This solicitation package seeks proposals for the removal and replacement of existing electrical equipment, including airfield lighting and airfield vault equipment, and reconstruction of Runway 05-23 at Pope Army Airfield in North Carolina. The solicitation was posted on August 28, 2020 by the Department of the Army Corps of Engineers Engineering District Savannah. Proposals are due by October 15, 2020 at 1:00 pm Eastern Time. The package includes four drawings files, four specifications files, a construction entrance gate PDF, and a powerpoint file. If any file is replaced by an updated version, it will have the same file name. The complete solicitation package consists of all blue clickable links.

View the file

Other files

File Type Posted
B.04 Abstract (W912HN20B3010).pdf PDF
C.04 Bid Opening Roster.pdf PDF
20B3010 Pkg1vol1.PDF PDF
W912HN20B30100006.pdf PDF
20B3010 Pkg3.PDF PDF
20B3010 Pkg1vol2.PDF PDF
20B3010 Pkg2.PDF PDF
Projnet Bidder Inquiries List with Responses.pdf PDF
20B3010 Pkg1vol1.PDF PDF
B.08 W912HN20B30100005.pdf PDF
USAASA Response to Pope AAF PERM Waiver OCT2020.pdf PDF
W912HN-20-B-3010_AMD4_PACK2.pdf PDF
B.08 W912HN20B30100004.pdf PDF
20B3010 Pkg2.PDF PDF
W912HN-20-B-3010_AMD4_PACK3.pdf PDF
20B3010 Pkg1vol2.PDF PDF
20B3010 Pkg3.PDF PDF
20B3010 Pkg1vol1.PDF PDF
W912HN-20-B-3010_AMD4_PACK1.pdf PDF
B.08 W912HN20B30100003.pdf PDF
W912HN-20-B-3010_AMD2_PACK2.pdf PDF
B.08 W912HN20B30100002.pdf PDF
W912HN-20-B-3010_AMD2_PACK1.pdf PDF
W912HN-20-B-3010_AMD2_PACK3.pdf PDF
20B3010 Pkg1vol1.PDF PDF
20B3010 Pkg1vol2.PDF PDF
Webex Chat Log FA-80003-18.txt TXT text file
20B3010 Pkg1vol1.PDF PDF
B.08 W912HN20B30100001.pdf PDF
TSC - Webex Meeting Ft. Bragg-Runway 05-23 Rehab.pptx PPTX presentation
SAS-Webex Meeting PAAF Repairs Slides.pptx PPTX presentation
Site Visit Sign-In Sheet.pdf PDF
CMT Webex Meeting Ft. Bragg FA-80003-18-X.rev.02.pptx PPTX presentation
A.02 PAAF Runway Repair - Location of Construction Entrance.pptx PPTX presentation
A.02 FA-80003-18_Construction Entrance_20200804.pdf PDF
20B3010 Pkg1vol2.PDF PDF
FA-80003-18-2-FULL.pdf PDF
20B3010 Pkg2.PDF PDF
20B3010 Pkg1vol1.PDF PDF
FA-80003-18-3-FULL.pdf PDF
FA-80003-18-1-VOL 1-FULL.pdf PDF
20B3010 Pkg3.PDF PDF
FA-80003-18-1-VOL 2-FULL.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Bragg, North Carolina

Solicitation Number

W912HN-20-B-3010

Runway Pavement and Airfield Lighting Rehab Package 3: North Taxiway

PN FA-80003-18-3

August 2020

U.S. ARMY ENGINEER DISTRICT, SAVANNAH

CORPS OF ENGINEERS

100 WEST OGLETHORPE AVENUE

SAVANNAH, GEORGIA 31401-3640

US Army Corps of Engineers Savannah District

Runway Pavement and Airfield Lighting Rehab - Taxiway North 20B3010 Ft. Bragg, NC Pkg 3

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 13 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DI VI SI ON 26 - ELECTRI CAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19.10 10 INSULATED WIRE AND CABLE

26 56 00 EXTERIOR LIGHTING

26 56 20 AIRFIELD LIGHTING AND VISUAL NAVIGATION AIDS

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 63 29 DRILLED CONCRETE PIERS AND SHAFTS

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 11.51 PAINT REMOVAL FROM AIRFIELD PAVEMENTS

32 01 16.71 COLD MILLING ASPHALT PAVING

32 01 17.61 SEALING CRACKS IN ASPHALT PAVING

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS

32 11 23.00 GRADED-CRUSHED AGGREGATE BASE COURSES

32 11 40.00 CONTROLLED LOW-STRENGTH MATERIAL (CLSM)

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 15.13 ASPHALT PAVING FOR AIRFIELDS

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 17 23 PAVEMENT MARKINGS

PROJECT TABLE OF CONTENTS Page 1

32 92 19 SEEDING

32 92 23 SODDING

DI VI SI ON 33 - UTI LI TI ES

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

APPENDICES

Appendix A ADDITIONAL BORING LOGS AND LABORATORY TEST RESULTS Appendix B EROSION CONTROL LETTER OF APPROVAL

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.1.1 Description of Work

The Contractor shall furnish all personnel, equipment, tools, materials, supervision, and other items and services necessary to accomplish what the Statement of Work (SOW) calls for to be performed and provided (the Work).

All Work done shall conform to: the terms of the contract/task order;

applicable Government regulations and building codes individually referenced or not; manufacturers’ instructions; and generally-accepted standards in relevant design professions and building trades.

1.1.2 Complete Project

Documents the Government provides to the Contractor describing a project’s design intent and the Work are meant to convey what the Government expects and requires from the Work and to define a complete project. The Contractor is responsible to satisfy itself that what the Government provided does so, and to resolve any uncertainty as to this before committing to do the Work. Thereafter, any omission of express reference to specific services or materials reasonably inferred to fall within the project scope, or that are commonly understood within the applicable design profession or building trade as necessary to properly complete a project, will not relieve the Contractor of the responsibility to perform or provide such at no additional cost to the Government.

1.1.3 Location

Facilities to be constructed or altered are located at Pope Army Airfield, Fort Bragg, North Carolina. The Base is located approximately 10 miles northwest of Fayetteville, North Carolina. The work shall be accomplished on the Pope Army Airfield.

1.1.4 Free Zone for Construction on Airfield

The Contractor shall coordinate with the Contracting Officer and Fort Bragg's Department of Emergency Services to establish a "FREE ZONE" to accomplish construction activities on the airfield. Contractor shall be required to sign a Free Zone Procedures Agreement outlining the responsibilities associated with operating a Free Zone on the Airfield.

1.1.4.1 Example Free Zone Procedures Agreement

An agreement between _ {Insert Contractor Name} _ and the United States.

1. Intending to be legally bound, I hereby accept the obligation contained in this Agreement and its attachments in consideration of my being grated access to a Military Construction Project on Pope Army Airfield involving a Free Zone. Free Zones (zones containing no protection level resources) are areas established within a Restricted/Controlled area when construction projects and similar

SECTION 01 00 00 Page 1 activities make it in appropriate or impractical to apply normal circulation controls. I understand and accept that by being granted access to a Free Zone and having knowledge of Security Procedures, special confidence and trust shall be placed in me by the United States Government.

2. I understand that all personnel requiring unescorted access to the installation that does not possess a credential authorized to facilitate access must be vetted against government authoritative databases (AFI 31-113).

3. I hereby acknowledge that I have received security indoctrination concerning the procedures applicable to the Free Zone for the project that I am working on.

4. I have been advised that crossing a Free Zone boundary is prohibited unless specific written approval is granted or an escort is present. This boundary constitutes a legal "No Trespassing" area IAW Sec. 21 Internal Security Act of 1950; 50 U.S.C 797. If a "Restricted Area" boundary is crossed, the use of force, up to and including, deadly force or apprehension by Security Forces is authorized. Any breach of the Agreement may result in termination of access to the Free Zone and/or base barment. I recognize that nothing in this Agreement constitutes a waiver by the United States of the right to prosecute for any statutory violation.

5. I have read this Agreement carefully and my questions, if any, have been answered.

SIGNATURE DATE

ORGANIZATION (CONTRACTOR NAME AND ADDRESS)

1.1.5 Workday/Week

See Section 01 14 00 WORK RESTRICTIONS for standard work hours and procedures for working outside standard hours.

1.1.6 Base and Safety Regulations

The Contractor shall comply with all applicable Army regulations and directives pertaining to security, safety, occupational health, fire prevention, environmental hazards, traffic, and personnel clearances while on Base.

1.1.7 Safety Briefing

The Contractor shall brief subcontractors on safety, occupational health, and fire prevention regulations, emphasizing the requirement to obtain a welding permit, when welding, cutting and brazing operations are required, and obtain authorization from the Base Fire Chief when open burning is

SECTION 01 00 00 Page 2 intended. The Contractor shall maintain documentation showing that all subcontractors have been briefed as required.

1.1.8 Anti-Terrorism/Force Protection Standards

All constructed work shall conform with UFC 4-010-01, DoD Minimum AT Standards for Buildings issued under the authority of DoD Instruction Number 2000.16, DoD Antiterrorism Standards which requires DoD Components to adopt and adhere to common criteria and minimum construction standards to mitigate antiterrorism vulnerabilities and terrorist threats.

1.2 SUBMITTAL REQUIREMENTS

See 01 33 00 SUBMITTAL PROCEDURES for requirements relating to project submittals.

1.2.1 Substitution of Materials and Equipment

If the Contractor proposes to use materials, equipment or accessories other than those specified, in addition to the items listed preceding and to the extent informative in evaluating, the Contractor shall submit plan and elevation drawings of an appropriate scale showing all piping, electrical connections, sizes of equipment, location of piping, and electrical penetrations, and all other associated equipment and materials.

The Contracting Officer reserves the right to accept or reject any or all of what is proposed to be changed based on the design intent conveyed in the drawings and specifications, and the completeness and clarity of the request submittal.

For reasons of compatibility, and experience with certain critical existing equipment, systems, components, materials etc, the Government will not entertain requests to substitute others for those identified as “Base Standard” in project drawings or specifications. E.g., the Base Standard lock cylinder core is by Stanley-Best Access Systems and, unless otherwise noted, no submittal providing for a similar core by another manufacturer will be approved.

It shall be understood and agreed that any substitution of materials and/or equipment, if approved, will be made by the Contractor at no additional cost to the Government in consequence of it, regardless of any changes in connections, spacing, electrical service, or appurtenances the substitution may require.

1.2.2 As-Built Drawings and Specification

See 01 78 00 CLOSEOUT SUBMITTALS for as-built drawing and specification requirements.

1.2.3 Geobase Requirements

See Section 01 78 00 CLOSEOUT SUBMITTALS for record GIS deliverable requirements.

1.2.4 Real Property Records

At the completion of construction and before final payment, the following information, by facility number, shall be provided by the Contractor to the Contracting Officer on a completed DD form 1354 for record purposes.

The Contractor will be furnished a copy of a filled-in sample 1354

SECTION 01 00 00 Page 3

Worksheet, which should aid in completion of the form. The Contractor shall:

1. Provide a draft 1354 to the CO at least 45 days prior to the contract completion date. At a reasonably scheduled time upon receipt of the draft, a representative from the Real Property office with the Contractor will do a thorough walk through and annotate any findings or corrections required.

2. Prepare an accounting of all installed/constructed property, by building number (if multiple buildings are included in the project/task order).

3. List Government-furnished/Contractor-installed items and Contractor-furnished/ Contractor-installed items.

4. List complete nomenclature of each item:

a. Manufacturer.

b. Model Number.

c. Serial Number.

d. Electrical rating, full nameplate data.

e. Capacity (MBTU, KVA, Tons, Sprinkler Heads, Etc.).

f. Cost of each item (Equipment cost only)

g. Other pertinent information (Warranty/guarantee information-start date, stop date)

5. List items including, but not necessarily limited to, the following:

a. Electrical equipment (special lighting fixtures, metering equipment, exterior floodlights and poles, constant current regulators, airfield lighting fixtures, airfield signs etc.)

b. Mechanical equipment (heating equipment, air conditioning systems equipment, pumps, controls and other items of mechanical equipment)

c. Other items that are considered to be real property installed equipment

6. The Real Property office is the point of contact for questions, comments or concerns on property records. The Contracting Officer can provide an example of a completed 1354.

Both the worksheet and draft copy will be available at the onset of the project.

1.3 SAFETY AND ENVIRONMENTAL PLANS

The Contractor shall submit a safety plan in accordance with the current Corps of Engineers Safety Manual, EM-385-1-1, and shall submit an environmental protection plan in accordance with specifications Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, if included in these technical provisions. A sample safety plan form will be provided at the Preconstruction Conference.

1.4 WORK COORDINATION

1.4.1 General

The Contractor shall coordinate all work schedules with the Contracting Officer and the construction inspector prior to the start of work. The Contractor shall notify the CO or the construction inspector five days

SECTION 01 00 00 Page 4 prior to moving onto the work-site to commence work. The Contractor must provide notification the day when moving back to the work-site after an interruption of work of two (2) or more work days. Before initiating any work, the Contractor shall meet with the CO and inspector and agree on:

- sequence of procedures

- means of access to premises and buildings

- placement of dumpsters and haul routes

- delivery of materials and use of approaches

- use of corridors, stairways, elevators, and similar means of egress

- requirements and means of communication

- location of partitions and barriers

- location of eating spaces and restroom for the Contractor 's employees

- other matters incidental to the project

1. Interruption of Work: If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes (except as otherwise described in the solicitation documents), the Contractor shall request permission, in writing, from the CO, or designated representative(s), at least ten (10) working days in advance.

2. Temporary Construction: Any Contractor-installed temporary construction intended to prevent interruption of normal work activity or loss of utility services is subject to approval of the Fort Bragg DPW through the CO.

1.4.2 Inspection

The Contractor shall obtain the construction inspector's approval prior to doing such work as closing walls or performing tests. The request shall be made sufficiently far ahead to permit an inspection of the area beforehand. If the inspector fails to arrive at the site at the time agreed, the Contractor may continue with the work in strict compliance with the project drawings and specifications,. The inspector's approval or failure to appear does not relieve the Contractor of its obligation to comply with the construction documents.

1.4.3 Water Utility Work

The water utility lines on Pope Army Airfield are owned and operated by American States Utility Services (ASUS) . The Contractor shall coordinate with ASUS when conducting any work pertaining to the water utility lines.

Compliance with ASUS’s requirements does not relieve the Contractor from complying with Pope Army Airfield requirements, including submittals, as-builts, and other coordination.

1.4.4 Road Closures

If any full or partial closure of a road is required, the Contractor shall submit a request to do so to the COR three (3) weeks prior to the planned date for the closure. The request shall include a map showing the location of the closure and a suitable alternate route for detouring traffic normally using the road to be closed. The Contractor shall provide all signage and barricades required to properly direct traffic having to detour.

1.4.5 Project Superintendent

The Contractor must employ a full-time superintendent for the project. The superintendent’s duties shall include the overall management of the project, coordination of the sub-contractors’ work, and liaison with the

SECTION 01 00 00 Page 5

Contracting Officer and the construction inspector. No work shall be performed without the presence of the superintendent or a competent representative on the job-site. A competent representative is as defined by the Occupational Safety and Health Administration (OSHA) Standards for Construction Industry part 1926.32, Definitions (29 C.F.R. 1926 OSHA).

This paragraph supplements FAR clause 52.236-6, Superintendence by the Contractor.

1.4.6 24-Hour Point of Contact

The Contractor shall provide the Contracting Officer with a 24-hour number or numbers where its authorized representative can be contacted at anytime day or night. This number should be provided at the pre-construction conference, but, in any event, not later than the earlier of the first day of contract work at the site or ten (10) days after the Notice to Proceed date.

1.4.7 Contractor's Office Space

Office space required for the Contractor’s operation shall be the responsibility of the Contractor and self-provided. Any office space to be located on Pope Army Airfield must be approved by the Contracting Officer.

1.4.8 Contractor's Storage Area

The Contractor will be allowed to set up storage trailers as needed to conduct the work in the areas indicated in the contract drawings. . The location of storage trailers must be approved by the Contracting Officer in advance. The Government is not responsible for damages or losses. This paragraph supplements FAR clause 52.236-10, Operations and Storage Areas.

1.4.9 Site and Storage Area Maintenance

The Contractor is responsible for maintaining the construction site and storage area(s) daily. This includes, but is not limited to, lawn mowing, ice and snow removal, and disposal of trash and debris.

1.4.10 Haul Routes

The Contractor is required to use the haul routes shown on the contract drawings for transportation of new materials and demolition demolition materials unless otherwise permitted in writing by the COR. When haul routes are not designated in the contract, the Contractor must obtain approval from the COR for the routes he intends to use. The axle load of earth-hauling equipment operating on paved streets shall not exceed 12,000 pounds.

1.4.11 Dust Control

The Contractor shall control all excavations, embankments, stockpiles, access roads, and other such areas of work so as to avoid excess dust becoming a hazard or nuisance to base personnel or surrounding facilities.

Approved sprinkling, chemical treatment, light bituminous treatment or similar methods will be permitted to control dust during work. Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard may occur. Additionally, the Contractor shall ensure that any equipment hauling rock, soil, or other debris is fitted with a tarp or other means adequate to contain it and prevent littering of parking lots or roadways. The Contractor shall attempt to ensure its

SECTION 01 00 00 Page 6 trucks and other equipment do not leave mud and debris on the roadways and shall pick up, clear and/or sweep away by whatever means necessary any that does get on the roadways to the satisfaction of the Contracting Officer.

1.4.12 Patching and Repairing

After the work has been completed, any Contractor-caused damages to Government-owned structures or other facilities, streets, curbs, walks, lawns, etc., shall be properly patched, repaired, or replaced to the satisfaction of the Contracting Officer. Any holes, cuts, breakage or damage in/to finished surfaces in the area of work shall be properly repaired and the affected areas then refinished, resurfaced or otherwise repaired to match those of the adjacent to the satisfaction of the Contracting Officer.

1.4.13 Disposition of Removed Government Property

All materials and equipment to be removed by the Contractor and not reinstalled or recycled under this contract, including debris generated by the project work, shall be removed at regular intervals from the site and disposed of off-base by the Contractor. Such disposal shall be in conformity with applicable Federal, state, and local pollution regulations and at the Contractor’s expense.

1.4.14 Excavations & Landscaping

The Contractor shall backfill all excavations within one (1) week unless ongoing work in an excavation precludes such action. In no event shall the Contractor stockpile removed earth material on the construction site unless it is to be used in another portion of the same project. For all disturbances to grounds, the Contractor shall complete final grading within one (1) week of the disturbance/backfilling. The Contractor shall complete final landscaping or seeding within three (3) weeks of the beginning of the planting season if possible or as soon as possible later when suitable conditions exist.

1.4.15 Final Cleanup

Upon completion of the project, all construction equipment and debris shall be removed from the site, and the site left in a condition acceptable to the Contracting Officer. This paragraph supplements FAR 52.236-12, Cleaning Up.

1.5 PERMITS

1.5.1 General

The following outlines permits which may be required incidental to design or construction. The list is not a complete one of all which may be. It is the responsibility of the Contractor to determine which permits are required, if any; when they must be applied for; and timely obtain them, whether listed here or not. The Contractor shall submit all permit applications to the Contracting Officer and pay all permit fees when due.

SECTION 01 00 00 Page 7

1.5.2 Special Permits Required (As Applicable to Work)

1.5.2.1 Emergency Power Generator Permit

The Contractor shall contact the Fort Bragg DPW, Air Quality Program Manager, to learn the requirements for an emergency power generator prior to having the generator delivered to the base.

1.5.2.2 Burn Permit

A Welding, Cutting, and Brazing Permit (burn permit) must be obtained by the Contractor from the Bragg Fire Department prior to conducting any operation that will create a spark or flame. If an open burn permit is required, the permit request shall be routed through the Fort Bragg DPW, Air Quality Program manager, no-later-than three (3) months prior to actual open burn effort.

1.5.2.3 Notice of Proposed Construction or Alteration

As described in CFR Title 14 Code of Federal Regulations, part 77, when planning to build within 20,000 ft of an active runway or use equipment in construction which will penetrate a 100 to 1 slope from the nearest point of the runway, among other defined circumstances, notice to the Federal Aviation Administration (FAA) is required unless expressly exempted. The Contractor is responsible for ensuring that FAA Form 7460-1 is completed and forwarded 45 days prior to the start of any construction and approved prior to the start of the project. by the Regional FAA Office (Airports Division, 1 Aviation Plaza, Jamaica, NY; (718) 553-3330; FAX (718) 995-5694).

1.5.2.4 Sewer Permit

Sewer extension, new installation, and connection to the existing sanitary sewer system require a permit. The application shall be signed, certified and stamped by an North Carolina Registered Engineer and submitted to the Fort Bragg DPW for local coordination, and signatures.

1.5.2.5 General NDPDES Permit

Stormwater discharge from a construction site requires a Notice of Intent (NOI) under the National Pollutant Discharge Elimination System (NPDES) to be submitted to the North Carolina Department of Environmental Quality prior to any construction activities. Fort Bragg DPW has obtained the permit and filed the NOI in advance of this project, using the erosion control plans, notes and details included in the Contract Drawings. A copy of the permit(s) will be provided to the Contractor by the government. The Contractor shall comply with all provisions of the permit throughout the project duratino.

1.5.2.6 ASUS Water Use Permit

All work proposed which will affect the water utility system, including water main installation and connection, must be reviewed and a permit for it issued by ASUS prior to being done. All work must conform with what is stated on the permit.

1.5.2.7 Aboveground/Underground Storage Tank Permits

A permit is required to install or work on any aboveground storage tank

SECTION 01 00 00 Page 8 larger than 110 gallons, to include generator sub-base tanks, and any underground storage tank or associated piping. Contact Fort Bragg DPW for more information

1.5.2.8 Excavation Permit

The Contractor shall apply for and obtain a Government Excavation Permit, also known as a “digging permit”, prior to any excavation. The permit can be obtained from Fort Bragg DPW. There is no charge for the permit. The digging permit is required for the Government to locate and mark existing underground utilities as well as for the Government’s internal notification and coordination. The Contractor shall not begin any below-grade work until this permit has been completed and approved. The Contractor shall make every attempt to identify and locate all valve and utility shut-off locations for use in the event of accidental damage. The Contractor shall note any utilities discovered during excavations not shown or shown incorrectly on the contract drawings (including any erroneous or missing dimensions on Government record drawings), and clearly identify those discoveries on the as-built drawings.

The Contractor shall initiate the request for a digging permit a minimum of thirty (30) calendar days prior to any excavation or ground penetration. The site plan shall clearly delineate the proposed work area and, if within a reasonable distance, the nearest building and cross street to the location of digging, etc. The location of the excavation or ground penetration shall be marked with white, water soluble, spray paint, or white utility marking flags, and the markings maintained until the area is reviewed and cleared by all utility agencies concerned. In the event a representative of a designated utility does not respond, the Contractor shall immediately notify the Contracting Officer. After identified utilities have been cleared through each office affected, a copy of the digging permit will be provided. The digging permit must be on the job site during the excavation process and every precaution taken during excavation to prevent damage to the existing utilities. The Contractor must immediately notify Fort Bragg DPW and the Contracting Officer if any utility is damaged during the excavation process.

1.6 UTILITIES AND SERVICES

1.6.1 Commercial Utilities

The Contractor is permitted to use utility services, including electric, gas, sewer, water, telephone, cable, as its work may require. The Contractor is responsible for the cost and usage of temporary connections to the services and for portable sanitary facilities and other requirements. All utility connections must be approved by the Contracting Officer. The Contractor also is responsible for the cost of any new or relocation of existing commercial utility lines. The Contractor shall contact directly each applicable utility to pay all costs. Any exterior equipment provided under the contract shall be painted color in accordance with Fort Bragg Installation Design Guide.

1.6.2 Utility Outages

Request utility outages in writing to the CO at least 10 work days in advance. Utility outages will be held on normal work days, after hours or on weekend/holidays as coordinated with the Contracting Officer, Ft.

SECTION 01 00 00 Page 9

Bragg DPW and the utility provider. The decision on when to have an outage (normal work hours, weekend, etc) will be based on the length of the outage and the normal business hours/hours of maximum usage for the facilities affected by the outage. Outages will be limited to a duration of 4 hours unless extenuating circumstances dictate otherwise.

1.6.3 Payment for Utility Services

The Government will make all reasonably required utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to and paid for by the Contractor at the prevailing rates. The Contractor shall carefully conserve all utilities furnished.

1.6.4 Meters and Temporary Connections

The Contractor, at its expense and in a manner satisfactory to the Contracting Officer, shall provide and maintain necessary temporary connections, distribution lines, and meters required to measure the amount of each utility used for the purpose of determining charges. The Contractor shall notify the Contracting Officer's Representative, in writing, no less than 10 working days before the temporary connection is made. The Contracting Officers Representative will then provide the contractor with the name and phone number of the utility provider. The contractor will be responsible for contacting the utility provider and making arrangements for connections and billing. For temporary electrical connections the Government or applicable utility provider will provide the meter (meter base provided by contractor) and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. The Contractor shall not make the final electrical connection. For temporary water and sewer connections the contractor will provide the meter and after inspection/approval by the Contracting Officer's Representative make the final connection at the contractor's expense.

1.6.5 Use of Permanent Building Utility Connections

Utilities consumed by the contractor from permanent building utility connections shall also be metered and paid for by the contractor. When the permanent system is activated the initial meter reading shall be recorded and reported as specified below. On building renovation projects the initial meter reading shall be recorded when the contractor is given possession of the building to perform the work. The contractor shall pay for utilities consumed through the permanent building connection until the work has been completed or the government has occupied the facility, which ever occurs first.

1.6.6 Initial Meter Readings

Upon installation of the meter, the initial reading shall be recorded (in the presence of the Contracting Officer's Representative) and forwarded to the point of contact for utility service with a copy to the Contracting Officer's Representative.

1.6.7 Final Meter Readings

Before completion of the work and final acceptance of the work by the Government, the Contractor shall notify the Contracting Officer and the

SECTION 01 00 00 Page 10 applicable utility provider, in writing, 10 working days before termination is desired. The Government or applicable utility provider will take a final meter reading. Electric service will be disconnected by the provider. Water and sewer connections will be disconnected by the contractor, at his expenses and by a method approved by the Contracting Officer's Representative. The Contractor shall then remove all the temporary distribution lines, meters, meter bases, and associated paraphernalia. The Contractor shall pay all outstanding utility bills before final acceptance of the work by the Government. Rates are subject to change.

1.6.8 Utility Charge Rates

Water ------------ $9.80134 per 1,000 gallons Electricity ------ $0.08906 per KW hour Wastewater ------- $9.85421 per 1,000 gallons

Rates are subject to change. Contact utility providers for trailers utility connection requirements.

1.6.9 Temporary Water Service Connections

The Contractor shall notify ASUS 10 days in advance of its requirement for temporary water service. All temporary water connections shall be performed by the Contractor at the expense of the Contractor. Where appropriate, backflow devices shall be used. All temporary service lines installed and used by the Contactor or any subcontractor during construction must be completely removed at the Contractor’s expense by the project’s completion.

1.6.10 Water Service Interruptions

The Contractor shall submit written notification not less than 14 work days in advance for each planned interruption of a utility service. No single interruption shall exceed eight hours. Any interruption of utility service must be approved by the Contracting Officer in advance. Service interruptions shall be accomplished at other than normal work hours if feasible. As a general rule, water distribution service shall not be interrupted. All water connections shall be made via “hot” tap on the main and shall be observed by ASUS personnel. ASUS is responsible for determining what constitutes sufficient reason to interrupt water service.

Interruption of water service due to scheduled construction work involving water system components shall be coordinated with ASUS at least 10 work days in advance to allow for proper water outage planning and water outage notification to affected parties. ASUS staff shall operate all valves and hydrants during any outage plan test and implementation of the scheduled water system outages and service restoration. The Contractor performing work requiring the interruption of water service shall provide all material, labor, and equipment required to minimize the extent and duration of a water outage and shall ensure restoration of service in the most efficient and complete manner in accordance with accepted industry standards and practices. This may require one or more line stops to preclude an extensive outage to multiple facilities. The Contractor shall comply with all base and state environmental requirements.

1.6.11 Abandonment of Water Lines

Service lines to be abandoned shall be excavated at the curb stop or corporation stop and the valve closed off. The service shall be physically

SECTION 01 00 00 Page 11 separated so as to have a minimum of three (3) feet horizontal clearance between the main and the cut service line. The location of the disconnection shall be noted on project as-built drawings, with a copy showing the point of disconnection provided to ASUS.

Water mains to be abandoned shall be cut and depressurized, then capped with a mechanical cap or concrete cover. Valves shall be closed, and the valve boxes removed. All fire hydrants abandoned shall be fully removed.

In the event a shut off valve is not available, the Contractor shall install a temporary line stop to enable separation of the water mains.

Where settlement is a structural concern, putting flowable fill in the main may be required.

1.6.12 Enabling/Disabling Fire Alarms Panels

All fire alarm panels shall be properly operating prior to the Contractor securing at the end of each workday. To have a fire alarm panel enabled/disabled the Contractor shall coordinate through the Resident Engineer. The Contractor shall bear all costs associated with enabling/disabling fire alarm panels.

1.6.13 Fire Hydrant Connection

Temporary connections to fire hydrants require prior coordination and approval from the Operations & Maintenance department of the water distribution system owner, ASUS, to ensure the proper operation of the hydrant and installation of an appropriate backflow prevention device. The Contractor shall be responsible for obtaining all devices and bearing all costs associated with providing, installing, and testing the backflow device.

1.6.14 Natural Gas Connection

The Contractor is responsible for making arrangements with the on-base natural gas utility for work involving the natural gas service. The Contractor shall bear all costs associated with moving or extending gas lines/service as well as all costs for meter installation. Existing natural gas lines are owned by Piedmont Natural Gas (PNG) . The Contractor shall complete all hookups to natural gas at completion of job.

1.7 MAINTENANCE/WARRANTY INFORMATION

1.7.1 Operations and Maintenance Manuals

The Contractor shall provide the Contracting Officer a specified number of copies of operation and maintenance instruction manuals. Except to the extent stated in more stringent terms in other parts of the drawings or specifications, manuals shall contain complete instructions on operating and maintaining the equipment, including piping and wiring diagrams. The manual shall be assembled in book form having a cover indicating the contents by equipment or system name and project title. Manuals shall be submitted a minimum of ten work days before the Contractor conducts the on-site operation and maintenance instruction. If such instruction is not required by the other parts of the specifications, manuals shall be provided at the final inspection.

1.7.2 Spare Parts List

Where required by the other parts of the specifications, the Contractor

SECTION 01 00 00 Page 12 shall provide the Contracting Officer the specified number of copies of spare parts lists. The lists shall provide the supply source, item description and current price of all parts and shall be cross referenced to equipment diagrams or pictures. Spare parts lists shall be assembled in book form and may be separate from or integral with the operation and maintenance instruction manuals. Spare parts lists shall be submitted with the related instruction manuals.

1.7.3 On-Site Instruction

The Contractor shall provide the services of a qualified person, where required by other parts of the specifications, to instruct Government personnel in the proper operation and maintenance of newly installed systems and equipment. The instructions shall be in accordance with the procedures and methods recommended by the equipment manufacturer. The Contractor shall schedule the on-site instruction with the Contracting Officer, but such instruction shall not occur until ten days after the receipt of operation and maintenance instruction manuals.

1.7.4 Back Flow Prevention Devices

In accordance with AFI 32-1066, all newly installed back flow prevention devices must be inspected by a certified inspector within one (1) week of installation and a follow-up inspection performed 3-months later. The Contractor shall submit appropriate documentation of these inspections in accordance with the submittal register.

1.7.5 Warranty Items

There shall be a maximum 24-hour response time by the Contractor on all warranty items installed under this contract and identified as either malfunctioning or inoperative after acceptance of the item. The Contractor shall notify both the Contracting Officer or his designated representative and the Inspector of the date, place, and time that the Contractor will be on location to determine the cause of the problem. Response time shall be defined as the time from when the Contracting Officer contacts the Contractor until the time the Contractor is present at the location of the equipment with the appropriate personnel to determine the problem and what is necessary to correct the problem. Warranty items shall be defined as all equipment, components, appurtenances, and wiring installed and the labor and materials necessary to install said items.

Corrective action shall be completed within 5 work days from the time the Contractor visits the location of the malfunction or inoperative equipment. Where parts are required to correct a malfunction, corrective action shall be completed within 5 work days from the time parts are received. If the Contractor fails to respond within the time frame indicated above, the Government shall declare the Contractor non-responsive and shall take all actions necessary to correct the problem with Government resources. All costs incurred as a result of the Government taking this action shall be properly accounted for and back charged to the Contractor.

1.8 OTHER INFORMATION

1.8.1 Shoring and Safety

The Contractor shall provide all shoring as required in accordance with local, state, federal and OSHA requirements for excavations utilized for

SECTION 01 00 00 Page 13 this project's scope of work. All workers shall be protected from danger.

Additionally all excavations shall be secured as necessary to prevent unauthorized personnel from entering the work sites and/or excavations.

1.8.2 Environmental Work

If contract requires specific environmental work be performed, no non-environmental work shall be accomplished which will alter the environmental work specifications or cause contamination of non-contaminated materials and areas.

1.8.3 Products Not Allowed

Materials containing asbestos, transformers containing PCB fluid, and the use of lead based paints or paints containing chromates are prohibited.

1.8.4 Ozone Depleting Chemicals

Ozone Depleting Chemicals, Class I and II listed in Attachment 2 of AFI 32-7080 are to be recovered by the Contractor and returned to the Government. The Ozone Depleting Chemicals may not be sold or given away to private industry unless otherwise specified by the Government.

1.8.5 Pesticide Applications

All pesticide applications must be approved by the Contracting Officer through the Base Entomology Shop. The Installation Pest Management Coordinator (IPMC) will determine if pesticides are on the approved chemical list for use on Pope Army Airfield. A label and Safety Data Sheet (SDS) of the pesticide must be available for review. All contract employees that apply pesticides must have an North Carolina pesticide application certificate/license and be registered in the Integrated Pest Management System (IPMIS). Following approval, the contractor shall maintain an inventory listing of all pesticides used on the installation for performance of this contract. The inventory listing shall contain the name of each pesticide used, location of the material, the container size, and location of the SDS. The contractor shall provide a monthly report of pesticides to the IPMC.

1.8.6 Radioactive Material (RAM)

The use of any device (e.g. soil density meters, XRF meters, etc) which contains RAM must be approved by the Base Radiation Safety Officer, at least 30 days prior to bringing RAM onto Fort Bragg.

1.8.7 Brand Names

References in specifications to any brand name equipment or materials shall be regarded as establishing a standard of quality and – to the extent not conflicting with II. C. of these General Conditions, regarding substitutions – shall not be construed as limiting competition. The Contractor may submit proposed equal equipment and/or materials for Government consideration during the submittal process of the contract after award.

1.8.8 Photographs

When permitted, the Contractor shall provide a minimum of twelve 4" x 6" color photographs prior to beginning actual construction and at two (2)

SECTION 01 00 00 Page 14 week intervals thereafter for the duration of the project’s construction.

The Contractor shall coordinate with: Fort Bragg Public Affairs (910-432-0502) and 43d Air Mobility Operations Group, Public Affairs Office (910-394-2357) and the facility user prior to taking any photographs of the construction area. Photographs shall be taken at different angles/locations so that the existing conditions, along with the construction progress, are fully represented. Photographs shall be taken inside and outside for all projects involving interior and exterior work.

Photos shall be submitted electronically. The photograph file name/title shall include a general description of the photo along with the date the photo was taken. Photos shall be submitted in accordance with the submittal schedule.

1.8.9 Recycling

The Contractor shall recycle all ferrous and non-ferrous metals removed in the project and general administrative refuse generated by it such as cardboard, one gallon mark 1 and 2 plastic bottles, type 1 and 2 plastic soda bottles, aluminum and steel soda cans, and mixed paper. All recyclable material shall be turned into the recycled off base.

1.8.10 Environmental Management System

Pope Army Airfield is committed to conducting its mission in a responsible manner which will protect human health, natural resources and the environment. Contractors will reduce environmental risks, promote pollution prevention, and meet all Environmental regulatory requirements during the execution and completion of the contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 00 00 Page 15

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with a "RO" designation indicate the USACE Resident Office is the approving authority for the submittal. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals Salvage Plan ; G, RO

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes milling and overlay of taxiway shoulders in conjuction with the installation of new taxiway edge lighting and signage will also be installed.

1.2.2 Location

The work is located on the Pope Army Airfield, Fort Bragg, North Carolina.

The exact location s are shown in the contract drawings .

1.3 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND UTILITIES

Obtain Government Excavation Permit (digging permit) prior to start of excavation. See 01 00 00 GENERAL REQUIREMENTS for procedures. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating

SECTION 01 11 00 Page 1

Radar (GPR), electromagnetic, or sonic equipment as needed to identify buried utilities , and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

1.5 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located on Pope Army Airfield .

Provide a salvage plan , listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

Required salvage items are listed below.

a. Taxiway Edge Lights. Select the 25 edge lights in best condition and turn over to the Government at a location identified by the

COR.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with a "RO" designation indicate the USACE Resident Office is the approving authority for the submittal. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel ; G, RO

1.2 SPECIAL SCHEDULING REQUIREMENTS

a. Prior to closing Runway 05/23 for construction, contractor shall demonstrate to the government their plan to execute the work within the allowable time frame is complete and ready for execution. At a minimum, material and equipment submittal approvals shall be completed and required materials shall be on-hand or ordered and scheduled for delivery at the appropriate time(s).

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The

SECTION 01 14 00 Page 1

Contracting Officer will identify designated smoking areas.

1.3.2 Working Hours

Regular government working hours consist of an 8 1/2 hour period , between 7 a.m. and 3:30 p.m., Monday through Friday, , excluding Government holidays. However, Contractor work hours for this project are anticipated to be as much as 7 days per week and 24 hours per day during certain activities, including Federal Holidays. Contractor shall notify COR of anticipated weekly work schedule at least 14 calendar days in advance.

Fort Bragg observes the following Legal Holidays on the day shown or the Friday before if it falls on a Saturday or the Monday after if it falls on a Sunday:

New Year's Day 1 January

Martin Luther King Day Third Monday in January

Presidents…

This is the start of the file's text. The full file is on GovTribe.