This federal contract modification amends solicitation W912HP19R2000 for the Reception Complex Phase 1 project at Fort Jackson in South Carolina. The U.S. Army Corps of Engineers, Charleston District, extends the price proposal deadline to September 19, 2019 at 10:00 AM EST. Additionally, drawing files GI002, A-101X, and A-102X with Revision 2 dated September 9 are added to the contract drawings. The scope of work and list of drawings and specifications files are updated to include amendment files.

AMD 0003

View the file

Other files for this federal contract opportunity

Other files attached to Reception Complex Phase 1, newest first.
File Type Posted
B._AMD_0006_Solicitation_W912HP19R2000_Reception_Complex.pdf PDF
B._AMD0006_Solicitation_W912HP19R2001_BTC4.pdf PDF
B._AMD_0005_Solicitation_19R2000_Reception_Complex_Phase_1.pdf PDF
B._AMD_0004_Solicitation_W912HP19R20000_Reception_Complex.pdf PDF
Specifications_Volume_5_-_IFC_Reception_Phase_1_AMD4.pdf PDF
Drawings_Volume_2_-_IFC_Reception_Phase_1_AMD3.pdf PDF
Specifications_Volume_1_-_IFC_Reception_Phase_1_AMD2.PDF PDF
B._AMD_0002_Solicitation_W912HP19R2000_Reception_Complex.pdf PDF
Specifications_Volume_5_-_IFC_Reception_Phase_1_AMD2.pdf PDF
Drawings_Volume_1_-_IFC_Reception_Phase_1_AMD2.pdf PDF
Drawings_Volume_3_-_IFC_Reception_Phase_1_AMD2.pdf PDF
Drawings_Volume_2_-_IFC_Reception_Phase_1_AMD2.pdf PDF
Specifications_Volume_2_-_IFC_Reception_Phase_1_AMD2.PDF PDF
Specifications_Volume_1_-_IFC_Reception_Phase_I_AMD1.pdf PDF
A._Site_Visit_Sign-In_Sheet.pdf PDF
Specifications_Volume_2_-_IFC_Reception_Phase_I_AMD1.pdf PDF
Drawings_Volume_1_-_IFC_Reception_Phase_1_AMD1.pdf PDF
Drawings_Volume_3_-_IFC_Reception_Phase_I_AMD1.pdf PDF
Specifications_Volume_5_-_IFC_Reception_Phase_AMD1.pdf PDF
Drawings_Volume_2_-_IFC_Recepton_Phase_1_AMD1.pdf PDF
Specifications_Volume_3_-_IFC_Reception_Phase_I_AMD1.pdf PDF
B._AMD_0001_Solicitation_W912HP19R2000_Reception_Complex.pdf PDF
junc-up.dgn —
junc-sp1.dgn —
junc-sp.dgn —
junc-gp1.dgn —
junc-gp.dgn —
junc-dp.dgn —
junv-tp.dgn —
junv-rp.dgn —
Drawings_Volume_3_-_IFC_Reception_Phase_I.pdf PDF
B._Solicitation_W912HP19R2000_Reception_Complex_Phase_1,_Ft._Jax.pdf PDF
Drawings_Volume_4_-_IFC_Reception_Phase_I.pdf PDF
B._Attachment_1_-_Proposal_Data_Sheet.pdf PDF
Drawings_Volume_2_-_IFC_Reception_Phase_I.pdf PDF
B._Attachment_3_-_Past_Performance_Questionnaire.pdf PDF
Specifications_Volume_3_-_IFC_Reception_Phase_I.PDF PDF
Specifications_Volume_5_-_IFC_Reception_Phase_I.pdf PDF
B._Attachment_4_-_Small_Business_Participation_Plan.pdf PDF
B._Attachment_2_-_Descriptive_Summary_Sheet.pdf PDF
Specifications_Volume_2_-_IFC_Reception_Phase_I.PDF PDF
Specifications_Volume_1_-_IFC_Reception_Phase_I.PDF PDF
Drawings_Volume_1_-_IFC_Reception_Phase_I.pdf PDF
Specifications_Volume_4_-_IFC_Reception_Phase_I.PDF PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912HP19R2000, Reception Complex Phase 1, is hereby amended to revise/add draw ings and extend the price proposal until Thursday, 19 September 2019 at 10:00am EST. See continuation pages for further details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Sep-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HP19R2000

X 9B. DATED (SEE ITEM 11)

07-Aug-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Sep-2019

CODE

U.S. ARMY CORPS OF ENGINEERS, CHARLESTON

DISTRICT, CONTRACTING DIVISION

69-A HAGOOD AVENUE

CHARLESTON SC 29403

W912HP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HP19R2000

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMD 0003

A. CONTRACT CHANGES: The price proposal has been extended until Thursday, 19 September 2019 at 1000 hours EST.

B. TECHNICAL SPECIFICATION CHANGES: There are no specification changes issued with this amendment.

C. CONTRACT DRAWINGS –

Volume 2:

GI002, A-101X, and A-102X with Revision 2 dated 9 September are hereby added to and made a part of the Contract Drawings.

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

SOW

Scope of Work Reception Complex, Phase 1

Ft. Jackson, SC

The full Scope of Work is outlined in the Drawing and Specifications PDF files entitled as follows and are included as separate attachments and incorporated into the solicitation/contract by reference.

Drawings Volume 1 - IFC Reception Phase I.pdf Drawings Volume 2 - IFC Reception Phase I.pdf Drawings Volume 3 - IFC Reception Phase I.pdf Drawings Volume 4 - IFC Reception Phase I.pdf

Specifications Volume 1 - IFC Reception Phase I.pdf Specifications Volume 2 - IFC Reception Phase I.pdf

W912HP19R2000

Specifications Volume 3 - IFC Reception Phase I.pdf Specifications Volume 4 - IFC Reception Phase I.pdf Specifications Volume 5 - IFC Reception Phase I.pdf

AMD 0001

Drawings Volume 1 - IFC Reception Phase I_AMD1.pdf Drawings Volume 2 - IFC Reception Phase I._AMD1pdf Drawings Volume 3 - IFC Reception Phase I_AMD1.pdf

Specifications Volume 1 - IFC Reception Phase I_AMD1.pdf Specifications Volume 2 - IFC Reception Phase I_AMD1.pdf Specifications Volume 3 - IFC Reception Phase I_AMD1.pdf Specifications Volume 5 - IFC Reception Phase I_AMD1.pdf

AMD 0002

Drawings Volume 1 – IFC Reception Phase 1_AMD2.pdf Drawings Volume 2 – IFC Reception Phase 1_AMD 2.pdf Drawings Volume 3 – IFC Reception Phase 1_AMD 2.pdf

Specifications Volume 1 – IFC Reception Phase 1_AMD2.pdf Specifications Volume 2 – IFC Reception Phase 1_AMD2.pdf Specifications Volume 5 – IFC Reception Phase 1_AMD2.pdf

AMD 0003

Drawings Volume 2 – IFC Reception Phase 1_AMD3.pdf

(End of Summary of Changes)

File details come from the government source that posted it. Updated .