This document outlines a federal contract solicitation for construction services. The U.S. Army Corps of Engineers Engineering District Louisville is seeking to award a contract to construct a new HC-130J general maintenance hangar at Patrick Air Force Base in Florida. The estimated construction cost is between $10-25 million. The NAICS code for this opportunity is 236220. As the size determination is $39.5 million, vendors must ensure their business size listed in SAM is correct for this NAICS code. This is a full and open procurement that requires a 10% price evaluation preference for HUBZone small businesses. Offerors must comply with CCR/ORCA requirements through SAM. No contract will be awarded until appropriated funds are made available for this acquisition.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For HC-130J General Maintenance Hangar Patrick AFB, FL
P2: 472236
Design-Bid-Build
Specifications Volume 1 of 3
Certified Final Submittal
06 August 2020
W912QR20B0012-0002
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR20B0012Specs_Vol1-0002
Louisville District
HC-130J GENERAL MAINTENANCE HANGAR
Patrick AFB, FL
Certified Final – Amendment 0002 Specifications – Volume I Project Number: SXHT203000 P2 Number: 472236 July 2020
HC-130J General Maintenance Hangar 107778AM02
THIS PAGE INTENTIONALLY LEFT BLANK
HC-130J General Maintenance Hangar
Patrick Air Force Base, FL
PN: SXHT203000
July 30, 2020 Burns & McDonnell 9400 Ward Parkway
Kansas City, MO 64114
CERTIFICATION PAGE
CIVIL STRUCTURAL ARCHITECTURAL
FIRE PROTECTION MECHANICAL ELECTRICAL
7- 30-2020 7-30-2020
7-30-2020 07/30/2020
THIS PAGE INTENTIONALLY LEFT BLANK
CIVIL/OPS/ENVIRONMENTAL BR
ATTN: GLENN W MOON
600 DR M L KING JR PL RM 821
LOUISVILLE KY 40202-2236
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
1 30
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR20B0012
X 9B. DATED (SEE ITEM 11)
14-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Aug-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964860
FACILITY CODECODE
EMAIL:TEL:
W912QR20B0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF CHANGES AMEND 0002
Solicitation W912QR20B0012 for the Construction of HC-130J General Maintenance Hangar at Patrick Air Force Base, Florida is hereby modified as follows:
1. Offerors must acknowledge all amendments.
2. The due date and time for bid submission is extended from 31 August 2020 at 10:00 AM Eastern Time to 7 September 2020 at 10:00 AM Eastern Time.
3. DRAWINGS ARE DELETED AND REPLACED IN THEIR ENTIRETY TO INCLUDE:
SUMMARY OF CHANGES
S-001 Removed crane in General Notes
S-002 Revised Note 3 in A2 Revised Note C.17 Deleted Note G
S-003 Revised Abbreviations
S-004 Revised Design Wind Pressures Table Revised Wind Isometric
S-005 Revised Wind Isometric
S-006 Revised B3
S-007 Revised slab thickness
S-008 Removed Dumpster Enclosure Foundation
S-009 Revised Notes
S-010 Removed veneer support angle from B2 Correct DBA Callout in Detail C3
S-011 Revised A1/S-011
S-100 Reduced plan dimensions Modified door track foundation Moved portion of shops to Bid Option A Removed cooling tower foundation
S-101 Reduced width of exterior grade beam Removed sanding booth pit
S-102 Reduced width of exterior grade beam
S-103 Reduced width of exterior grade beam Reduced plan dimensions Modified door track foundation
S-104 Reduced width of exterior grade beam Reduced plan dimensions Modified door track foundation Moved portion of shops to Bid Option A
S-105 Reduced width of exterior grade beam Revised Option F to be Option B
S-106 Reduced plan dimensions Reduced width of exterior grade beam Removed Paint Booth pit Revised Option H to be Option C
S-107 Added sheet
S-110 Reduced plan dimensions Modified door track foundation Moved portion of shops to Bid Option A Removed cooling tower foundation
S-111 Reduced width of exterior grade beam Removed sanding booth pit
S-112 Reduced width of exterior grade beam
S-113
Reduced plan dimensions Modified door track foundation
S-114
Reduced plan dimensions Modified door track foundation Moved portion of shops to Bid Option A
S-115
Revised Option F to be Option B
S-116
Reduced width of exterior grade beam Removed Paint Booth pit Revised Option H to be Option C
S-117
Added sheet
S-120 Revised Option Callouts.
S-121
Reduced framing sizes at mechanical equipment.
Removed D1/S-121
S-130
Revised Note 9
S-131
Removed roof penetrations Removed roof stack framing from project and annotated as “Future” Guy Wire annotation revised to Guy Cable
S-132
Added Note 10 on Plan
S-133
Removed roof penetration
S-134
S-136 Reduced plan dimensions Removed roof penetration Correct ED Callout
S-135 Added SJI Bridging callouts
S-137 Added sheet
S-140 Revised plan dimensions Added bracing
S-143 Revised plan dimensions Added bracing Revised member sizes
S-144 Revised plan dimensions Added bracing Revised member sizes
S-151 Revised plan dimensions
S-160 Revised plan dimensions
S-163 Revised plan dimensions Revised member sizes Reduced extent of SF1 Added truss types
S-164 Revised plan dimensions Revised member sizes Reduced extent of SF1 Added truss types
S-170 Revised plan dimensions
S-173 Revised plan dimensions Revised member sizes Reduced extent of SF1 Added truss types
Removed roof hatch Removed roof penetrations.
Removed roof stack framing from project and annotated as “Future”
S-174
Revised plan dimensions Revised member sizes Reduced extent of SF1 Revised truss types
S-190
Deleted sheet
S-200 Revised dimensions and elevations Revised member sizes Revised brace connections Removed members originally supporting roof access ladder.
S-201
Revised member sizes
S-202
Revised elevations Revised member sizes
Revised truss type
S-203
Revised member sizes
Revised truss type
S-204
S-205
S-206
S-207
S-220
Revised hot-rolled girts to cold-formed steel girts
S-221
S-222
Omitted lower girts at door pockets
S-223
Revised hot-rolled girts to cold-formed steel girts Omitted lower girts at door pockets Added girts at new wall panel
S-224
S-225
S-226
S-230 Removed framing supporting crane
S-231
Deleted Sheet
S-300 Revised mechanical cleanout and rail depression sizes at door track foundation
S-301
Removed CMU and foundation curb at door pockets.
S-302 Revised exterior grade beam widths
S-303
Revised exterior grade beam widths
S-304
Revised exterior grade beam widths
S-305 Revised exterior grade beam widths
S-306 Removed CMU and foundation curb at door pockets.
S-307 Deleted Sheet
S-310 Added C4
S-400 Revised splice elevation Revised estimated top of column elevations
S-410 Added two additional truss types Revised member sizes Moved truss camber diagram to S-411
S-411 Added sheet
S-412 Revised details
S-413 Revised dimensions Revised member sizes Revised splice plate callout in B2 Correct the truss seat callout on C3
S-414 Revised framing details
S-420 Revised framing details
S-421 Revised framing details
S-422 Revised framing details
S-423 Revised framing details
S-430 Revised Sections C2 and A2
S-431
Revised Sections C2 and A2
S-432 Revised Section B4
S-433
Revised framing details
S-434
S-436
S-437
S-438
Revised Section C3 and C4
S-439
S-440
S-441
S-450
Removed crane framing
S-451
S-452
S-500
Eliminated channel girt and sloping girt details
S-501 Revised framing details to accommodate cold-formed steel girts
S-502
Revised soffit framing
S-503
S-504
S-505
S-506
S-507
S-515
LP001
Modified Occupant Load Calculations and Building Areas (Tables 10, 11 & 23)
LP002
Modified Life Safety Floor Plan to reflect revised layout
A-010
Modified Aircraft Clearance Plan for reduce hangar area.
A-011 Modified Aircraft Clearance Section for reduce hangar height.
A-050
Modified Air Barrier Floor Plan and Summary values to reflect revised layout
A-051 Modified Air Barrier Sections to reflect reduced hangar height.
A-100
Modified Overall Floor Plan to reflect revised layout
A-101 Floor Plan A1 – Removed roof climb ladder.
Floor Plan A1 - Removed reference to Sanding Booth relocation scope.
Floor Plan A1 - Modified wall perimeter construction.
Detail C4 – Modified detail to reflect revised wall construction.
A-102
Floor Plan A1 - Modified wall perimeter construction.
Floor Plan B4 – Modified wall perimeter construction.
Floor Plan B4 – Modified Option Label.
A-103
Floor Plan A1 - Modified Floor Plan to reflect revised layout Floor Plan B4 – Modified wall perimeter construction and OH Door location.
Floor Plan B4 – Modified Option Label.
A-104
Floor Plan A1 - Modified Floor Plan to reflect revised layout Floor Plan B4 – Modified wall perimeter construction.
Floor Plan B4 – Added Bid Option for Welding Room.
A-120
R.C. Plan A1 – Modified Overall Reflected Ceiling Plan to reflect revised layout and hangar door enclosure.
R.C. Plan A1 – Moved Bird Netting scope to Bid Option.
A-121 R.C. Plan A1 – Removed roof climb ladder and roof access hatch.
A-122
R.C. Plan B4 – Modified Option Label.
A-123
R.C. Plan A1 – Modified Plan to reflect revised layout. Modified enclosure of hangar doors.
R.C. Plan B4 – Modified Option Label.
A-124 R.C. Plan A1 – Modified Plan to reflect revised layout. Modified enclosure of hangar doors.
R.C. Plan B4 – Added Bid Option for Welding Room.
A-130
Roof Plan A1 – Removed roof access hatch and roof fall protection.
Roof Plan A4 – Added Welding Room as Bid Option.
Roof Plan B4 – Modified Option Label.
Roof Plan C4 – Modified Option Label.
A-201 Elevation A1 – Modified roof elevation height. Removed exterior masonry wainscot. Modified enclosure of hangar doors.
Elevation C1 – Modified roof elevation height. Removed exterior masonry wainscot. Modified enclosure of hangar doors.
A-202
Modified Exterior Finishes DescriptionA-202 Elevation A1 – Removed exterior masonry wainscot.
Elevation C1 – Modified roof elevation height. Removed masonry wainscot. Modified enclosure of hangar doors.
A-203 Modified Exterior Finishes DescriptionA-203 Elevation A1 – Added elevation of Welding Room Bid Option.
Elevation A2 – Modified Bid Option labels and added Welding Room to elevation.
Elevation C2 – Modified roof elevation height. Removed masonry wainscot. Modified enclosure of hangar doors.
Modified Exterior Finishes Description
A-204 Elevations A1 & A3 – Removed exterior masonry wainscot.
Elevation A4 – Added elevation in its entirety.
Elevations B1 & B3 – Modified hangar door pocket enclosure.
Modified Exterior Finishes Description
A-205 Removed masonry wainscot at all elevations.
Modified Exterior Finishes Description
A-206 Removed masonry wainscot at all elevations.
Elevations C1 & C3 – Relocated O.H. door as shown.
Modified Exterior Finishes Description
A-207 Section A1 – Modified section to reflect revised wall construction.
Elevation A3 – Removed exterior masonry wainscot.
A-208 Sheet DELETED in its entirety.
A-301 Section A1 – Modified roof elevation height.
Section C1 – Modified roof elevation height. Modified enclosure of hangar doors. Added interior soffit enclosure around hangar door tracks.
A-302 Section A1 – Modified roof elevation height. Modified enclosure of hangar doors. Added interior soffit enclosure around hangar door tracks. Removed exterior masonry wainscot.
Section C1 – Modified roof elevation height.
A-303 Section A1 – Modified roof elevation height. Modified enclosure of hangar doors. Added interior soffit enclosure around hangar door tracks. Removed exterior masonry wainscot.
Section C1 – Removed paint booth. Relabeled bid option.
A-321 Wall Section A1 - Modified enclosure of hangar door pocket.
A-322 Wall Section A1 – Modified wall construction to reflect removed masonry wainscot.
Wall Section A2 – Modified wall construction to reflect removed masonry wainscot.
A-323 Wall Section A4 – Modified wall construction to reflect removed masonry wainscot.
Wall Section A5 – Modified wall construction to reflect removed masonry wainscot.
A-324 Wall Section A2 – Modified wall construction to reflect removed masonry wainscot.
A-351
Detail A1 – Modified wall base detail to reflect removed masonry wainscot.
Detail C3 – Modified wall base detail to reflect removed masonry wainscot.
A-353
Wall Detail A1 – Modified wall construction to reflect removed masonry wainscot.
Wall Detail A2 – Removed detail in its entirety.
Wall Detail C1 – Removed detail in its entirety.
Wall Detail A4 – Modified expansion joint detailing.
A-354
Wall Detail A4 – Modified expansion joint detailing.
A-357
Roof Detail C1 – Modified expansion joint detailing.
A-358
Modified plan details to reflect removed masonry wainscot.
A-359 Detail B1 – Modified detail to reflect removed masonry wainscot. Modified expansion joint detailing.
Detail B4 – Modified expansion joint detailing.
A-401
Plan B4 – Relabeled bid option.
A-403
Plan B4 – Modified wall construction to reflect removed masonry wainscot. Relabeled bid option.
A-404
Sheet deleted in its entirety.
A-521
Deleted roof fall protection detail B1.
A-551 Deleted floor coating control joint C1 at hangar floor.
A-601
Revised Bid Option labels in Door Remarks.
Deleted Doors 101B & 101E.
Added hardware set for Door 105E.
Revised exterior openings to be aluminum doors and frames.
A-602
Modified Bid Option labels Added bid option schedule for Welding Room.
Revised exterior openings to be aluminum doors and frames.
A-604 Modified door details to reflect removed masonry wainscot.
Revised exterior door details for aluminum doors and frames.
A-605
Modified overhead jamb details to reflect removed masonry wainscot.
A-610
Modified hangar door plan and details to reflect revised enclosure.
A-611
Modified hangar door details for revised door configuration.
A-612
Modified hangar door details for revised door configuration
A-621 Modified window details to reflect removed masonry wainscot.
A-622
Modified Elevations A1 & B1 to reflect added louvers.
Section B4 - Modified expansion joint detailing.
A-631
Modified Louver Schedule to reflect design revisions.
Detail A1 – Modified detail to reflect removed masonry wainscot.
A-641
Removed Roof Ladder Details A2, A4, B2 & C2 in their entirety with deleted scope.
A-642 Sheet deleted in its entirety.
A-701 Removed hangar flooring bid options and finishes.
Removed floor finish ‘EF-1’ from several rooms and replaced with finish ‘CH-1’ and wall base
‘RB-1’.
Relabeled bid options.
A-710
Modified floor striping and sign locations for removed roof access ladder and hangar door and enclosure configuration.
A-711 Removed floor striping at deleted roof access ladder.
A-712
Relabeled bid option.
A-713
Modified floor striping and sign locations for removed roof access ladder and hangar door and enclosure configuration.
Relabeled bid option.
A-714 Modified floor striping and sign locations for removed roof access ladder and hangar door and enclosure configuration.
Added Welding Room bid option.
A-751 Modified signage schedule to reflect revised design.
A-753 Removed Exterior Sign Detail B5 in its entirety.
I-100 Removed “MISC EQUIPMENT LIST (GFGI) – (OPTION L).
Relabeled bid options.
I-111 Removed “MISC EQUIPMENT LIST (GFGI) – (OPTION L).
Removed Misc Equipment labels from floor plan.
I-112 Removed “MISC EQUIPMENT LIST (GFGI) – (OPTION L).
Removed Misc Equipment labels from floor plan.
Relabeled bid option.
I-113 Removed “MISC EQUIPMENT LIST (GFGI) – (OPTION L).
Removed Misc Equipment labels from floor plan.
Relabeled bid option.
I-114 Removed “MISC EQUIPMENT LIST (GFGI) – (OPTION L).
Removed Misc Equipment labels from floor plan.
Relabeled bid option.
FA001
Adjust fire alarm criteria for CIS exceptions.
FA101
Adjust design for new option C.
Provide FA devises at exits.
Remove unneeded tamper switch.
FA102
Adjust design for renaming of Options A and B. No changes to original design.
FX101
Adjust design for renaming of Options A, B, and C.
Move Enlarged views of options to FX501. No changes to original design
FX501
Adjust design for renaming of Options A, B, and C.
Apply enlarged views of bid options to sheets. No changes to original design
P-001 GFGI Legend added
P-100 Overall plan incorporates changes made to other sheets
P-101 Removed Cooling tower water line Removed EEW/S & EEW floor drains and associated piping Revised new Keyed Note 1 Added new Keyed Note 2
P-102 Removed EEW floor drains and associated piping
P-103 Removed EEW/S & EEW Floor drains and associated piping Aligned Hangar Trench Drain and door track drains with new locations Revised Keyed Note 2
P-104 Removed EEW/S & EEW floor drains and associated piping Relocated SS vent to room 139 Aligned Hangar Trench Drain and door track drains with new locations
P-105 Updated new Option B marks
P-106 Overall plan incorporates changes made to other sheets
P-107 Removed cooling tower fill lines Removed dust collection system Removed natural gas line serving MAU-PB-03 Removed EEW/S & EEW floor drains and associated vent piping
P-108 Removed EEW floor drains and associated vent piping Removed TP-3 from this sheet Updated Keyed Notes to new Option B
P-109 Removed natural gas line serving MAU-PB-03 Removed EEW/S & EEW floor drains associated vent piping Aligned Hangar Trench Drain and door track drains with new locations Breathing air controls systems removed from project as government furnished government installed (GFGI) equipment
P-110 Removed EEW/S & EEW floor drains associated vent piping Aligned Hangar Trench Drain and door track drains with new locations VTR moved to room 139 Created new Option A scope Added new Keyed Notes 3 & 4
P-111
Relocated TP-3 into Room 130.
Updated drawing to new Option B
P-401
Removed cooling tower fill lines Removed natural gas line serving MAU-PB-03 & MAU-01 Compressed air and breathing air equipment removed from project as GFGI equipment; piping to remain in project Revised new Keyed Notes
P-403
Removed natural gas line serving MAU-PB-03 Removed EEW/S & EEW floor drains Removed EEW/S & EEW floor drains Relocated TP-2 into Room 102 Removed CA and BA service in Room 102 Rerouted option C SS vent and VTR Updated drawing to new Option C
P-502 Breathing air equipment removed from project as GFGI equipment; piping to remain in project.
P-503
Removed view A1 Removed cabinet in view A2 Compressed air equipment removed from project as GFGI equipment; piping to remain in project.
P-504 Removed view A1
P-505
Adjusted FCO location in view A1 Edited requirements of view A4
P-601
Updated Trap Primer Schedule requirement and notes Renamed BFP-102 to BFP-02 and removed BFP-103 Edited Cleanout Schedule requirements
P-602
Compressed air and breathing air equipment removed from project as GFGI equipment Edited requirements of Thermostatic Mixing Valve Schedule
P-901
Removed EEW/S & EEW floor drains associated piping Updated drawing to new Option C
P-902
Removed EEW/S & EEW floor drains associated piping
P-903
Relocated TP-3
P-904 Removed natural gas service to MAU-PB-03 & MAU-01
P-905
Removed compressed air service from paint room Created new Option A scope Compressed air equipment removed from project as GFGI equipment; piping to remain in project.
P-906
Removed breathing air service from paint room Breathing air equipment and controls removed from project as GFGI equipment; piping to remain in project.
M-002
Removed MAU-01, EF-03 & 04 from Ductwork Construction and Leakage Testing Table Removed Paint Booth from Design Conditions Schedule
M-100 Overall plan incorporates changes made to other sheets
M-101
Removed connections to Sanding Booth Removed TOA duct Relocated Louver L21 and associated ductwork down to accommodate lower roof height Revised new Keyed Note 3.
M-102
Relocated Louver L20 and associated ductwork down to accommodate lower roof height
M-103
Removed duct connections to exhaust stacks.
Removed connections to Sanding Booth Revised size of louver L11.
Relocated Hangar make-up air louver to near Column lines C & 2.
Revised new Keyed Notes 1, 3, & 4
M-105
Relocated Hangar make-up air louver to near Column lines C & 9.
Revised new Keyed Notes 1, 2, 3, 6, & 7
M-106
Removed controls for MAU-01 & EF-04 Rerouted CHW piping Resized CHW piping
M-107
Added Keyed Note 2
M-108 Rerouted and resized CHW piping serving FCU-01 & 06
M-109 Created new Option A scope.
M-301 Created new Option A scope
M-302
Removed MAU-PB-03, EF-PB-08 and associated ductwork, piping and vent; Exhaust stack to remain Rerouted FCU-06 supply up to accommodate roll-up door Revised new Keyed Notes 1, 2, & 3
M-303 Removed duct work connecting to exhaust stacks and exhaust stacks Relocated Louver L21 down to accommodate lower roof height Revised new Keyed Notes
M-304 Relocated Louver L21 down to accommodate lower roof height
M-401 Removed MAU-01 and duct connections to MAU-01 Removed CHP-03 & 06 Clarified requirements with BOD tags Revised new Keyed Notes 1, 8, 9 & 10
M-402 Removed MAU-01 and piping serving MAU-01 Resized piping serving FCU-11 Removed Keyed Notes
M-403 Removed VAV-21, 22, & 23 and associated ductwork.
Removed EF-03 & 04 and associated ductwork Revised new Keyed Notes 3, 4, & 5.
M-404 Removed MAU-PB-03, EF-PB-08 and associated ductwork, exhaust stacks, gravity hood, piping and vent Rerouted FCU-06 supply up to accommodate roll-up door Revised new Keyed Notes
M-405 Removed view A3 Removed ACH-02 and associated piping Resized CHW piping serving ACH-01 Revised General Note 2
M-406 Removed view A3 Resized CHW piping Removed CHP-03, 04, 05 & 06 and associated piping Reconfigured CHW piping to accommodate constant primary only pumping configuration
M-501 Removed view C4
M-504 Removed view A3
M-505 Removed view A1 & A3
M-506 Resized partition in view A1 Revised Note C in view B3
M-507 Removed view A1 & A3
M-601 Removed MAU-01, EF-03 & 04 Clarified electrical requirements of AHU-01 and MAU-02 Revised notes on Fan Coil Unit Schedule Revised notes on Fan Schedule
M-602 Removed ACH-02, CHP-03, 04, 05 & 06, CWP-01, 02 & 03, VAV-21, 22 & 23 Revised requirement of ACH-01 Revised notes on Air Cooled Chiller Schedule Revised notes on HVAC Pump Schedule Revised pump values and notes on Variable Air Volume Box Schedule
M-603 Removed CV-101, 102, 103, 105 & 118-138 Revised Control Valve Schedule values & notes.
Removed Gravity Hood Schedule Added Note 2 to Expansion Tank Schedule Revised requirements of Air Separator Schedule Revised note requirements of Diffuser Register and Grille Schedule
M-604 Deleted sheet
M-610 Removed ACH-02, CHP-03, CHP-06, MAU-01 & MAU-PB-03 Created Option A scope Resized chilled water piping Rerouted piping serving FCU-01 & 06 Changed CV-104, 107, 110 valve types
M-611 Deleted sheet
M-612 Deleted sheet
M-702 Removed MAU-01 & Paintbooth Systems from Controls Architecture Clarified controls architecture chiller requirements
M-705 Added EF-11 to Option B
M-707 Deleted sheet
M-708 Deleted sheet
M-709 Deleted sheet
M-710 Deleted sheet
M-711 Removed ACH-02, CHP-03, 04, 05 06 and associated controls
Revised to accommodate constant primary only pumping and associated controls
M-712
Sequenced revised for one chiller operation only Sequence revised for constant primary pumping
M-713
Removed ACH-02, CHP-03, 04, 05 & 06 and associated control points Points revised to accommodate constant primary only pumping
M-714 Deleted sheet
M-715 Deleted sheet
M-716 Deleted sheet
M-717 Deleted sheet
M-719 Created Option A scope
M-721 Updated Option Lettering
M-722 Updated Option Lettering
M-723 Updated Option Lettering
M-724 Deleted sheet
M-719
Created Option A scope
M-901
Removed MAU-01, CHP-03, 04, 05 & 06, and associated piping, ductwork, and vent Resized CHW piping Added tags to clarify requirements
E-100
Removed Paint Booth
Revised base bid floor plan
ES101
Revised Parking Lot lighting layout Revised chillers layout Removed Option I and Option J Removed Keyed Note 11, 12 and 13 Added requirement to provide portable generator to building #9678
EG101
Revised floor plan with new base bid layout Revised grounding locations based on the new layout Keyed Note 7 – Revised Option F to be Option B Keyed Note 8 - Revised Option F to be Option B Keyed Note 10 - Revised to Not Used
Keyed Note 11 - Revised Option H to be Option C Keyed Note 12 - Revised Option H to be Option C Added Keyed Note 13
EG102
Revised floor plan with new base bid layout Keyed Note 5 – Revised Option F to be Option B Keyed Note 6 - Revised Option H to be Option C Added Keyed Note 8
EG401
Removed Detail C1
Revised Option H to be Option C Added Detail C3 Enlarged Plan for Option A Keyed Note 4 – Revised Option F to be Option B Keyed Note 5 - Revised Option H to be Option C Added Keyed Note 6
EG402
Added Detail B3 Enlarged Plan for Option A Keyed Note 5 – Revised Option F to be Option B Keyed Note 6 - Revised Option H to be Option C Added Keyed Note 7
EL 104
Revised floor plan to match new base bid layout
EL401
Keyed Note 1 – Revised Option F to be Option B
EL402
Added Detail A3 Enlarged Plan for Option A Keyed Note 1 – Revised Option H to be C
EL602
Added Schedule for Option A
EP101
Removed electrical equipment associated with removed options including but lot limited to CHWP-03, CHWP-06, MAU-01 and VFDs in Rm 141
Added 120V to motor damper Revised Keyed Note 3
Revised Keyed 4 to “NOT USED”
EP102
Keyed Note 1- Remove Reference to Manufacturer Keyed Note 2 – Revised Option F to be Option B Keyed Note 4 – Revised Option F to be Option B Removed 400Hz Converter and Cord Reel Remote Control from drawing
EP103
Keyed Note 1- Remove Reference to Manufacturer Keyed Note 6 – Revised Option H to be Option C Removed disconnect for structural crane Added 120V power to motorized damper
EP104
Revised floor plan to match new base bid layout Revised Keyed Not1 to “NOT USED” Keyed Note 2- Remove Reference to Manufacturer Removed 400 HZ cord reel\ Added 120V power to motorized damper
EP401
Keyed Note 2 – Revised Option F to be Option B
EP402
EP403
Removed Option J Revised Option H to be Option C Added Enlarged Plan for Option A Keyed Note 1 – Revised Option H to be C
EP501
Removed Detail A1 -400HZ Cord Reel
EP601
Keyed Note 1 – Revised Option F to be Option B Keyed Note 2 – Revised Option H to be Option C Panel EL1 Revised Circuit Breakers 15 and 17 Load Served column for correct options.
Panel L1 Revised Circuit Breakers 9 and 21 Load Served column for correct options.
EP602
Removed all mechanical loads associated with Option J
T-103
Revised floor plan to match new base bid
T-104 Revised floor plan to match new base bid layout
T-401 Revised Option labels
T-402 Revised Option labels
T-403 Added Sheet
VA100
Added limits of construction coordinates
GC005
Updated phasing limits Updated phasing notes
GC006
Updated phasing limits Updated phasing notes
GC007
Added note 6
CD100
Add demolition note 14
CD101
Removed parking lot bid option demolition work Added subbase removal requirement
CD102
Removed mill and overlay work for existing parking lot Added subbase removal requirement
CD103
Added subbase removal requirement
CD104
Added subbase removal requirement
CE110
Updated sheet to reflect new erosion control plan
CE111
Adjusted temporary sediment basin Added inlet protection to at the north end of the site
CE112
Removed silt fencing north of the existing parking lot
CE113
Shifted construction entrance to the south
CE121
Revised permanent seeding locations
CE121
Revised permanent seeding locations
CE123
Revised permanent seeding locations
CE124
Revised permanent seeding locations
CE150
Revised permanent seeding locations
CE501
Revised silt fence detail
CE502
Revised compost sock detail
CS100
Removed chiller bid option Removed parking bid option Added welding room bid option A
CS101
Shortened tug road north of Hangar Removed sidewalk on west side of Hangar Removed dumpster pad and enclosure Removed proposed parking spaces Revised chiller pad size
CS102
Removed proposed parking Removed mill and overlay of existing parking lot Removed sidewalk on north and east side of hangar Added stop sign at the intersection of the parking lot and tug road
CS103
Removed sidewalk on east side of Hangar Extended Hangar apron north to match the shortened Hangar
CS104
Removed sidewalk on east side of Hangar Extended Hangar apron north to match the shortened Hangar
CS111
Added bid option A for the welding room Moved door stoop for roll up door to the west side of the hangar for bid option C
CS201
Adjusted staking points for new site layout
CS202
Adjusted staking points for new site layout
CS203
Adjusted staking points for new site layout
CS204
Adjusted staking points for new site layout
CS210
Revised staking point tables for new staking point locations and elevations
CS211
Revised staking point tables for new staking point locations and elevations
CS401
Revised enlarged jointing plan C1 for smaller landside concrete apron Revised enlarged jointing plan A1 for larger airside concrete apron
CS503
Revised detail A3 to 100’ spacing for taxilane shoulder markings
CS506
Added stop sign detail Revised handrail detail bid option note
CG100
New site layout shown
CG101
Removed proposed grading for dumpster pad and enclosure Revised proposed grading around existing parking lot for removal of proposed parking spaces Removed landside cleanout key note
CG102
Revised proposed grading around existing parking lot for removal of proposed parking spaces Removed proposed grading for existing parking lot
CG104
Revised proposed grading at south east corner of Hangar
CG401
Revised enlarged jointing elevation plan C1 for smaller landside concrete apron Revised enlarged jointing elevation plan A1 for larger airside concrete apron
CU101
Revised structure SS-3 from a cleanout to a manhole
CU102
Electrical ductbank routing revised Updated pavement removal and replacement
CU103
Revised fire hydrant location
CU104
Revised fire hydrant location
CU201
Added profile C1 for building connection
CU505
Revised note 2 from 12,000 gallons to 8,000 gallons
4. SPECIFICATIONS ARE DELETED AND REPLACED IN THEIR ENTIRETY TO INCLUDE:
SUMMARY OF CHANGES
00 10 00 Price Breakout Schedule deleted and replaced in its entirety.
01 00 00 Added Nuclear gauges or equipment to SD-01 Precon Submittals Updated Installation Access requirements Added attachment for Construction project Sign Updated Basis of Design Requirements Updated Permits, Permit Responsibilities, and Permit Completion Certifications by replacing beneficial occupancy with contract completion date Updated Submission of Final DD Form 1354 section by replacing beneficial occupancy with contract completion date Added Redzone meeting requirements Added Miscellaneous Equipment Requirements
01 32 01.00 06 Updated table to replace spec section 00 80 00 with 01 00 00 for Redzone meeting
01 33 00.00 06 Updated 1.5 Electronic File Format requirements
01 35 26.00 06 Updated Safety requirements for ASSE/SAFE to the 2016 Fall Protection Code under References Updated SSHO experience requirements Updated Hot Work Permit requirements Revised Weight Handling Equipment requirements (rigging)
01 45 04.10 06 Revised Subcontractor CQC Orientation requirements Updated CQC System Manager experience requirements Revised Registered Roof Observer requirements
01 46 00.00 06 Revised systems to be commissions section, removed cooing towers and air compressors Added spec section reference to Sequencing paragraph Deleted Maintenance and Service Life Plan paragraph Removed requirements for water-cooled chillers, condenser water pumps, and cooling towers Deleted Cooling Tower Piping from piping system checklist Modified Functional Performance Test Checklist – Centrifugal Chillers paragraph Deleted Functional Performance Test Checklist – Cooling Tower paragraph requirements Removed air compressors from Section 1.3 Added reference to 23 09 00 to Section 1.6.1 Deleted Section 3.1.9
01 50 00 Updated Temporary Utilities section indicating reasonable amounts of water and electrical to be provided to contractor without charge Deleted 3.5.7.b Trailers or Storage Buildings
01 78 23 Revised Training paragraph to replace beneficial occupancy with contract completion date
03 35 00.00 10 Removed reference to Dry Shake Finish
03 53 14.00 20 Deleted Section 03 53 14.00 20 LIGHT REFLECTIVE NON-FERROUS METALLIC AGGREGATE
FLOOR SYSTEM
05 40 00 Revised to include additional drawing requirements Revised requirements for cold-formed steel wall girts
05 50 13 Revised to remove floor gratings and roof hatches
11 01 50 Revised to have two total users at fuselage Revised to remove remote power tagline
11 50 10 Removed from project
22 00 00 Clarified Water Cooler requirements Added Wall Hung Lavatories (LAV-2) Added lavatory thermostatic mixing valves, Section 2.4.6 Clarified drain strainers in Section 2.5.
Clarified DDC control on water heater.
Deleted Sections 2.11.1, 2.11.2, 2.11.3, 2.11.5, 2.11.7, 2.11.8 & 2.11.9 Deleted Section 2.12.7.3, 2.12.7.4, 2.12.7.5, 2.12.7.6, 2.12.7.7, 2.12.7.8 & 2.12.9 Added Equipment Tags Requirement to Section 3.6 Removed smoke test from section 3.9 Removed roof drain from Section 3.9.5 Removed air compressors from Section 3.9.5 Clarified pipe usages in Table I
22 60 75 Removed from project
23 00 00 Clarified requirements of section 1.2.2 Clarified requirements of Section 2.10.1.3 Clarified requirements of Section 2.10.4 Removed condenser water piping from Section 2.19 Clarified requirements of Section 3.1 Added requirement for Outside Air and Exterior ductwork to section 3.3.5 Clarified requirements of Section 3.11
Clarified requirements of Section 3.14
23 09 13 Removed condenser water piping from Section 1.2 Removed condenser water requirements and conductivity sensor from Section 2.6 Clarified requirements of Section 3.6.4
23 11 25 Clarified requirements of Section 2.2.1 Removed requirements for PE piping valve supports from Section 2.3
23 21 23 Clarified requirements of Section 2.2.5
23 35 19.00 20 Removed Section 2.1.5 Removed Section 2.3 Removed Section 2.4 Removed Section 2.5 Removed Section 2.6.5 Removed Section 3.1.3 Removed Section 3.1.4 Removed Section 3.1.7
23 64 10 Removed water-cooled chillers and references of cooling towers from specification Removed factory testing requirement Removed screw compressors and water-cooled condenser coils from Section 2.4.1 Removed variable speed requirements from Section 2.3 Removed lead/lag control and condenser water points for Section 2.5.4 Revised unloading requirements and removed Rotary Screw Compressors from Section 2.5.5 Removed variable speed drive requirements from Section 2.5.6 Removed Section 2.5.7 Removed brazed plate heat exchanger from Section 2.5.8 Removed Section 2.5.10 Revised corrosion protection requirements of Section 2.7 Removed Section 2.8 Removed condenser water piping, refrigerant piping and cooling towers from Section 2.9 Removed Section 3.1.8 Removed Section 3.2 Clarified requirements of Section 3.4
23 64 26 Removed condenser water piping from specification Removed condenser water treatment and testing requirements from specification.
Clarified requirements of Section 2.2.1 Clarified requirements of Section 2.5.6 Clarified requirements of Section 2.10.3 Removed Section 2.5.10 Removed Section 2.10.5 Removed Section 3.5.3 Removed Section 3.7
23 82 02.00 10
Clarified requirements of Section 1.6.
Removed cooling towers from Section 3.2.1 Removed reference to Specification 23 23 00 in Section 3.6 Revised number of test reports required in Section 3.6 Removed Section 3.7
23 65 00 Removed from project
26 35 43 Deleted Section 26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTOR
26 51 00 Paragraph 1.6.1 b was modified to read “Warranty period must begin on date of substantial completion. Contractor shall provide the Contracting Officer signed warranty certificates prior to final payment”
26 56 00 Paragraph 1.7.1 b was modified to read “Warranty period must begin on date of substantial completion. Contractor shall provide the Contracting Officer signed warranty certificates prior to final payment”
32 92 19 Removed Broadcast and Drop Seeding from Section 3.2.2
33 61 13.13 Removed condenser water piping from specification Removed Section 3.3.2 Removed Section 3.5.1 Removed requirement for hard copies of maintenance manuals.
41 22 13.15 Deleted Section 41 22 13.15 BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING
- END OF ‘SUMMARY OF CHANGES’ -
PRICE BREAKOUT SCHEDULE
Project: HC-130J General Maintenance Hangar (PN SXHT203000 – P2 472236)
Location: Patrick Air Force Base, Florida
Proposer's Name:
Item No.
Description Quantity
Unit Unit Price
Amount
BASE PROPOSAL
0001 Primary Facility – HC-130J Hangar
1 Job N/A $
0002 Sitework 1 Job N/A $
TOTAL BASE PROPOSAL $
OPTIONS
0003 Option A – Welding Room 140 1 Job N/A $
0004 Option B – Administration Shop Area (NE Corner)
1 Job N/A $
Option C – Paint Booth Enclosure #102
Option D - Bird Netting
Option E – Furniture and Fixtures
Job
Job
Job
N/A
N/A
N/A
TOTAL OPTIONS $
TOTAL BASE PROPOSAL AND ALL OPTIONS $
Description of Base Proposal Items
a) Item No. 0001 "Primary Facility – HC-130J Hangar" includes all Base Proposal work required within a line five feet outside of the new HC-130J Hangar.
b) Item No. 0002 "Sitework" includes all Base Proposal work required for demolition, site clearing, grading and drainage, utilities, paving, landscaping, permits, and other construction work required beyond a line five feet outside of the new HC-130J Hangar.
Description of Option Items
a) Item No. 0003 “Option A – Welding Room 140” includes all additional work required for the enclosed conditioned space to be fully completed and turned over to the Government. This shall include foundations, utilities, walls, roof, doors, finishes, HVAC, plumbing, lighting, power, telecommunications, etc. required for the space to be a complete and usable facility for Government. This work includes but is not limited to the following drawings and specifications:
Drawing: A-100, A-104, A-120, A-124, A-130, A-203, A-204, A-602, A-701, A-710, A-714, A-751, I- 114, S-107, S-117, S-121, S-137, S-226, CS111, EG101, EG102, EG401, EG402, EL104, EL402,EL602, EP104, EP403, P-110, P-905, M-104, M-109, M-301, M-505, M-506, M-601, M-602, M-603, M-610, M-
719, T-104, T-401, T-403, FA102, FX101, FX501
Specifications: 23 35 19.00 20
***The Contracting Officer may exercise this option by written notice to the Contractor within 120 calendar days from Notice-to-Proceed (NTP).
b) Item No. 0004 “Option B – Administration Shop Area (NE Corner)” includes all additional work required for the enclosed conditioned space to be fully completed and turned over to the Government. This shall include foundations, utilities, walls, roof, doors, finishes, HVAC, plumbing, lighting, power, telecommunications, etc. required for the space to be a complete and usable facility for Government. This work includes but is not limited to the following drawings and specifications:
Drawing: A-100, A-102. A-120, A-122, A-130, A-202, A-203, A-205, A-403, A-602, A-701, A-710, A- 712, A-751, I-100, I-112,EG101, EG102 EG401, EG402, EL102, EL401, EL602, EP102, EP401, EP601, EP605, EP606, FA102, FX501, M-002, M-105, M-403, M-506, M-601, M-602, M-603, M-610, M-702, M- 721, M-722, M-723, P-102, P-105, P-111, P-601, P-902, P-903, T-401, T0402, S-105, S-115, S-120, S-135, S-225, CS111, FA102, FX101, FX501
Specifications: 22 00 00, 23 00 00
***The Contracting Officer may exercise this option by written notice to the Contractor within 120 calendar days from Notice-to-Proceed (NTP).
g) Item No. 0005 “Option C – Paint Booth Enclosure #102 ” includes all additional work required for the enclosed conditioned space to be fully completed and turned over to the Government. This shall include foundations, utilities, walls, roof, doors, finishes, HVAC, plumbing, lighting, power, telecommunications, etc. required for the space to be a complete and usable facility for Government. This work includes but is not limited to the following drawings and specifications:
Drawing: A-100, A-103. A-120, A-123, A-130, A-201, A-203, A-206, A-303, A-602, A-701, A-710, A- 713, A-751, I-100, I-113,.E-100, EG101, EG102, EG401, EG402, EL103, EL402, EL602, EP103, EP403, EP601, EP603, EP602, EP605, EP606, FA101, FX501, M-108, M-302, M-404, M-601, M-602, M-603, M- 610, P-101, P-103, P-403, P-901, T-401, T-42, S-106, S-116, S-136, FA101, FX101, FX501
***The Contracting Officer may exercise this option by written notice to the Contractor within 120 calendar days from Notice-to-Proceed (NTP).
b) Item No. 0006 “Option D – Bird Netting)” includes all additional work required for the complete installation of bird netting. This work includes but is not limited to the following drawings and specifications:
Drawing: A-120, A-121, A-122, A-123, A-124, A-301, A-302, A-303, A-321, A-322, A-324, A-611, Specifications: 10 81 13
***The Contracting Officer may exercise this option by written notice to the Contractor within 120 calendar days from Notice-to-Proceed (NTP).
h) Item No. 0007 “Option E – Furniture and Fixtures)” shall constitute full compensation for the work associated with the procurement and installation of the Furniture, Fixtures, & Equipment (FF&E) Package, in accordance with requirements of the solicitation documents and criteria drawings.
***The Contracting Officer may exercise this option by written notice to the Contractor within 570 calendar days from Notice-to-Proceed (NTP).
- END OF PRICE BREAKOUT SCHEDULE -
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 ADDITIONAL SPECIAL CONTRACT REQUIREMENTS
01 32 01.00 06 PROJECT SCHEDULE
01 33 00.00 06 SUBMITTAL PROCEDURES
01 33 29.00 06 SUSTAINABILITY REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING (CONTRACTOR CxA)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
03 53 14.00 20 LIGHT REFLECTIVE NON-FERROUS METALLIC AGGREGATE FLOOR
SYSTEM
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
PROJECT TABLE OF CONTENTS Page 1
VOLUME I
**AM02**
**AM02**
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 42 13 METAL WALL PANELS
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 34 16.10 STEEL SLIDING HANGAR DOORS
08 34 19.10 20 ROLLING SERVICE AND FIRE DOORS
08 51 13 ALUMINUM WINDOWS
08 60 45 TRANSLUCENT PANELS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM
09 90 00 PAINTS AND COATINGS
09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL PROTECTION
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
10 81 13 BIRD CONTROL DEVICES
DIVISION 11 - EQUIPMENT
11 01 50 RIGID RAIL FALL PROTECTION SYSTEMS
11 50 10 PAINT SPRAY BOOTHS
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
PROJECT TABLE OF CONTENTS Page 2
VOLUME II
**AM02** **AM02**
**AM02** **AM02**____________________________________
**AM02** **AM02**_________________________________________________________________
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION
12 59 00 SYSTEMS FURNITURE
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 13 25.00 10 HIGH EXPANSION FOAM (HI EX. HEF) FIRE PROTECTION SYSTEM
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 60 75 CENTRAL VACUUM DUST COLLECTION SYSTEM
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 35 19.00 20 INDUSTRIAL VENTILATION AND EXHAUST
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED WATER PIPING SYSTEMS
23 65 00 COOLING TOWERS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS
26 13 00 SF6 PAD-MOUNTED SWITCHGEAR
26 13 01 PAD-MOUNTED DEAD-FRONT AIR INSULATED SWITCHGEAR
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
PROJECT TABLE OF CONTENTS Page 3
VOLUME III
**AM02** **AM02**_______________________________________________________
**AM02** **AM02**________________________________
**AM02** **AM02**________________________________________________________________
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE BASE COURSES
32 11 23.23 BASE COURSE DRAINAGE LAYERS
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 ASPHALT PAVING FOR AIRFIELDS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 17 23 PAVEMENT MARKINGS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 61 13.13 PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.15 BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING
41 22 23.19 MONORAIL HOISTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
**AM02** **AM02**_________________________________________________________________
SECTION 01 00 00
ADDITIONAL SPECIAL CONTRACT REQUIREMENTS
PATRICK AFB
Per UAI 5122.1302-100: Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and Subcontractors at all tiers are encouraged to promote the training and employment of U.S.