About this file

Addendum 04 posted

View the file

Other files

File Type Posted
W912J6-12-R-0002_0004_BDE_RC.pdf PDF
W912J6-12-R-0002-0003_AMENDMENT 03_29TH_RC.pdf PDF
General_Decision_Number_.docx DOCX document
Running QUESTIONS AND ANSWERS.docx DOCX document
Running QUESTIONS AND ANSWERS.docx DOCX document
Running QUESTIONS AND ANSWERS.docx DOCX document
Addendum_003.pdf PDF
A-402 - ENLARGED FLOOR PLANS- RESTROOMS.pdf PDF
A-313-O - ENLARGED PARTIAL BUILDING SECTIONS- AUDITORIUM- OBI-1 CONDITION.pdf PDF
A-611 - DOOR SCHEDULE DOOR AND FRAME TYPES.pdf PDF
I-650 - INTERIOR ROOM FINISH SCHEDULE.pdf PDF
I-651 - INTERIOR FINISH LEGEND.pdf PDF
W912J6-12-R-0002-0002_ADDENDUM 02.pdf PDF
Addendum 002 02APR12.pdf PDF
Running QUESTIONS AND ANSWERS.docx DOCX document
Running QUESTIONS AND ANSWERS.docx DOCX document
Running QUESTIONS AND ANSWERS.docx DOCX document
W912J6-12-R-0002-0002_ADDENDUM 02.pdf PDF
W912J6-12-R-0002-0001_ADDENDUM 01.pdf PDF
Addendum 001 30MAR12.pdf PDF
Running QUESTIONS AND ANSWERS as of 5 April 2012.docx DOCX document
Addendum 002 02APR12.pdf PDF
PREPROP_SLIDES_29th_IBCT_Readines_Center 1 .pdf PDF
29th BDE Readiness Center Sign in Sheet.pdf PDF
PREPROP_SLIDES_29th_IBCT_Readines_Center.pptx PPTX presentation
Exhibit C New.docx DOCX document
Exhibit_C_RC.docx DOCX document
QUESTIONS AND ANSWERS.docx DOCX document
EXHIBIT_A_RC 1 .docx DOCX document
Exhibit_D_ _E_RC.docx DOCX document
Exhibit_B_RC.docx DOCX document
Exhibit I TEP Sample.docx DOCX document
EXHIBIT F for forward Pricing.docx DOCX document
W912J6-12-R-0002_BDE_RC_Phase 1.pdf PDF
Exhibit H TEP Calculation.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HIARNG Kalaeloa Readiness Center (RC) W90FY-Q-09-D-0006-9N02

Kalaeloa, Hawaii PN 150043

Addendum 004

19 April 2012 Page 1

ADDENDUM 004

19 April 2012

This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents, Amendment No. 1, Addendum 001, Addendum 002 and Addendum 003 as noted below. Acknowledge receipt of this Addendum in the space provided in the Bid Form. Failure to do so may subject Bidder to disqualification.

This Amendment consists of 2 pages including all attachments noted herein.

MODIFICATIONS TO DRAWINGS:

1) Sheet C-103 – SITE PLAN – SECTOR TWO

a. Add the following note under Install Mobile Kitchen Trainer:

“Use Detail 5/C-502 for Mobile Kitchen Trainer Pad construction.”

2) Sheet C-122 – GRADING PLAN – SECTOR ONE

a. Add the following note to the 3 Stormwater Injection Bores indicated:

“Assume 50’ Bore Depth with a 1’ diameter.”

3) Sheet A-112B – SECOND FLOOR REFLECTED CEILING PLAN – SECTOR B

a. At Windows along Grid Line D.2 (high windows) add Window Tag 14.

Eight (8) Windows and associated Window Tags Total.

4) Sheet E-601 – ONE LINE DIAGRAM

a. Revise the notation associated with the feeder from the 200A switch and fuse in (SW2) to read: “PROVIDE (3) #4/0, 15KV ALUMINUM CABLES IN A 5” CONDUIT, AND (1)

SPARE 5” CONDUIT TO NAVY 4.16KV SUBSTATION. REFER TO ELECTRICAL SITE

PLAN ON SHEET E-100A.”

b. The notation “TO NAVY 4.16KV SUBSTATION” along the line between (SW1) 600A switch and (SW2) 600A switch should be deleted.

MODIFICATIONS TO SPECIFICATIONS:

1) Specification Section 034100 – PRECAST STRUCTURAL CONCRETE:

a. Revise Honed Finish to Acid-Etched Finish. Revise 034100 – 2.15.A.2 to read:

“1. Acid-Etched Finish: Use acid and hot-water solution, equipment, application techniques, and cleaning procedures to expose matrix surfaces and provide a smooth panel surface with no large exposed aggregate visible. Protect hardware and connections from acid attack.

a. Typical for exposed exterior precast panels.”

HIARNG Kalaeloa Readiness Center (RC) W90FY-Q-09-D-0006-9N02

Kalaeloa, Hawaii PN 150043

Addendum 004

19 April 2012 Page 2

2) Specification Section 034500 – PRECAST ARCHITECTURAL CONCRETE:

a. Revise Honed Finish to Acid-Etched Finish. Revise 034500 – 2.15.A.2 to read:

“1. Acid-Etched Finish: Use acid and hot-water solution, equipment, application techniques, and cleaning procedures to expose matrix surfaces and provide a smooth panel surface with no large exposed aggregate visible. Protect hardware and connections from acid attack.

b. Typical for exposed exterior precast panels.”

ATTACHMENTS: None

END OF ADDENDUM 004