This document contains a log of requests for information (RFIs) related to a solicitation for the construction of a new National Guard Readiness Center in Michigan. Key details include:

  • The RFI log addresses questions received between January 9th and January 18th regarding specifications, drawings, and other requirements for the project. Responses clarify allowable roles for quality control and safety managers, provide additional drawing references, and commit to addressing questions in future amendments.

  • The readiness center project involves designing up to 46,831 square feet of new facility space to support training, administrative, and logistical needs. The design must meet industry standards and codes for facilities intended to serve a minimum 50-year life span. Site improvements and utility infrastructure are also within the project scope.

  • The bid opening date was extended to January 31st, 2030 at 12:30 PM Eastern time via an upcoming amendment in response to an RFI. Clarification was provided that the contract period of 90 days will also be updated in that amendment.

View the file

Other files

File Type Posted
Abstract Pg 1.pdf PDF
Abstract Pg 2.pdf PDF
w912JB24B00001 Updated.pdf PDF
w912JB24B00001 AMEND 5.pdf PDF
2024-01-31 MARNG RFI LOG (1).xlsx XLSX spreadsheet
W912JB24B0001 Amend 4.pdf PDF
Amendment 3.pdf PDF
W912JB24B0001 Amend 2.pdf PDF
2024-01-29 MARNG RFI LOG (1).xlsx XLSX spreadsheet
RFI Log as of 29.xlsx XLSX spreadsheet
W912JB24B0001 Amendment.pdf PDF
RFI LOG as of 23 Jan 24.xlsx XLSX spreadsheet
Geotech Report MI ARNG GAAF RC.pdf PDF
Pre-Bid Site Visit Sign-in sheet.pdf PDF
Readiness Center Pre-Bid Conference_Site Visit.pptx PPTX presentation
RFI Log.docx DOCX document
GAAF Vetting Access Roster.xlsx XLSX spreadsheet
W912JB24B0001 1229.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf__Part2.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf__Part4.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf__Part3.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf__Part1.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf__Part5.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3.pdf Part 2.pdf PDF
MI ARNG GAAF RC Volume 2 TYPE B 100 Drawings FULL_R3 Part 1.pdf PDF
MI ARNG GAFF RC Volume 3 TYPE B 100 Specifications_R1.pdf PDF
W912JB24B0001 Signed.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BIDDER RFI 2024

MIARNG Readiness Center - BIDDER RFI LOG 2024
#DATERFI DETAILPrimary DisciplineResponseResponse Date
0011/9/24The solicitation states that the price shall be good for 60 days, while the Site Visit slides state 90 days. Please clarify.
MIARNGThis is for 90 days. It will be updated in the ammendment1/12/24
0021/9/24Please advise what the time frame is for award of the option(s) and any resulting project schedule extensions if they are not all awarded at the same timeMIARNGThe bid opening will be extended via amendment to 31 Jan 1230pm est1/12/24
0031/9/24Spec 01 35 26 (para. 1.6.1.1.1) states that the SSHO may also serve as the QC Manager duties but may not serve as the Superintendent. However, Spec 01 45 00.00 10 (para. 3.4.2) states that the QC Manager is assigned as the CQC Manager but has duties as project superintendent in addition to quality control. In addition, Spec 01 00 00 (para. 1.38.1, Key Personnel Description, states: “An individual Key Team Member may not hold more than one key role.” This is followed by the minimum qualifications for Project Manager, Site Superintendent, Quality Control Manager, and Safety Manager. Please clarify the project requirements for the QC Manager, SSHO and Superintendent).MIARNGIt appears that the note in section 01 00 00 – “An individual Key Team Member may not hold more than one key role” contradicts language in spec 01 35 26.

Atkins understanding is that per 01 35 26 – The Quality Control Manager and Site Safety and Health Office can be the same person, but there needs to be a separate Project Superintendent.

Section 01 45 00.00 10 does not specifically mention “Quality Control Manager”, it states that the Contractor Quality Control manager also has superintendent duties. Meaning observation and inspection of site work, production of reports and is on site at all times during construction. Atkins understanding is that there is no difference between a Quality Control Manager and a Contractor Quality Control Manager.

Final response and decision to be confirmed by MIARNG.1/12/24
0041/9/24Drawing CS503 shows chain link fence details but no chain link fence is found on the drawings. Please advise.CIVILPlease refer to sheet OLI705 & OLI706. Optional line item drawings for the project are located at the back of the drawing set starting from OLI700 - OLI786.1/12/24
0051/9/24Please confirm that the project is tax exempt per Spec 01 00 00.MIARNGIn accordance with FAR 52.229-3 Federal, State and loca taxes, a clclause by reference in this solicitation. The contract price incldes all applicable federal ,
0061/9/24Please consider allowing submittal of the Bid via email. Typically, trades do not provide their bids until late in the process, making it difficult to copy, bind, and deliver the Bid documents.MIARNGThis is will not be an option
0071/10/24DMI Metals - I recently viewed the Readiness Center project in Grayling, MI and am interested in quoting the standing seam roof. Your name was listed as a contact, and I was wondering if Substitution Requests are acceptable.MIARNGPer FAR requirements, the specs do not name specific manufacturers or products. The specs include salient characteristics of products and materials. If a specific product meets the listed characteristics, then a it can be evaluated during the submittal process.
0081/12/24Should coatings on concrete be polyurea on the interior and bituminous coating on the exterior? These are preferred practices in many communities in Michigan due to constant expansion-contraction of concrete tanks susceptible to toxins including phosphates, sulfuric acids, cleaning agents, and petroleum products. Epoxy coatings have been defined as too hard-brittle to survive in extreme temperature conditions. Cracking can occur and lead to premature failures on concrete designs (see recommended Concrete GI Spec).PLUMBING
0091/12/24Are HDPE solutions acceptable as alternatives for the grease interceptor and oil separators? Fully welded designs using dual-wall construction are better for long-term structural durability, leak-free performance, and chemical resistance.PLUMBINGPer FAR requirements, the specs do not name specific manufacturers or products. The specs include salient characteristics of products and materials. If a specific product meets the listed characteristics, then a it can be evaluated during the submittal process.
0101/12/24Per S-201 and A-123 a prefabricated canopy on the south elevation is by others. If the Contractor installs framing with metal deck for this canopy, please provide detailsARCHITECTURE / STRUCTURE / PLUMBINGAtkins will provide revised drawings/specs in an addendum.1/12/24
0111/12/24Per details on A-451 all shower cabins are wall fiberglass commercial showers. No spec found neither in architectural nor plumbing sections. Please clarifySPECSAtkins will provide revised specs in an addendum. / Shower walls can match shower pan material1/15/24
0121/12/24What is the thickness of stone beneath slab-on-grade? Drawing S-111 refers to Geotechnical Report, but no Geotech Report included in RFPMIARNGGeotechnical report which is in the design report can be made available by MIARNG.1/15/24
0131/12/24Please provide Food Service drawings. Spec 1106 40.13, 1.2.3 classified responsibilities of all parties, but section 2.1.2Food Service Equipment Schedule does not show this classification. Please advise.SPECS