This pre-solicitation notice announces the U.S. Army Corps of Engineers' intent to issue a request for proposals for multiple award task order contracts to provide design-build and design-bid-build construction services throughout Italy. The contracts will have a maximum value of $49,999,995 over five one-year ordering periods. Services will include new construction, renovation, repair, utilities, and environmental remediation work. A two-phase evaluation process will be used to select up to five awardees. Interested firms must submit qualification documentation by March 22 to be included on a restricted plan holders list and invited to participate further. The notice provides details on the planned solicitation, pre-proposal conference, place of performance, and required documentation for firms to demonstrate qualifications under Italian law.
This amendment makes various changes. See continued pages. Changes to the RFP sections are shown within this amendment in the following pages via "track changes". Insertions are highlighted via blue, bold font. Deletions are highlighted via red, strikethrough font. *Note the specifications binder is replaced in its entirety (via separate attachment).
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY19 Italy MATOC
This amendment makes various changes. See continued pages. Changes to the RFP sections are show n w ithin this amendment in the follow ing pages via "track changes". Insertions are highlighted via blue, bold font. Deletions are highlighted via red, strikethrough font. Note the specif ications binder is replaced in its entirety.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912GB19R0031
X 9B. DATED (SEE ITEM 11)
07-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Apr-2018
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912GB19R0031
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The following have been modified:
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 00 00 00 Procurement and Contracting Requirements SECTION 00 01 10 Table of Contents SECTION 00 10 00 Solicitation Contract Line Item Number (CLIN) Schedule SECTION 00 21 00 Instructions to Offerors SECTION 00 22 00 Supplementary Instructions – Phase ONE of TWO SECTION 00 22 20 Supplementary Instructions – Phase TWO of TWO SECTION 00 45 00 Representations and Certifications - Clauses SECTION 00 70 00 Conditions of the Contract – Contract Clauses SECTION 01 11 00 Summary of Work SECTION 01 30 00 Administrative Requirements
ATTACHMENTS
ATTACHMENT 1 - SPECIFICATIONS BINDER (replaced entirely via solicitation amendment 0004) ATTACHMENT 2 - EXPERIENCE INFORMATION SHEET (updated via solicitation amendment 0003)
ATTACHMENT 3 - EXPERIENCE OVERVIEW SHEET
ATTACHMENT 4 - PAST PERFORMANCE EVALUATION QUESTIONNAIRE
ATTACHMENT 5 - BANK LETTER OF ASSURANCE TEMPLATE (updated via solicitation amendment 0002)
ATTACHMENT 6 - BANK LETTER OF GUARANTY TEMPLATE
ATTACHMENT 7 - SAMPLE COMMITMENT LETTER
ATTACHMENT 8 - PREPROPOSAL CONFERENCE ATTENDEE INFO SHEET
SECTION 00 21 00 - INSTRUCTIONS
INSTRUCTIONS
A. INTRODUCTION
1. The US Army Corps of Engineers (USACE) Europe District (NAU) intends to award a target of five (5) Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) for Design-Build and Design-Bid-Build Construction providing new facilities and real property repair and maintenance in support of defense operations in Italy. NOTE: When the word “Offeror” is encountered in the RFP, it is intended to mean a company seeking to do business with the Government that submits a proposal in response to this Solicitation. When the word “Government” is encountered, it is intended to mean USACE NAU. “Request For Proposal,” “RFP” and “Solicitation” are used synonymously throughout.
2. All task orders under this MATOC shall not exceed the total shared capacity of $49,995,000.0049,950.000.
Each awardee will be given fair opportunity for each order in accordance with FAR 16.505(b)(1). The Government may exceed the stated minimum/maximum task order limitation upon mutual agreement of all parties (see FAR 52.216-19 in the RFP).
3. For the purposes of this Solicitation, the Government will utilize the Two-Phase Design-Build Selection
Procedures in accordance with FAR 36.303.
a. In Phase ONE, interested firms or joint venture entities (referred to as “Offerors”) shall submit specified performance capability proposals, demonstrating their capability to successfully perform task orders under the awarded contract. The Government will evaluate the qualifications in accordance with the criteria described in this Solicitation and intends to select a maximum of seven (7) of the most highly qualified Offerors to submit competitive proposals in Phase TWO.
b. In Phase TWO, the Government will evaluate both technical capability and price. Only those Offerors who receive a written notification that their firm has been selected to participate in Phase TWO of this Solicitation are invited to submit a Phase TWO proposal. Those Offerors selected for Phase TWO will be provided the technical requirements package for one or more Seed Task Orders that will be representative of the type work and task orders anticipated to be issued under any resultant contract(s). The Government intends to award a target of five IDIQ contracts resulting from Phase TWO. Award may be made to fewer than or greater than five Offerors at the Government’s discretion. The Government’s Phase TWO evaluation approach will utilize the Best Value Tradeoff Process for Source Selection in accordance with FAR 15.101-1 to determine best value. See Section 00 22 20 for further details on the Government’s Phase TWO evaluation approach.
4. General Description of Seed Task Orders: Please note the following is a general description of the anticipated Seed Task Orders; it is not the final description:
SEED Project 1: The Contractor shall provide design and construction services to renovate existing buildings 6A and 6B on Caserma Ederle in Vicenza, Italy that function as barracks. The functional purpose of the building will not change. The renovation includes interior architectural upgrades and systems upgrades (mechanical, electrical, communications and plumbing), and new fire suppression system.
SEED Project 2: Project consists of renovation of two separate buildings on the US Army base in Longare, Italy. Building 1 scope consists of the following: Renovation of the 2nd and 3rd floor of a three story, solid concrete/masonry structure with an approximate gross area of 1,660 m2 (17,868 ft2). The renovations include architectural and minor layout changes to include: reconfiguration of interior walls on the second floor, painting, flooring, interior doors and frames, window coverings, security upgrades, electrical upgrades and open storage secret space, new lighting, new HVAC distribution system and security, electrical, and communications upgrades and misc. other improvements. Building 2 scope consists of the following: Complete renovation of a single story, solid concrete/masonry structure with clay tile joist roof framing single. The building is currently configured as a veterinary clinic and will be renovation to be used as an Emergency Operations Center. The renovations includes demolition and relocation of interior non-loading walls to accommodate new open and private office layouts, new restroom configuration, new interior finishes, new doors and window coverings, security upgrades, new electrical distribution system, communications upgrades, new HVAC distribution system, and misc. other improvements.
SEED Project 3: The Contractor shall provide design and construction services to renovate 12 existing Earth Covered Magazines (ECMs) and 7 Above Ground Magazines (AGMs) at Caserma Darby outside Livorno, Italy. The renovations include concrete repair, grubbing, demolition, excavation, and new intrusion detection equipment with associated new fiber communication lines.
B. PRE-PROPOSAL CONFERENCE
The Government intends to hold a pre-proposal conference for Phase ONE and a combined pre-proposal conference with site visit at the seed projects locations in Phase TWO. Only the most highly qualified offerors from Phase ONE will participate in the pre-proposal conference for Phase TWO.
The Phase ONE pre-proposal conference details are as follows:
1. Location:
Viest Hotel (https://www.viest.it/en/) Via Uberto Scarpelli, 41 36100 Vicenza (VI), Italy
2. Time/Date: The conference will take place on 16 April 2019. Check-in will begin at 0900 local time and presentations will begin at 0930. The conference is expected to conclude no later than 1200.
3. Registration Instructions: Due to limited space, attendees are limited to no more than TWO people per Offeror.
Offerors must pre-register their attendees no later than 12 April 2019 at 1500 Central European Time. To Pre- Register, complete the site visit attendee information sheet (RFP attachment) and upload it to FBO via the “Electronic Response” feature (see paragraph C3a below for further instructions on that feature).
C. PROPOSAL SUBMISSION
1. Introduction. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Offerors are required to meet all Solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors.
The Offeror shall submit in the proposal all requested information specified in this section of the Request for Proposal (RFP) at or before the exact time specified. Failure to meet a requirement may result in an Offeror being ineligible for award. Copies of the RFP are available by INTERNET ACCESS ONLY. All RFP documents will made available for viewing at the Federal Business Opportunities (FBO) website (http://www.fbo.gov). All amendments will be made available for viewing in FBO. It shall be the Offeror’s responsibility to check the website for any amendments.
2. Inquiries. Offerors with technical inquiries and any other questions shall submit their inquiries via Bidder
Inquiry in ProjNet at http://www.projnet.org/projnet. The bidder inquiry key is: RH675A-FFGS94
Offerors are requested to review the specification in its entirety and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The Government reserves the right to decline addressing certain questions. Further, no questions, unless in the Government’s interest, will be answered any later than ten business calendar days prior to the stated deadline for offers. All Offerors are encouraged to register on ProjNet for alerts to stay abreast of Q&A’s that are posted in reference to this Solicitation. Only self-registered users on ProjNet can submit and review inquiries. To self-register, go to the webpage, click BID tab, select Bidder Inquiry, select agency USACE, enter the key for this Solicitation listed above, and your email address. After initial login, enter all the required information to create your user ID. Verify the information on the next screen and from there you may submit and view inquiries. Those submitting inquiries will receive a system generated email notification when their inquiry has been processed and answered. It is the Offeror’s responsibility to monitor for inquiries and responses.
3. General Proposal Submission Requirements.
c. Electronic Proposals. In an effort to reduce paperwork and costs, ALL RESPONSES TO THIS ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY. Hand carried delivery or USPS/UPS/Fedex delivery of hard copies and/or CD-ROMs are not authorized. Facsimile submission is not authorized. Email submission is not authorized. ELECTRONIC PROPOSAL SUBMISSION IS REQUIRED THROUGH THE FEDBIZOPPS (FBO.GOV) “ELECTRONIC RESPONSE” FEATURE. The FBO vendor user guide has information & instructions on how to utilize this feature. The FBO vendor user guide is accessible via the following web URL:
https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf.
d. File Size Limitations. Offerors are advised to follow the FBO instructions for uploading files larger than 10MB (java upload). FBO has not posted official file size limitations for its electronic response module;
however, it has been observed that uploads to FBO tend to be problematic when the files are sized 100MB or greater. If needed, Offerors are advised to break the files down into smaller sections to upload it to the system. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
e. File Names. To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention: Each filename shall begin with the Solicitation number, followed by the word “RESPONSE,” followed by your firm’s name, and finally a brief file description. EXAMPLES:
(1) “W912GB19R0031 RESPONSE Firmname Volume I.pdf”
(2) “W912GB19R0031 RESPONSE Firmname Volume I Part 1.pdf”
(3) “W912GB19R0031 RESPONSE Firmname Volume I Part 2.pdf”
(4) “W912GB19R0031 RESPONSE Firmname Volume I diagrams, figures.pdf”
(5) “W912GB19R0031 RESPONSE Firmname Volume II.pdf”
f. File Organization, Formatting, and other instructions. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger. Pages shall be letter sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages. Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Proposals shall completely and adequately address the requirements of this Solicitation. Offerors are reminded that elaborate corporate marketing information, formatting, special reproduction techniques, etc., are not necessary. Failing to submit attachments or failing to complete the proposal properly may result in rejection of the offer without further evaluation. Information pertaining to more than one evaluation factor should be repeated in the each section for each factor. Electronic files shall be Microsoft Windows compatible. Files shall be submitted in their native format (i.e., doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one zipped folder.
g. Upload Completion & Deadline. Interested parties shall submit responses no later than the date specified on the Solicitation document. The time & date of proposal receipt will be the upload completion / delivery time & date recorded within FBO. Do not assume that electronic submission will occur instantaneously.
Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process and troubleshooting. Proposal submission difficulties should be coordinated with the Federal Service Desk at https://fsd.gov and/or +1-866-606-8220 (Mon-Fri 8am-8pm Eastern Time UTC -5:00). Experience shows that if an upload does not complete until after the deadline, the FBO upload WILL NOT COMPLETE. The FBO system will automatically shut off the “Electronic Submission” feature at the specified deadline--once that occurs, the feature will disappear from the announcement. Offerors are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline may be emailed to Jason Malak, Contract Specialist (jason.r.malak@usace.army.mil), but be advised they will be considered late and as such will be processed in accordance with FAR 15.208.
h. Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to OfferorsCompetitive Acquisition (Jan 2004),” subparagraph (e). The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.
i. SPECIAL NOTICE: System for Award Management. Please take notice that the System for Award
Management (SAM, www.sam.gov) has a new entity registration requirement that firms submit an "original, signed notarized letter identifying the authorized Entity Administrator for the entity associated with the Data Universal Numbering System (DUNS) number before the registration will be activated." This applies to all new entity registrations and all entity registration renewals, effective 29 April 2018. Further information behind this new requirement is posted to the General Services Administration's (GSA) announcement page at https://www.gsa.gov/samupdate. Please also refer to Federal Service Desk's (FSD) instructions on how to comply with this new requirement. NOTE: the instructions are different for domestic (U.S. based) and international (not U.S. based) firms. Offerors are reminded that this Solicitation includes the provision FAR 52.204-7 SAM or FAR 52.212-1 Instructions to Offerors--Commercial Items, and the resulting award will include the clause FAR 52.204- 13 SAM Maintenance or 52.212-4 Contract Terms and Conditions--Commercial Items. These provisions/clauses require all contractors to register and maintain an active SAM entity registration in order to be eligible for contract awards, as prescribed by the regulation at FAR Subpart 4.11. In order to eligible for the contract award resulting from this Solicitation, Offerors are advised to take immediate action to ensure your SAM entity registration is current and/or will be current at the time of proposal receipt by this contracting office. Instructions for domestic entities (located in the U.S. or its outlying areas): https://fsd.gov/fsd-gov/answer.do?sysparm_kbid=d2e67885db0d5f00b3257d321f96194b&sysparm_search=kb0013183. Instructions for international entities (not located in the U.S. or its outlying areas): https://www.fsd.gov/fsd-gov/answer.do?sysparm_kbid=dbf8053adb119344d71272131f961946&sysparm_search=KB0013221
SECTION 01 00 00 - GENERAL REQUIREMENTS
01 30 00 ADMIN REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
1. ORDERING PROCEDURES
1.1 General. Ordering procedures will be tailored per task order depending on the circumstances pertinent to each task order scope. These procedures will be determined by the Ordering Contracting Officer in accordance with FAR 16.505. In some cases, the Ordering Contracting Officer may evaluate proposals based on price-only; in other cases, the Ordering Contracting Officer may use other non-price evaluation criteria in addition to price and select the Offeror that presents the best value to the Government. Fair opportunity in accordance with FAR 16.505(b)(1) will be paramount, and the basis for award will be explained in each task order RFP.
Task order proposal requirements will be kept to a minimum as best as possible.
1.2 Site Visits. Offerors attendance at site visits is considered vital to preparation of competitive and cost-effective offers, and to understanding the total results desired by the Government. Failure to attend site visits shall not be used as an excuse for omission or miscalculation in offers, and may be taken into consideration in determining a Contractor’s eligibility to participate in future Task Orders. The Contractors will not be reimbursed for attendance during negotiations, site visits, proposal preparation or other Pre-Task Order award costs. The Ordering Contractor Officer reserves the right to make attendance at site visits mandatory for specific Task Orders and to reject offers by Contractors who have not attended the site visits.
1.3 Proposal Deadlines. Each Task Order RFP will include a stated deadline, by which Contractors shall respond with a proposal to the Ordering Contracting Officer Contractors.
1.4 Negotiations. Task Order proposals will either be accepted as is or negotiated to the mutual agreement of both the Government and the Contractor. In most instances, the Ordering Contracting Officer will intend to evaluate proposals and award a task order without negotiations. Therefore, Offerors should include their best price terms in their initial offer and not assume they will have an opportunity to participate in negotiations and/or be asked to submit a revised proposal. However, the Contracting Officer may determine it necessary after evaluating initial proposals to engage in negotiations and/or other bilateral communications with one or more Offerors. Offerors are reminded, in accordance with FAR 52.215-20, the Contracting Officer may require additional Other than Cost and Pricing Data to support analysis as required to determine a price fair and reasonable in accordance with FAR 15.403-1.
1.5 Task Order Award. Upon conclusion of satisfactory discussions or negotiations (if required), a Task Order will be issued by the Contracting Officer reflecting the negotiated order price and payment terms as outlined in the statement of work or specifications. In any instance where there is failure to reach agreement on price, the Government reserves the right to withdraw the project and have it completed by other means. Task Orders will be issued on DD Form 1155. The Task Order becomes binding when the Contracting Officer signs the Order. The Firm Fixed Price amount for Task Orders shall constitute full compensation to the Contractor for
(1) Furnishing all plant, labor equipment, appliances, and materials; and (2) Performing all operations required to complete the work in conformity with the drawings, specifications and/or statement of work. The Contractor shall include in their proposal costs of all work required by drawings, specifications, and/or statement of work.
1.6 Task Order Award Notifications. The Ordering Contracting Officer will notify all Offerors when a task order award is made.
1.7 Debriefs. Offerors are encouraged to request the Ordering Contracting Officer for a debrief. Debriefs will be authorized in accordance with FAR Part 16.505.
1.8 Task Order Ombudsman. In accordance with FAR Part 16.505 and AFARS 5116.505, the Head of the Contracting Activity has appointed a task and delivery order ombudsman. If the Contractor believes it was not fairly considered for a particular Task Order, the Contractor may present the matter to the Contracting Officer. The Contractor may appeal the explanation or decision of the Contracting Officer to the US Army Corps of Engineers (USACE) Ombudsman. The ombudsman has the authority to review complaints from contractors awarded multiple award contracts that they have not been afforded a fair opportunity to be considered for award of a particular task order. After coordination with the Contracting Officer, and if he/she agrees with the Contractor, the Ombudsman may require that a Contracting Officer take corrective action regarding the complaint. At this time, the USACE Ombudsman is Colonel Douglas S. Lowry (douglas.s.lowrey@usace.army.mil). Offerors may request updated information for the USACE Ombudsman from the Ordering Contracting Officer.
1.9 Notice to Proceed (NTP). NTP will be issued separately after receipt and approval of an acceptable Bank Letter of Guaranty or Bond, if required, and approved submittals as identified per Task Order RFP.
2. PLANS AND SPECIFICATIONS
When applicable, the Government will provide the contractor one copy of the construction drawings and statement of work (with pertinent supplemental specifications) upon issuance of each Task Order. All further reproduction shall be at the Contractor’s expense. The Government will provide these as hard copy or as electronic media, such as e-mail or CD ROM.
3. CONTRACTOR TASK ORDER SUBMITTALS
The Government requires all documentation (i.e., certificates, licenses, resumes, etc.) submitted and made available for verification purposes shall be in the English language in accordance with Local Clause STR
52.000-4043 CORRESPONDENCE IN THE ENGLISH LANGUAGE (ADDITIONAL INFORMATION).
3.1 Contractor’s Project Manager
a. The Contractor shall appoint an English speaking individual to be the Contractor’s Project Manager. The Contractor’s Project Manager shall have a minimum of five (5) years of construction management experience. Verification documentation will be made available to the Government upon request.
b. This individual shall conduct the overall management coordination on this contract and serve as the central point of contact with the Contracting Officer or his/her authorized representative for the performance of all work. An additional English speaking individual must be designated to act for the Project Manager, when work is being performed during the absence of the Project Manager.
c. The Contractor shall provide to the U.S. Government, within seven (7) days of award, the names, addresses, and home phone numbers of the Project Manager and the alternate Contractor personnel with authority to act for the Contractor if the Project Manager cannot be contacted. The Contractor shall also provide the Government, at the Pre-construction Conference for awarded task orders, the names, address, and home phone numbers of the Project Manager’s supervisor.
d. When the Contractor wishes to change authorized Contractor personnel, a ten (10) workday advance written notice of change shall be provided to and approved by the Contracting Officer or his/her representative prior to any change. The Project Manager and/or any alternates designated to act for them, shall have full authority to contractually commit the Contractor for action on matters pertaining to administration of this contract. The Project Manager and his alternate shall be able to understand, speak, and write basic and technical English.
3.2 Submittals, Shop Drawings, and As-Builts
a. The Contractor is responsible for preparation of all shop drawings, submittals, and as-builts for each Task Order when required and as specified per Task Order. All Task Order submittals shall be prepared in accordance with the FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION and Specification Section 01 33 00 requirements and are subject to the COR’s approval.
b. The Contractor shall develop submittals for the Base Contract and shall provide these submittals to the Contracting Officer (KO) for review and approval no later than fifteen (15) calendar days after award of the Base Contract. In the event any of the Base Contract submittals are disapproved by the KO, the Contractor shall revise the disapproved submittal to address all comments and resubmit to the KO within seven (7) days of receipt of comments. Base Contract submittals shall include but are not limited to Safety Plan, Quality Control Plan, and the Bank Letter of Assurance.
c. The Contractor shall update contract submittals and provide to the KO and/or COR, whichever is applicable, for review and approval whenever changes occur or are proposed.
3.3 Quality Control
The Contractor shall submit a Quality Control Plan with each task order. The plan shall adhere to Specification 01 45 00. The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with FAR 52.246-12 INSPECTION OF CONSTRUCTION.
3.4 Safety
a. Safety shall be the sole responsibility of the Contractor. The Contractor shall comply with the Contract
Clause FAR 52.236-13 ACCIDENT PREVENTION and DFARS 252.223-7006 PROHIBITION ON
STORAGE, TREATMENT AND DISPOAL OF TOXIC HAZARDOUS MATERIALS.
b. The Contract shall submit a Safety Plan with each task order to describe procedures and plans for preventing accidents and for preserving the life and health of the public, the Contractor, or Government personnel performing, or in any way coming in contact with the performance of this contract.
c. The Contractor’s Safety Plan shall comply with the latest EM 385-1-1 Appendix A of the U.S. Army Corps of Engineers Safety and Health Requirements Manual and Contract Clause FAR 52.236-13 ACCIDENT PREVENTION. The plan, at a minimum, shall address responsibilities and procedures that all prime and subcontractor personnel shall follow in the areas of fire safety, protective clothing, protective equipment, disposal of waste and contaminated oil, and use electric welders, power equipment, and any other systems necessary to protect the employee.
d. Regularly scheduled safety meetings shall be held by the Contractor on site for all of the Contractor’s supervisors on the project to review past activities, plan for new or changed operations and establish safe working procedures for anticipated hazards. At least one tool box safety meeting shall be conducted weekly by the line supervisor or foreman for all workers. Documentation of safety meetings and attendance shall be submitted to the Government.
3.5 Asbestos Plan
When required by the task order, the Contractor shall submit an Asbestos Plan that demonstrates the Contractor’s ability to perform asbestos abatement. The Plan shall identify how key personnel are to be trained and/or certified and how annual training will be provided and documented. A plan for how the asbestos will be handled when encountered during non-asbestos work (contingency) shall be included. The Plan shall state that the COR will be notified prior to working with asbestos or if previously unidentified asbestos is encountered. If asbestos work is to be performed by a subcontractor, the experience and certification of credentials shall be provided. If the firm will perform the asbestos abatement, the firm’s certified personnel shall be identified and a copy of their latest certification provided.
3.6 Permits and Responsibilities
Permits and Responsibilities are the responsibility of the Contractor as required in Contract Clause FAR 52.236-7 PERMITS AND RESPONSIBILITIES and Specification 00 74 00.
3.7 Schedules
Schedules shall be negotiated and determined per Task Order. Schedules shall be submitted to the Government for acceptance in accordance with Specification Section 01 32 01 or 01 32 16 (if applicable).
Refer to Specification Section 00 71 01 for time extensions for adverse weather.
4. CONTRACTOR’S RESPONSIBILITY
a. The contractor shall be held responsible for any and all damages attributed to the actions of the
Contractor or its subcontractors outside the limits of construction, including drainage structure, electrical or telephone facilities, pavement and other facilities.
b. When required, the Contractor shall lay out their work from Government established base lines and/or bench marks as indicated per Task Order. The Contractor shall furnish at their own expense all stakes, templates, platforms, equipment, tools, material, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades as established per Task Order.
c. The Contractor shall erect and maintain temporary barricades, if required, to limit public access to hazardous areas. Barricades shall be required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Barricades shall be securely placed, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
d. The Contractor shall be responsible for the security of their equipment.
e. Construction debris, waste materials, packaging material and the like shall be removed from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways shall be cleaned away.
Materials resulting from demolition activities which are salvageable shall become the property of the contractor unless otherwise stated in the Task Order. Stored material, whether new or salvaged, shall be neatly stacked.
f. All debris shall be removed and the area restored to its original condition, including top soil and seeding if necessary.
5. CHANGES
Changes shall be determined in accordance with the provisions of Contract Clause FAR 52.243-4
CHANGES.
6. WARRANTY OF CONSTRUCTION – EUROPE
The Contractor warrants that the work is performed in a satisfactory manner and meets industry standards.
The Contractor shall provide an understood warranty of two (2) years for all construction and as applicable in the Contract Clause WARRANTY OF CONSTRUCTION EUROPE. Extended warranties if applicable shall be provided per Task Order.
7. CLOSE OUT
Refer to Specification Section 01 78 00 CLOSEOUT SUBMITTALS. All shop drawings, if required, warranties, extended warranties, test records, inspection certifications, and manufacturer certificates shall be provided to the Contracting Officer. The Contractor shall certify in writing that upon completion of the work and cleanup of the work areas that the site is environmentally clean with no Hazardous, Toxic and Radioactive Wastes (HTRW) contaminates resulting from the Contractor’s operation.
8. PAYMENTS
Payments shall be in accordance with Contract Clauses FAR 52.232-5 Payments Under Fixed-Price Construction Contracts and FAR 52.232-27 Prompt Payment for Construction Contracts. Also see Specification Section 00 74 00.
9. PERFORMANCE OF TASK ORDERS
9.1 In performance of work under this contract, the Contractor shall:
a. At the end of each work week, provide the Contracting Officer’s Representative (COR) or authorized representative with a work schedule for the next week complete with an Activity Hazard Analysis (AHA), listing the Task Orders to be worked and the required trades for the following week. The Contracting Officer’s Representative shall be notified immediately if revisions to the Task Order are necessary during the work week.
b. Arrange with the COR or authorized representative a sequence of procedures, means of access, space for storage or materials and equipment, use of approaches, corridors, and stairways. Since space for storage is limited in work areas, the majority of storage must be outside or at the Contractor’s assigned area.
Only materials to be used for work under this contract may be stored at the assigned area.
c. The buildings and work areas may be occupied during performance of work under this contract. The Contractor shall take particular care in the execution of the work in all computer, mechanical, electrical, and telephone equipment areas. Uninterrupted operations must be maintained in these areas.
10. LIQUIDATED DAMAGES – CONSTRUCTION
The Liquidated Damage rates will be specified in individual Task Orders in accordance with FAR Clause 52.211-12 Liquidated Damages.
11. EVALUATION OF CONTRACTOR PERFORMANCE
In accordance with FAR 42.1502, the Contractor’s performance will be evaluated upon completion of each Task Order. Evaluations may be performed on all Task Orders, regardless of the dollar amount.
12. SPECIFICATIONS
The following specifications are incorporated by reference to this contract and all task orders (as applicable):
00 74 00 Special Conditions (NAU), 08/18 00 74 0102 Time Extensions for Unusually Adverse Weather (NAU), 03/18
00 74 17 Supplemental Conditions for Projects in Italy (NAU), 03/18 01 30 00 General Requirements (NAU), 06/18 01 32 01 Project Schedule (NAU), 03/18 01 32 16 Small Project Progress Schedules (NAU), 03/18 (as applicable) 01 33 00 SubmittalsSubmittal Procedures (NAU), 04/18 01 33 16 Design After Award (NAU), 05/18 01 35 26 Safety and Occupational Health Requirements (NAU), 03/18 01 45 00 Quality Control (NAU), 03/18 01 45 01 Resident Management System Contractor Mode (RMS CM) (NAU), 04/18 01 45 05 Contractor Site Personnel Requirements (NAU), 05/18 (updated at task order level) 01 45 10 Design Quality Control (NAU) 01 78 00 CloseoutsCloseout Submittals (NAU), 06/18 01 78 23 Operations & Maintenance Data, 06/18 EP 310-1-6a Construction Project Signs, 06/06
Department of the Army Manual No. EM 385-1-1 Safety and Health Requirements Manual:
http://www.usace.army.mil/CESO/Pages/Home.aspx
13. ANTITERRORISM/OPERATIONS SECURITY
U.S. Army Europe (USAREUR) requires a Mandatory Antiterrorism/Operations Security Review for this acquisition using the standard language text required US based contactor employees and associated sub-contractor employees to make available and to receive government provide area of responsibility (AOR) specific to the following provision and clauses and not all provisions/contract clauses will apply to this requirement.
Clause 1:
AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
Clause 4:
Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something).
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
Clause 11:
For Contracts Requiring Performance or Delivery in a Foreign Country. All non-local contracting personnel will comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor's compliance with combatant commander and subordinate task force commander policies and directives.