This document is an amendment to a solicitation for construction services at Moody Air Force Base. The amendment changes the site visit date and registration deadline to July 14, 2020 and July 6, 2020 respectively. It also extends the bid due date to August 6, 2020. The solicitation is for construction of a Personnel Recovery Hangar at Moody AFB and was originally posted on June 23, 2020 by the Department of the Army Corps of Engineers Savannah District with bids due on July 23, 2020. The specifications include construction requirements and drawings.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QSEU083023
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Purpose of this amendment is to make the follow ing changes:
1. The site visit has changed to July 14, 2020 at 9:30 AM ET.
2. The last day to register for the site visit is July 6, 2020. Any requests submitted after 11:59PM ET on July 6, 2020 w ill not be accepted.
Follow the instructions in the site visit clause, 52.236-27 Alt I for registration procedures.
3. The bid due date is changed to August 6, 2020, 2:00 PM ET.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HN20B3002
X 9B. DATED (SEE ITEM 11)
23-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Jun-2020
CODE
USACE - SAVANNAH DISTRICT
100 W. OGLETHORPE AVE
SAVANNAH GA 31401
W912HN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HN20B3002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 23-Jul-2020 02:00 PM to 06-Aug-2020 02:00 PM.
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- July 14, 2020.
(c) Participants will meet at—
Check-in time begins at 0930 AM ET. Expect approximately one hour to allow for all visitor passes to be processed. Visitors are to report to the visitors center at the south gate to Moody AFB accessed at the intersection of Bemiss Rd(Hwy 125) and Davidson Rd. Transportation via bus from the gate to the project site is planned.
Visitors are to provide full name and State Driver's license number to the Project Manager, Mr. Craig
Harrell, email: craig.l.harrell@usace.army.mil, telephone number: 912-652-5150. The last day for site visit participants to register for the site visit is July 6, 2020.
(End of provision)
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by reference:
52.236-10 Operations and Storage Areas APR 1984
The following have been modified:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in
W912HN20B3002
the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor any time between the date of award and within 120 calendar days after issuance of Notice to Proceed. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
The following have been deleted:
52.246-21 Alt I Warranty of Construction (Mar 1994) - Alternate I APR 1984 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012