AM-0002-W912HV21R0001-APSI Rev Spec-Dwg Final.pdf

PDF 178 KB Posted

Attached to
Asia Pacific Stability Initiative (APSI) – Fuel Receipt and Distribution Upgrades Yokota
Solicitation number
W912HV21R0001
Issued by

About this file

This document is an amendment to a solicitation for the Asia Pacific Stability Initiative (APSI) – Fuel Receipt and Distribution Upgrades Yokota project. The project involves expanding and upgrading an existing liquid fuel unloading facility at Yokota Air Base to accommodate both rail cars and fuel delivery trucks. Specific work includes replacing rail station headers, adding truck offload headers, constructing new below-ground drop tanks with pumps and piping, upgrading the backup generator, adding secondary containment and a remote spill containment basin, constructing truck access roads and an offload parking area, and improving on-base roads. The amendment extends the proposal due date from February 26, 2021 to March 9, 2021, and increases the offeror acceptance period from 180 to 210 calendar days. It also revises multiple specifications and drawing sheets and adds new specifications and drawings.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY20 MCAF ZNRE2031002 Asia Pacific Stability Iniative (APSI) - Fuel Receipt and Distribution Upgrades, Yokota AB.

See continuation page(s).

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HV21R0001

X 9B. DATED (SEE ITEM 11)

04-Nov-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Feb-2021

CODE

CONTRACTING DIVISION

USACE-JAPAN DISTRICT

RM 147, BLDG. 250

CAMP ZAMA

ZAMA-CITY, KANAGAWA 252-8511

JAPAN

W912HV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HV21R0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

CONTINUATION PAGE - AM-0002

A. CHANGES TO SPECIFICATIONS – The amendment mark “(AM-0002)” is shown on each page of the amended page(s).

(1) Revised Section(s) to Project Specifications. Attached hereto are the following revised section(s) to the specifications. Revised section(s) will replace like-numbered section(s) in the subject solicitation specifications, though some existing section attachment(s) pertaining to these sections remain in effect, as identified below. Changes are indicated by a red line in the left margin or in red font of revised areas. All portions of the revised section(s) shall apply whether or not changes have been indicated.

Revised Section(s) Section 01 11 00.00 10 (existing Attachment 01 11 00.00 10-A and 01 11 00.00 10-B remains in effect and are not attached to this Amendment)

Section 01 50 00 (existing Attachment 01 50 00-A and 01 50 00-B remains in effect and are not attached to this Amendment)

Section 03 30 00 Section 09 97 13.15 Section 09 97 13.27 Section 22 00 00 Section 26 05 48.00 10 Section 26 08 00

Section 26 11 16.00 33 (existing Attachment 26 11 16.00 33-A remains in effect and is not attached to this Amendment)

Section 26 20 00 Section 26 24 13 Section 26 32 15.00 10 Section 26 41 00 Section 33 52 40 Section 33 56 10 Section 33 57 55 Section 33 71 02 Section 34 11 00

(2) Revised Section Attachment(s) to Project Specifications. Attached hereto are the following revised section attachment(s) to the specifications. Revised section attachment(s) will replace like-numbered section attachment(s) in the subject solicitation specifications. Changes are indicated by a red line in the left margin or in red font of revised areas. All portions of the revised section attachment(s) shall apply whether or not changes have been indicated.

Revised Attachment(s) Section 01 33 00-B

(3) Added Section(s) to Project Specifications. Attached hereto are the following added section(s) to the specifications.

Added Section(s) 10 44 16

(4) Added Section Attachment(s) to Project Specifications. Attached hereto are the following added section attachment(s) to the specifications.

Added Attachment(s):

26 11 16.00 33-B

(5) Deleted Section(s) to Project Specifications. The following section(s) are deleted in its entirety from the specifications.

Deleted Section(s):

26 28 01.00 10

(6) The SF 1442 is revised as below:

The required response date/time at 13(A) is changed from 26-Feb-2021 02:00 PM to 09-Mar-2021 02:00 PM. The offeror acceptance period at 13(D) is increased by 30 from 180 to 210 calendar days for Government acceptance after the date offers are due.

B. CHANGES TO DRAWINGS (ISSUED) – The amendment mark “(AM-0002)” is shown on each sheet of the amended drawing sheet(s).

(1) Revised Sheet(s) to Drawings. Attached hereto are the following revised sheets to the drawings. Revised sheets will replace like-numbered sheets in the subject solicitation drawings. Changes are indicated in revision clouds. All portions of the revised sheet(s) shall apply whether or not changes have been indicated.

Revised Sheet(s) to Drawing:

G-003

CG121

CG122

CG123

C-502 C-503 S-001 S-401 M-002 M-017

MD101

MD102

MD103

M-103 M-104 M-105 M-106 M-107

M-204 M-401 M-402 M-403 M-504 P-101 P-501

ED401

EG102

EL501

EP103

EP401

EP502

EP601

EP602

EI502

EI701

EI702

M-108 M-109 M-110

EI801

EI802

C. All questions and the Government responses regarding this solicitation are to be submitted and viewed through the web-based program "Bidder Inquiry Module". This program is located on the world-wide internet and can be accessed at https://www.projnet.org/projnet. Answers provided to the respective questions through the ProjNet do not amend the solicitation (specifications, drawings, etc.) unless revision to the specifications or drawings is specifically noted and incorporated into the solicitation via an amendment.

D. The Proposal Due Date and Time has been extended to March 9, 2021 at 2:00 PM, Japan Standard Time.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 26-Feb-2021 02:00 PM to 09-Mar-2021 02:00 PM.

The offeror acceptance period has increased by 30 from 180 to 210.

(End of Summary of Changes)