MEMORANDUM FOR FILE
FROM: 158 MSG/MSC
SUBJECT: Questions and Answers for CURZ 152812, F-35 Alter Aircraft Shelter B385, Fuel
Cell as of 18 May 2018
1. Solicitation states, “FAR 52.216-1 TYPE OF CONTRACT (APR 1984) The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.” Is an electronic copy of the Fixed Price Contract available for review?
A. No, an electronic copy of the contract award is not available. The resultant contract is essentially the solicitation document after the removal of solicitation provisions. All other terms and conditions and clauses carry over from the solicitation to the contract.
2. Builder’s Risk: Neither FAR 52.228-5 or FAR 28.307-2 contemplate Builder’s Risk coverage for this project. Assuming the Government carries the Builder’s Risk Policy, what is the policy deductible, and is the Contractor required to insure down the policy deductible?
A. Please see FAR Clause 52.236-7 Permits and Responsibilities.
3. Specification Section 01 00 00 – Special Contract Requirements is listed in the Table of
Contents, but is not included - is this section available?
A. Section 01 00 00 is not labeled by mistake. It starts on .pdf page 11 of the specification document volume 1.
4. Solicitation No. W912LN-18-B-5001 Paragraph 11. SUBCONTRACTING PLAN calls for the offerors to prepare and submit their subcontracting plan “if required”. Please advise if the plan is required for this project.
A. Subcontracting Plan is only required of Large Business Bidders if requested by the
Contracting Officer. Subcontracting Plan is not required at the time of bid opening. If the apparent low bidder is a Large Business, the Contracting Officer will then request the Bidder submit a Subcontracting Plan by a specified date and time in accordance with Solicitation No.
W912LN-18-B-5001 Paragraph 11. The plan shall be included in and made a part of the resultant contract. Failure to submit the Subcontracting Plan shall make the Bidder ineligible for the award of the contract.