DATE
CONSTRUCTED
TYPE OF
LINING
TYPE OF
FUEL
1 WEST RAMP
WRIGHT-PATTERSON
50,000
GALLONS
APPROX. 1950 TYPE 4 F-24
2 WEST RAMP
WRIGHT-PATTERSON
50,000
GALLONS
APPROX. 1950 TYPE 4 F-24
3 WEST RAMP
WRIGHT-PATTERSON
50,000
GALLONS
APPROX. 1950 TYPE 4 F-24
4 WEST RAMP
WRIGHT-PATTERSON
50,000
GALLONS
APPROX. 1950 TYPE 4 F-24
3.5 FUEL REMOVAL
All possible fuel will be pumped or otherwise removed from the tanks by the Contractor, in coordination with the Government. Consider unattainable remaining fuel contaminated or waste fuel; pump remaining fuel into 55-gallon drums or other suitable containers for disposal in accordance with approved procedures meeting local, State, and Federal regulations. Dispose of remaining fuel emulsions in accordance with applicable local, State, and Federal regulations. Drums or tanks used for containerizing waste fuel will be furnished by the Contractor. Oil/water separator for fuel separation will be furnished by the Government.
3.6 IDENTIFICATION OF TANKS WITH HAZARDOUS WASTE SLUDGES AND RESIDUES
The following tank is known or suspected to contain hazardous wastes:
TANK NUMBER TYPE OF FUEL HAZARDOUS WASTE, STATUS, TYPE AND
BASIS-KNOWN (OR SUSPECT)
1 F-24 Sludge and sandblast residue, ignitability
2 F-24 Sludge and sandblast residue, ignitability
3 F-24 Sludge and sandblast residue, ignitability
4 F-24 Sludge and sandblast residue, ignitability
3.7 TANK CLEANING
For the interior of the tanks, the shell, bottom, columns, roof, roof beams, and interior accessory system components such as pumps, piping, and ladders, must be cleaned, free of dirt, scale, loose materials, fuel, oil, grease, sludge, and other deleterious materials.
SECTION 33 01 50.60 Page 18
3.7.1 Monitoring
Monitoring of airborne concentrations of benzene in accordance with 29 CFR 1910.1028 , and as specified herein. Air monitoring, testing, and reporting must be performed by a CIH or an Industrial Hygiene (IH) Technician who is under the direction of the CIH.
a. The CIH or the IH Technician under the direction of the CIH must be on the Job Site directing the monitoring, and inspecting the Work to ensure that the requirements of the Contract have been satisfied during the entire operation.
b. Take personal air monitoring samples on employees who are anticipated to have the greatest risk of exposure as determined by the CIH. In addition, take air monitoring samples on at least 25 percent of the work crew or a minimum of two employees, whichever is greater, during each work shift.
c. Submit results of air monitoring samples, signed by the CIH, within 2 working days after the air samples are taken. Notify the Contracting Officer immediately of exposure to 0.5 ppm for benzene.
3.7.1.1 Monitoring During Tank Cleaning Work
Perform personal and area monitoring during the entire tank cleaning operation. Sufficient area monitoring must be conducted at the physical boundary at all times to ensure unprotected personnel are not exposed above 0.5 ppm for benzene. If the outside boundary benzene levels are at or exceed 0.5 ppm, work must be stopped and the CIH must immediately correct the condition(s) causing the increased levels and notify the Contracting Officer immediately. The CIH must review the sampling data collected on that day to determine if condition(s) requires any further change in work methods. Tank cleaning work must resume when approval is given by the CIH. The Contractor must control the benzene levels to less than 0.5 ppm at all times. As a minimum, conduct area monitoring daily on each shift in which tank cleaning operations are performed in areas immediately adjacent to the control area. For outdoor operations, at least one sample on each shift must be taken on the downwind side of the control area. If adjacent areas are contaminated, clean and visually inspect contaminated areas. The CIH must certify that the area has been cleaned of contamination.
3.7.2 Water Removal and Disposal
Pump or otherwise remove water from the tank. This water must be packaged, labeled, stored, transported, treated, and disposed of in accordance with 40 CFR 260 , 40 CFR 261 , 40 CFR 262 , 40 CFR 263 , 40 CFR 264 , 40 CFR 265 , and 40 CFR 266 .
3.7.3 Sludge and Sediment Removal and Disposal
Squeegee or brush any sludge, sediment, or other loose material into piles, shovel into buckets or other suitable containers, and remove from the tank.
Package, label, store, transport, treat, and dispose of hazardous sludge and sediment in accordance with 40 CFR 260 , 40 CFR 261 , 40 CFR 262 , 40 CFR 263 , 40 CFR 264 , 40 CFR 265 , 40 CFR 266 , and State and local
SECTION 33 01 50.60 Page 19 regulations.
3.7.4 Washing
After water, fuel, and sludge have been removed, thoroughly wash the tank interior. Contractor must limit the water pressure during washing so that it does not cause damage to the tank. Contractor must clean a representative test panel with their planned washing procedure. Test panel access must be provided to and examined by the Contracting Officer to determine whether coating damage is occurring as a result as a result of the Contractor's washing procedure. Contractor must modify water temperature and pressures based on cleaning test panel results. Maximum allowable pressure on tank surfaces must be 200 psig and maximum allowable temperature of wash water must be 135 degrees F. Prior to cleaning the tank, tests must be conducted to determine the minimum distance of the nozzle to the steel to prevent damage to the tank coating. Perform Quality Control to inspect the cleaning during the process to ensure the coating is not being removed. Minimize the use of water; substitute brush blasting when practical. Start washing at the top of the walls and columns and work down to the floor. Wash the floor last starting from the sides and working towards the sump. Wash to remove oil, sludge, wax, tar, and other fuel residue adhering to the surface. Wash by any one or a combination of the following methods:
a. Use only fresh water under pressure.
b. Hand-scrub the surfaces vigorously with long-handled stiff-bristle brushes. Wet the brushes intermittently during scrubbing process.
For heavily oil-soaked areas which still appear to retain some residue after first scrubbing, repeat the scrub process until clean.
c. Rinse the surfaces thoroughly with fresh water.
d. Brush-off blast clean.
3.7.5 Wash Water and Sediment Removal
During the washing process, operate a portable pump continuously with suction hose extended to the tank bottom to remove water, detergent, dirt, oil, or other loose materials washed off. Following the final rinse, pump, squeegee, and mop the tank dry.
a. Prior to discharge or disposal, test the wash water, sediment, and sludge in accordance with Paragraph "Water, Sediment, and Sludge Analysis". The Contractor must furnish temporary tanks to hold water until testing is completed.
b. The water is non-hazardous and can be disposed of into the facility's oil water separator, provided the water has rested and any emulsified water has separated prior to entry into the oil water separator.