SELFRIDGE REPAIR NW SEWER
W912JB-19-B-5001
RFI’S
1. Can Govt. provide soil borings in the area where new sanitary line to be installed?
Please see the Specification Book developed for the project.
1.04 SITE CONDITIONS
Soil borings were made during the design of this project at locations identified on the Drawings. The logs of the borings and soil data for this project are provided to the CONTRACTOR. Interpretation of all data and reports for construction purposes is the responsibility of the CONTRACTOR.
Please see the ATTACHMENTS Section for soil boring information
2. In absence soil borings, what would contractor base their bid on regarding dewatering, excavation bracing, and other excavation related issues?
3. Materials Submittals AF66 file indicate we need to provide CCTV Inspection. Is this for the existing system? Please clarify what you need CCTV for?
Please see the Specification Book developed for the project.
ARTICLE 4 – TESTING AND ACCEPTANCE – Page S-7
The Contractor shall provide for Closed Circuit Television (CCTV) inspection, in accordance with
The General Requirements, of all sanitary sewers Constructed.
4. Are the exhumed/excavated spoils staying on the base (referring to any spoils which are
NOT placed back into the excavation)?
*Section 01 57 00*
5. Are we allowed to discharge groundwater and accumulated "trench" water into the storm and/or sanitary sewer?
NO, Please see the Specification Book developed for the project.
*Section 01 57 00*