01_39_00_Request_for_Information.pdf

PDF 243 KB Posted

Attached to
Repair Maintenance Ramp Federal contract opportunity
Solicitation number
W912JV-19-B-7001
Issued by
Department of the Army Oregon Army National Guard

About this file

This document provides specifications for a Request for Information process on a construction project for repair and maintenance of a ramp at Kingsley Field Air National Guard Base. The contractor must submit RFIs in writing using the prescribed format and include references to applicable drawings or specifications as needed. RFIs will be submitted to the Contracting Officer's Representative and Architect-Engineer and responses will be provided within 7 days for urgent RFIs and 14 days for routine RFIs. Relatedly, solicitation number W912JV-19-B-7001 from the Department of the Army Oregon Army National Guard is for repair and maintenance of the ramp at Kingsley Field, though no further details are provided on required products or services.

Request for Information

View the file

Other files for this federal contract opportunity

Other files attached to Repair Maintenance Ramp, newest first.
File Type Posted
FINAL_RFI's_as_of_7_June_19.pdf PDF
Attachment_2-_Fuel_Tank.pdf PDF
Attachment_4_-_Exhibit_7460.PDF PDF
Attachment_3-_Fuel_Tank_Trench.pdf PDF
FINAL_RFI's_as_of_7_June_19.pdf PDF
01_40_00_General_Projects_and_Quality.pdf PDF
01_72_00_Warranties.pdf PDF
01_78_23_O_and_M_Data.pdf PDF
RFI's_as_of_1_June_19.pdf PDF
01_78_00_Contract_Closeout.pdf PDF
01_33_00_Submittals.pdf PDF
01_14_00_Security_Requirements.pdf PDF
01_72_00_Record_Documents.pdf PDF
RFI's_as_of_30_May.pdf PDF
Revised_Specs.pdf PDF
RFI's.pdf PDF
W912JV19B7001.pdf PDF
Drawings.pdf PDF
Specifications.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 39 00 Page 1

ORANG Repair Maint. Ramp KJAQ162682

Kingsley Field ANGB Type B-2 Submittal

SECTION 01 39 00

PART 1 - GENERAL

1.1 REQUIREMENTS INCLUDED

REQUEST FOR INFORMATION

a. Provides procedures and guidelines for preparation, submittal and response to Contractor's Request for Information (RFI's) during construction of project.

1.2 RFI DEFINITION

a. The formal Request for Information (RFI) process is one tool to be utilized by the Contractor to request information from the Contracting

Officer regarding the Contract. It should be used only when the

Contractor:

(1) Discovers an unforeseen condition or constructability issue; or

(2) Has a question regarding information in the Contract Documents; or

(3) Requires information not found in the Contract Documents.

b. All attempts should be made by the Contractor to resolve issues without the generation of a formal RFI.

1.3 RFI PROCEDURE

a. RFI's shall be issued by the General Contractor in a written form and numbered sequentially RFI's shall be submitted by the General contractor in a written form using the government prescribed Request for Information format. The contractor shall submit the RFI electronically via e-mail attaching the RFI to the e-mail. Any attachments must be in a standard format compatible with Microsoft Office or .pdf format. Requests from subcontractors shall be made only through the General Contractor and shall be submitted to the Contracting Officer’s Representative and Architect-

Engineer with a copy furnished to the Contracting Officer. The subject line of the e-mail shall include the project name, the RFI number, and the

RFI subject.

b. Contractor shall completely and clearly indicate clarification item(s) required. References to applicable drawing sheets or specification sections shall be included where applicable or the RFI may be returned unanswered.

c. Contractor shall submit recommendation(s) of how to resolve the RFI.

d. Acknowledge whether proposal for work involves a required time or cost modification to the Contract.

e. Any delays and costs resulting from the improper preparation of RFI's will be the sole responsibility of the Contractor.

f. RFI Flow: Contractor shall submit RFI’s via email to the Contracting

Officer’s Representative and Architect-Engineer and his designated representatives as provided at the pre-construction conference. RFIs will be marked by the contractor as either “Urgent” or “Routine”. Every effort will be made to respond to urgent RFIs within 7 days and routine RFIs within 14 days, although complex RFIs may take longer to respond to. The

01 39 00 Page 2

ORANG Repair Maint. Ramp KJAQ162682

Kingsley Field ANGB Type B-2 Submittal contractor is responsible for projecting out his work sufficiently to ensure adequate time to resolve issues. Abuse of the “urgent” request based on the failure of the contractor to address foreseeable issues in a timely manner will not automatically be a justification for delays.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

-- END OF SECTION --