Q A from Synopsis posted July 8 2011

View the file

Other files

File Type Posted
QUESTIONS AND ANSWERS 08102011 Addendum.docx DOCX document
Addendum 2 080911.pdf PDF
Addendum 1 080911.pdf PDF
QUESTIONS AND ANSWERS 08092011 Addendum.docx DOCX document
QUESTIONS AND ANSWERS 08092011.docx DOCX document
QUESTIONS AND ANSWERS 08092011.docx DOCX document
Addendum__2.docx DOCX document
NCSRC Development Fees 080411.pdf PDF
QUESTIONS AND ANSWERS 08042011 REVISED 1600.docx DOCX document
Soils Report NCSRC.pdf PDF
LEED 2009 NCSRC Scorecard 080411.pdf PDF
QUESTIONS AND ANSWERS 08042011 REVISED.docx DOCX document
760092813_dsc_0253.jpg JPG image
QUESTIONS AND ANSWERS 07292011 REVISED.doc DOC document
QUESTIONS AND ANSWERS 07272011.doc DOC document
QUESTIONS AND ANSWERS 07262011 revised.doc DOC document
QUESTIONS AND ANSWERS 07262011.doc DOC document
Preproposal conference 072211 —
ATTENDANCE PRE-PROPOSAL CONF JULY 22 2011.pdf PDF
QUESTIONS AND ANSWERS 07222011.doc DOC document
W912LC-11-R-0006 MOD 0001.pdf PDF
Package 2 - Site.pdf PDF
SOLICITATION W912LC-11-R-0006.pdf PDF
080201 - Final Design - Specifications Vol 1.pdf PDF
Package 3 - Arch Int Kitchen.pdf PDF
Package 4 - Structural Mech Pumb Elec FP.pdf PDF
080201 - Final Design - Specifications Vol 2.pdf PDF
Exhibit C SSS NCOSPR Final.doc DOC document
Exhibit D and F NCOSPR Final.doc DOC document
Package 1 - General.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS RELATED TO: NORTH COLORADO SPRINGS READINESS CENTER-SYNOPSIS

SOLICITATION: W912LC-11-R-0006

Make Sure You Have the Latest Version of this Web Page “Refresh” or “Reload” Dated: July 8, 2011

1. Q. Is the new Readiness Center at Buckley AFB a design/build project? If yes, when will bridging documents be available? If not, when will contract documents be available?

A. This is not a design build requirement. Drawings and specifications will be posted with the solicitation on fbo.gov as stated in the synopsis.

2. Do you have an estimated date of release?

A. The Solicitation will be posted on fbo.gov as stated in the synopsis.

3. We may be interested in bidding on the solar PV portion of the work at the North Colorado Springs Readiness Center. Would you please let me know the estimated size in DC kW that the solar PV amount to? Thank you very much.

A. Please review Solicitation on fbo.gov when posted.