W912P520R0004 Price Schedule.xlsx
XLSX spreadsheet 76 KB Posted
- Attached to
- Kentucky Lock-Downstream Lock Monolith Construction Federal contract opportunity
- Solicitation number
- W912P520R0004
About this file
This document contains a price schedule and options for construction of downstream lock monoliths for the Kentucky Lock project. The price schedule lists estimated quantities, units, unit prices, and estimated amounts for over 100 line items across multiple divisions of work. The line items cover general requirements, existing conditions assessment, concrete work, metals, instrumentation, embedded utilities, earthwork, backfill, geotextiles, storm drainage, roadway work, and marine construction. The document also provides seven options for additional work on various monoliths, with each option containing its own set of line items and estimated pricing. This appears to be the complete pricing submittal for the referenced federal construction project.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 | ||||||
| Base Price Schedule | ||||||
| C1A, C1B, C4B, C4C | ||||||
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-00 | Mobilization and Demobilization - Batch Plant | 01 22 00 | 1 | Job | $ | $ |
| 0102-00 | Mobilization and Demobilization - Conveyor | 01 22 00 | 1 | Job | $ | $ |
| 0103-00 | Mobilization and Demobilization - QA Testing Lab and Core Storage Bldg. | 01 22 00 | 1 | Job | $ | $ |
| 0104-00 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0105-00 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0106-00 | Maintenance and Protection of Traffic | 01 50 00 | 1 | Job | $ | $ |
| 0107-00 | Maintain Testing Lab and COE Field Offices | 01 50 00 | 60 | MO | $ | $ |
| 0108-00 | Diversion and Care of Water | 01 57 24 | 60 | MO | $ | $ |
| 0109-00 | Data Management | 01 31 00 | 60 | MO | $ | $ |
| 0110-00 | LiDAR and Orthoimagery - Monolith Foundations | 01 32 23 | 50 | EA | $ | $ |
| 0111-00 | LiDAR and Orthoimagery - Lock Chamber | 01 32 23 | 1 | Job | $ | $ |
| 0112-00 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 02 | Div 02; Existing Conditions | |||||
| 0201-00 | Core Drilling in Rock (HQ) | 02 32 00 | 1,805.0 | LF | $ | $ |
| 0202-00 | Drilling in Soil | 02 32 00 | 142.0 | LF | $ | $ |
| 0203-00 | Optical Televiewer Logging | 02 32 00 | 625.0 | LF | $ | $ |
| 0204-00 | Soil Index Testing | 02 32 00 | 24.0 | EA | $ | $ |
| 0205-00 | Unconfined Compression Test | 02 32 00 | 6.0 | EA | $ | $ |
| 0206-00 | CU Triaxial Test | 02 32 00 | 3.0 | EA | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-00 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-00 | 2" LDPE Foam Expansion Joint | 03 15 14 | 80,200.0 | SF | $ | $ |
| 0303-00 | Reinforcing Steel - Material | 03 20 02 | 2,211.7 | TON | $ | $ |
| 0304-00 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 2,211.7 | TON | $ | $ |
| 0305-00 | Cement, Type II, MH - Low Alkali | 03 30 01 | 18,020.0 | TON | $ | $ |
| 0306-00 | Class F Fly Ash | 03 30 01 | 13,560.0 | TON | $ | $ |
| 0307-00 | Structural Concrete (4ksi) | 03 70 00 | 35,730.0 | CY | $ | $ |
| 0308-00 | Mass Concrete (3ksi) | 03 70 00 | 94,500.0 | CY | $ | $ |
| 0309-00 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 670.0 | CY | $ | $ |
| 0310-00 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 100.0 | CY | $ | $ |
| 0311-00 | Mud Mat Concrete (4ksi) | 03 70 01 | 3,000.0 | CY | $ | $ |
| 05 | Div 05; Metals | |||||
| 0501-00 | Miscellaneous Metal (10" Discharge Ports) | 05 50 15 | 1 | Job | $ | $ |
| 0502-00 | Wall Armor | 05 50 15 | 1 | Job | $ | $ |
| 0503-00 | Culvert Liners | 05 50 15 | 1 | Job | $ | $ |
| 0504-00 | Miscellaneous Metal (Check Post, Ladder, Line Hook) | 05 50 15 | 1 | Job | $ | $ |
| 13 | Div 13; Special Construction | |||||
| 1301-00 | Instrumentation Program | 13 50 00 | 60 | MO | $ | $ |
| 22 | Div 22; Plumbing | |||||
| 2201-00 | Embedded Piping | 22 00 02 | 1 | Job | $ | $ |
| 26 | Div 26; Electrical | |||||
| 2601-00 | Embedded Electrical Conduits | 26 20 01 | 1 | Job | $ | $ |
| 2602-00 | Grounding and Bonding for Electrical System | 26 05 26 | 1 | Job | $ | $ |
| 2603-00 | Cathodic Protection | 26 42 14 | 1 | Job | $ | $ |
| 31 | Div 31; Earthwork | |||||
| EXCAVATION | ||||||
| 3101-00 | Dental Excavation | 31 23 05 | CY | $ | $ | |
| 3102-00 | Dental Concrete | 31 23 05 | CY | $ | $ | |
| 3103-00 | Rock Excavation | 31 23 05 | 37,400.0 | CY | $ | $ |
| 3104-00 | Pre-Splitting | 31 23 06 | 3,270.0 | SY | $ | $ |
| 3105-00 | Line Drilling (6" spacing) | 31 23 06 | 2,630.0 | SY | $ | $ |
| 3106-00 | Preliminary Clean-Ups | 31 60 00 | 43,000.0 | SY | $ | $ |
| 3107-00 | 60 Inch Drilled Shaft | 31 63 23 | 966 | LF | $ | $ |
| 35 | Div 35; Waterway & Marine Const | |||||
| 3501-00 | Fabricate Miter Gates Embedded Metals | 35 20 16.33 | 1 | Job | $ | $ |
| 3502-00 | Fabricate Miter Gates | 35 20 16.33 | 1 | Job | $ | $ |
| 3503-00 | Caisson Embedded Metals and Fillers (US) | 1 | Job | $ | $ | |
| 3504-00 | Culvert Bulkhead Slot Embedded Metals (US) | 1 | Job | $ | $ | |
| 3505-00 | Trunnion Anchors and Embedded Metals | 1 | Job | $ | $ | |
| 3506-00 | Floating Mooring Bitt Tracks and Embedded Metals | 35 59 29 | 1 | Job | $ | $ |
| 3507-00 | Caisson Embedded Metals and Fillers (DS) | 1 | Job | $ | $ | |
| 3508-00 | Culvert Bulkhead Slot Embedded Metals (DS) | 1 | Job | $ | $ |
BASE ESTIMATED AMOUNT $
Page &P of &N
Option 1
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 1 Price Schedule |
| C2A |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-01 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-01 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-01 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-01 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-01 | 2" LDPE Foam Expansion Joint | 03 15 14 | 14,950.0 | SF | $ | $ |
| 0303-01 | Reinforcing Steel - Material | 03 20 02 | 214.6 | TON | $ | $ |
| 0304-01 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 214.6 | TON | $ | $ |
| 0305-01 | Cement, Type II, MH - Low Alkali | 03 30 01 | 3,326.0 | TON | $ | $ |
| 0306-01 | Class F Fly Ash | 03 30 01 | 2,503.0 | TON | $ | $ |
| 0307-01 | Structural Concrete (4ksi) | 03 70 00 | 3,979.0 | CY | $ | $ |
| 0308-01 | Mass Concrete (3ksi) | 03 70 00 | 19,470.0 | CY | $ | $ |
| 0309-01 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 636.0 | CY | $ | $ |
| 0310-01 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 100.0 | CY | $ | $ |
OPTION 1 ESTIMATED AMOUNT $
Option 2
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 2 Price Schedule |
| C5B |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-02 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-02 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-02 | Data Management | 01 31 00 | MO | $ | $ | |
| 0074-02 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-02 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-02 | 2" LDPE Foam Expansion Joint | 03 15 14 | 9,680.0 | SF | $ | $ |
| 0303-02 | Reinforcing Steel - Material | 03 20 02 | 297.7 | TON | $ | $ |
| 0304-02 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 297.7 | TON | $ | $ |
| 0305-02 | Cement, Type II, MH - Low Alkali | 03 30 01 | 2,760.0 | TON | $ | $ |
| 0306-02 | Class F Fly Ash | 03 30 01 | 2,077.0 | TON | $ | $ |
| 0307-02 | Structural Concrete (4ksi) | 03 70 00 | 3,660.0 | CY | $ | $ |
| 0308-02 | Mass Concrete (3ksi) | 03 70 00 | 16,290.0 | CY | $ | $ |
| 0309-02 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 70.0 | CY | $ | $ |
| 0310-02 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 50.0 | CY | $ | $ |
OPTION 2 ESTIMATED AMOUNT $
Option 3
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 3 Price Schedule |
| C3A |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-03 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-03 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-03 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-03 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-03 | 2" LDPE Foam Expansion Joint | 03 15 14 | 17,995.0 | SF | $ | $ |
| 0303-03 | Reinforcing Steel - Material | 03 20 02 | 802.3 | TON | $ | $ |
| 0304-03 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 802.3 | TON | $ | $ |
| 0305-03 | Cement, Type II, MH - Low Alkali | 03 30 01 | 3,755.0 | TON | $ | $ |
| 0306-03 | Class F Fly Ash | 03 30 01 | 2,826.0 | TON | $ | $ |
| 0307-03 | Structural Concrete (4ksi) | 03 70 00 | 7,846.0 | CY | $ | $ |
| 0308-03 | Mass Concrete (3ksi) | 03 70 00 | 18,582.0 | CY | $ | $ |
| 0309-03 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 77.0 | CY | $ | $ |
| 0310-03 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 100.0 | CY | $ | $ |
| 35 | Div 35; Waterway & Marine Const | |||||
| 3509-03 | Install Miter Gates Embedded Metals | 35 20 17 | 1 | Job | $ | $ |
| 3510-03 | Install Miter Gates | 35 20 16.33 | 1 | Job | $ | $ |
OPTION 3 ESTIMATED AMOUNT $
Option 4
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 4 Price Schedule |
| C1C, C2B, C2C, C3C |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-04 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-04 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-04 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-04 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-04 | 2" LDPE Foam Expansion Joint | 03 15 14 | 45,975.0 | SF | $ | $ |
| 0303-04 | Reinforcing Steel - Material | 03 20 02 | 1,179.8 | TON | $ | $ |
| 0304-04 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 1,179.8 | TON | $ | $ |
| 0305-04 | Cement, Type II, MH - Low Alkali | 03 30 01 | 11,003.0 | TON | $ | $ |
| 0306-04 | Class F Fly Ash | 03 30 01 | 8,281.0 | TON | $ | $ |
| 0307-04 | Structural Concrete (4ksi) | 03 70 00 | 9,252.0 | CY | $ | $ |
| 0308-04 | Mass Concrete (3ksi) | 03 70 00 | 70,178.0 | CY | $ | $ |
| 0309-04 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 458.0 | CY | $ | $ |
| 0310-04 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 100.0 | CY | $ | $ |
OPTION 4 ESTIMATED AMOUNT $
Option 5
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 5 Price Schedule |
| C5C, C6A, C6B |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-05 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-05 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-05 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-05 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-05 | 2" LDPE Foam Expansion Joint | 03 15 14 | 41,497.0 | SF | $ | $ |
| 0303-05 | Reinforcing Steel - Material | 03 20 02 | 1,297.9 | TON | $ | $ |
| 0304-05 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 1,297.7 | TON | $ | $ |
| 0305-05 | Cement, Type II, MH - Low Alkali | 03 30 01 | 9,924.0 | TON | $ | $ |
| 0306-05 | Class F Fly Ash | 03 30 01 | 7,469.0 | TON | $ | $ |
| 0307-05 | Structural Concrete (4ksi) | 03 70 00 | 11,556.0 | CY | $ | $ |
| 0308-05 | Mass Concrete (3ksi) | 03 70 00 | 60,052.0 | CY | $ | $ |
| 0309-05 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 429.0 | CY | $ | $ |
| 0310-05 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 100.0 | CY | $ | $ |
OPTION 5 ESTIMATED AMOUNT $
Option 6
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 6 Price Schedule |
| Grouting perimeter of lock chamber (GR) |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0101-06 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0102-06 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0103-06 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 31 | Div 31; Earthwork | |||||
| GROUTING | ||||||
| 3133 | Drill Grout Holes in Rock | |||||
| 3133A-06 | First 20,933 Linear Feet | 31 32 23 | 20,933 | LF | $ | $ |
| 3133B-06 | Over 20,933 Linear Feet | 31 32 23 | 2,326 | LF | $ | $ |
| 3135-06 | Pressure Washing (Hydraulic) | 31 32 23 | 212.0 | HR | $ | $ |
| 3136-06 | Pressure Testing (Hydraulic) | 31 32 23 | 2,620 | EA | $ | $ |
| 3137-06 | Portland Cement in Grout | 31 32 23 | 21,354 | CF | $ | $ |
| 3138-06 | Grouting Connections | 31 32 23 | 2,620 | EA | $ | $ |
| 3139 | Placing Grout | |||||
| 3139A-06 | First 348,100 Gallons | 32 32 23 | 348,100 | GAL | $ | $ |
| 3139B-06 | Over 348,100 Gallons | 33 32 23 | 38,678.0 | GAL | $ | $ |
| 3140-06 | Government Requested Standby - Grouting | 31 32 23 | 70.0 | HR | $ | $ |
| 3142-06 | Re-Drill Grout Holes in Rock | 31 32 23 | 2,620.0 | LF | $ | $ |
| BACKFILL | ||||||
| 3101-06 | Lock Soil Backfill - Tuscaloosa Material | 31 00 00 | 217,000 | CY | $ | $ |
| 3102-06 | Lock Rock Backfill - 8-inch Minus Material | 31 00 00 | 115,000 | CY | $ | $ |
| Div 31; Geotextiles for Earthwork | ||||||
| 3103-06 | Nonwoven Geotextile Fabric | 31 05 19.13 | 2,000 | SF | $ | $ |
| 33 | Div 33; Storm Drainage Utilities | |||||
| CORRUGATED METAL PIPE | ||||||
| 3301-06 | 12-inch Perforated Corrugated Metal Pipe | 33 40 00 | 1,600 | LF | $ | $ |
OPTION 6 ESTIMATED AMOUNT $
Option 7
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Option 7 Price Schedule |
| C3B |
| PRICE ITEM | DESCRIPTION | SPEC # | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| 01 | Div 01; General Requirements | |||||
| 0104-07 | Mobilization and Demobilization - General | 01 22 00 | 1 | Job | $ | $ |
| 0105-07 | Premiums for Performance and Payment Bonds | 01 22 00 | 1 | Job | $ | $ |
| 0112-07 | Advanced Modeling Package (BIM) | 01 78 00 | 1 | Job | $ | $ |
| 02 | Div 02; Existing Conditions | |||||
| 0209-07 | Core Drilling in Rock (PQ) | 02 32 00 | 126.0 | LF | $ | $ |
| 0210-07 | Drilling in Soil | 02 32 00 | 161.0 | LF | $ | $ |
| 0211-07 | Optical Televiewer Logging | 02 32 00 | 126 | LF | $ | $ |
| 0212-07 | Piezometer Installed | 02 32 00 | 287 | LF | $ | $ |
| 03 | Div 03; Concrete | |||||
| 0301-07 | Waterstop | 03 15 14 | 1 | Job | $ | $ |
| 0302-07 | 2" LDPE Foam Expansion Joint | 03 15 14 | 8,484 | SF | $ | $ |
| 0303-07 | Reinforcing Steel - Material | 03 20 02 | 355 | TON | $ | $ |
| 0304-07 | Place Rebar for Monolith, Structural, Mass, Second Stage and Miscellaneous Concrete | 03 20 02 | 354.6 | TON | $ | $ |
| 0305-07 | Cement, Type II, MH - Low Alkali | 03 30 01 | 2,036 | TON | $ | $ |
| 0306-07 | Class F Fly Ash | 03 30 01 | 1,532.0 | TON | $ | $ |
| 0307-07 | Structural Concrete (4ksi) | 03 70 00 | 4,310.0 | CY | $ | $ |
| 0308-07 | Mass Concrete (3ksi) | 03 70 00 | 10,124.0 | CY | $ | $ |
| 0309-07 | Second Stage and Miscellaneous Concrete (4ksi) | 03 80 00 | 290.0 | CY | $ | $ |
| 0310-07 | Congested Second Stage / Repair Concrete (4ksi) | 03 80 00 | 75 | CY | $ | $ |
| 22 | Div 22; Plumbing | |||||
| 2201-07 | Embedded Piping | 22 00 02 | 1.0 | Job | $ | $ |
| 31 | Div 31; Earthwork | |||||
| BACKFILL | ||||||
| 3101-07 | Lock Soil Backfill - Tuscaloosa Material | 31 00 00 | 217000 | CY | $ | $ |
| 3102-07 | Lock Rock Backfill - 8-inch Minus Material | 31 00 00 | 115,000 | CY | $ | $ |
| Div 31; Geotextiles for Earthwork | ||||||
| 3103-07 | Nonwoven Geotextile Fabric | 31 05 19.13 | 2,000.0 | SF | $ | $ |
| 32 | Div 32; Exterior Improvements | |||||
| 3201-07 | 18" Class IV RCP | 124 | LF | $ | $ | |
| 3202-07 | 24" Class IV RCP | 322 | LF | $ | $ | |
| 3203-07 | 30" Class IV RCP | 448 | LF | $ | $ | |
| 3204-07 | 36" Class IV RCP | 117 | LF | $ | $ | |
| 3205-07 | 18" HDPE | 42 | LF | $ | $ | |
| 3206-07 | 24" HDPE | 127 | LF | $ | $ | |
| 3207-07 | 36" HDPE | 520 | LF | $ | $ | |
| 3208-07 | Drop Box Inlet (Type 1) | 1 | EA | $ | $ | |
| 3209-07 | Drop Box Inlet (Type 2) | 2 | EA | $ | $ | |
| 3210-07 | Manhole (Type A) | 1 | EA | $ | $ | |
| 3211-07 | Manhole (Type B) | 3 | EA | $ | $ | |
| 3212-07 | Sloped & Flared Box In/Out 18" | 6 | EA | $ | $ | |
| 3213-07 | Sloped & Flared Box In/Out 24" | 2 | EA | $ | $ | |
| 3214-07 | Sloped & Flared Box In/Out 36" | 1 | EA | $ | $ | |
| 3215-07 | KYTC Class II Channel Lining (18-36" drainage pipe) | 55 | TON | $ | $ | |
| ROADWAY | ||||||
| 3218-07 | Crushed Stone Base | 2475 | TON | $ | $ | |
| 3219-07 | Clearing, Grubbing, and Site Demolition | 1 | Job | $ | $ | |
| 3222-07 | Asphalt Sawcut | 33 | LF | $ | $ | |
| 3223-07 | Seeding and Mulching | 63929 | SY | $ | $ | |
| 33 | Div 33; Storm Drainage Utilities | |||||
| CORRUGATED METAL PIPE | ||||||
| 3301-07 | 12-inch Perforated Corrugated Metal Pipe | 33 40 00 | 1600 | LF | $ | $ |
OPTION 7 ESTIMATED AMOUNT $
Summary
| Kentucky Lock Addition, Downstream Lock Monoliths, W912P5-20-R-0004 |
| Price Schedule Summary |
| PRICE ITEM | DESCRIPTION | SPECIFICATION NUMBER | EST. QTY. | UNIT | UNIT | |
| PRICE | ESTIMATED |
AMOUNT
| BASE ESTIMATED AMOUNT | $ |
| OPTION 1 ESTIMATED AMOUNT | $ |
| OPTION 2 ESTIMATED AMOUNT | $ |
| OPTION 3 ESTIMATED AMOUNT | $ |
| OPTION 4 ESTIMATED AMOUNT | $ |
| OPTION 5 ESTIMATED AMOUNT | $ |
| OPTION 6 ESTIMATED AMOUNT | $ |
| OPTION 7 ESTIMATED AMOUNT | $ |
TOTAL ESTIMATED AMOUNT (BASE+ALL OPTIONS) $