B.08.02.01_Attach_1_Specifications_Binder_Italy_MATOC_AMENDED.pdf

PDF 1 MB Posted

Attached to
FY19 Italy Design-Build (DB) / Design-Bid-Build (DBB) Construction MATOC
Solicitation number
W912GB-19-R-0031
Issued by

About this file

This pre-solicitation notice announces the U.S. Army Corps of Engineers Europe District's intent to issue a multiple award task order contract for design-build and design-bid-build construction services throughout Italy. The contract will have a one-year base period and four one-year options, with a total value not to exceed $49.9 million. The notice requests that interested firms submit qualification documentation by March 22nd to be considered for the restricted plan holders list and pre-qualification process. Firms must have applicable Italian S.O.A. certifications in categories including industrial and other buildings, water and gas pipelines, utility systems, roads and bridges, and environmental protection works. The notice indicates the government will host an optional pre-proposal conference on or around April 8th and issue the formal solicitation with a response deadline no less than 30 days later. Construction services will include repair, maintenance, renovation and new construction work. Task orders will be located primarily in Vicenza, Livorno and Aviano but may occur throughout Italy.

B.08.02.01 Attach 1 Specifications Binder Italy MATOC AMENDED

View the file

Other files

File Type Posted
D.03.05_FBO_MATOC_AWARD_SYNOPSIS.pdf PDF
B.08.02.14_Attach_14_Phase_TWO_Price_Proposal_Form_-_UPDATED.xlsx XLSX spreadsheet
SEED__1_RFP_Letter_Amendment.pdf PDF
SEED__3_RFP_Letter_Amendment.pdf PDF
B.08.03.6_Amendment_0006_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.03.11_Amendment_0011_FY19_Italy_DB_DBB_MATOC.pdf PDF
SEED__1_Att_10_Flow_Tests_Documents.pdf PDF
B.08.02.12_Attach_12_-_SEED_Project__2_Package_REVISED_(As_of_Amendment_0010).pdf PDF
B.08.03.10_Amendment_0010_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.03.9_Amendment_0009_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.02.12_Attach_12_-_SEED_Project__2_Package_REVISED_(As_of_Amendment_0008).pdf PDF
B.08.02.11_Attach_11_-_SEED_Project__1_Package_REVISED_(As_of_Amendment_0008).pdf PDF
B.08.02.13_Attach_13_-_SEED_Project__3_Package_REVISED_(As_of_Amendment_0008).pdf PDF
B.08.03.8_Amendment_0008_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.02.01_Attach_1_Specifications_Binder_Italy_MATOC_REVISED_06.21.2019.pdf PDF
B.08.03.7_Amendment_0007_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.02.14_Attach_14_Phase_TWO_Price_Proposal_Form.xlsx XLSX spreadsheet
B.08.02.11_Attach_11_-_SEED_Project__1_Package.pdf PDF
B.08.02_Solicitation_FY19_Italy_DB_DBB_MATOC_2019.04.07_FINAL.pdf PDF
B.08.02.12_Attach_12_-_SEED_Project__2_Package.pdf PDF
B.08.02.13_Attach_13_-_SEED_Project__3_Package.pdf PDF
B.08.03.4_Amendment_0004_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.03.3_Amendment_0003_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.02.02_Attach_2_ExpInfoSheet_19R0031_REVISED.docx DOCX document
B.08.02.05_Attach_5_BLA_Template_19R0031_REVISED.docx DOCX document
A.08.02_MATOC_PPC_Slides_Italy_2019.04.17_FINAL.pdf PDF
B.08.03.1_Amendment_0002_FY19_Italy_DB_DBB_MATOC.pdf PDF
B.08.02.08_Attach_8_Preproposal_Conf_Attendee_Info_Sheet_CONSOLIDATED.pdf PDF
B.08.03_Solicitation_Amendment_0001.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 74 00

SPECIAL CONDITIONS (NAU)

03/19

PART 1 GENERAL

1.1 PAYMENT

1.2 DEFINITIONS

1.3 ORDER OF PRECEDENCE

1.4 DOCUMENTS IN MULTIPLE LANGUAGES

1.5 COMMUNICATION IN ENGLISH

1.5.1 English Speaking Representative

1.5.2 Correspondence And Documentation

1.5.3 Translations for Disputes

1.5.4 Additional Language Requirements

1.5.5 Language Fluency

1.6 PERMITS

1.6.1 General Requirements

1.6.2 Permits and Notifications

1.6.3 Final Acceptance

1.7 THIRD PARTY INSPECTION REQUIREMENTS

1.8 CONTRACTOR WORKFORCE

1.8.1 Foreign Employees

1.9 CONTRACTOR OBLIGATION

1.10 SUBMITTALS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 SITE ACCESS

3.1.1 General Access Requirements

3.1.2 Work on Military Installations (General)

3.1.3 Access to Operational Areas

3.2 CONTRACT EXECUTION IN THE HOST NATION

3.2.1 Prime Contractor Responsibility for Subcontractor Disputes

3.2.2 Access to Areas Under Military Control

3.2.3 Contractor Responsibility

3.2.4 Archaeological and Historical Sites

3.3 CONTRACTOR LIAISON AND COMMUNICATION WITH HOST GOVERNMENTS

3.4 RESTRICTIONS ON PAYMENT SUBMISSIONS

-- End of Section Table of Contents --

DOCUMENT 00 74 00 Page 1

SECTION 00 74 00

SPECIAL CONDITIONS (NAU)

03/19

PART 1 GENERAL

1.1 PAYMENT

Separate payment will not be made for compliance with this or any other Division 00 or Division 01 specification. All costs associated with these specifications shall be included in the applicable unit prices or lump-sum prices contained in the Bidding Schedule.

1.2 DEFINITIONS

The following terms are used throughout the contract documents. Except where a definition is provided with the specific occurrence, the following definitions apply to these terms.

a. Betterment. Any deliverable provided by an offeror prior to award or by the contractor after award which conforms to and exceeds the provisions of the contact. A betterment provided prior to award becomes binding upon award of the contract. After award, a betterment becomes a binding contract requirement upon acceptance by the Government of the document proposing the betterment, whether specifically identified as such or not.

b. Host Nation (HN). The country where the construction work is being performed.

c. Host Nation Language. The Official Language recognized by the national government of the country where the work is performed. If no Official Language has been designated, or where multiple Official Languages have been designated, it is the predominant language of the Government agency responsible for operation and maintenance of the facility or product constructed under this contract.

1.3 ORDER OF PRECEDENCE

In the event of conflict or inconsistency between any of the provisions of this contract, precedence shall be given in the following order:

(1) Clause 52.236-21 Specifications and Drawings (Alt I)

(2) Any portion of a contractor provided deliverable (including, but not limited to, plans, specifications, engineering studies and analyses, shop drawings, equipment installation drawings) that both conforms to or exceeds the provisions of the contract (Betterments). All deliverables must conform to all provisions of the contract, in the order of precedence herein.

(3) Any portions of the accepted proposal that both conform to and exceed the provisions of the solicitation (Betterments).

(4) Contract Sections starting with "00", including these Special Conditions

DOCUMENT 00 74 00 Page 2

(5) Section 01 00 00, including Section 01 10 10 Statement of Work (Summary of Work or Scope of Work)

(6) All Other Specification Sections

(7) Special Requirements (SRs) or Special Technical Requirements (STRs)

(8) Referenced Technical Standards (such as NFPA, UFC, ASTM, DIN)

(9) Referenced Design Guides or other non-technical standards

(10) Drawings

(11) All other technical attachments to the contract, including Host Nation Technical Requirements, Standards, and References.

Amendments take precedence over all items listed above to the extent noted above and in the referenced clauses. For instance an amendment to a Drawing takes precedence over the original drawing but not over the Special Technical Requirements.

Design and product requirements, including criteria are minimum requisites.

In case of conflicting requirements within documents of the same order of precedence, the more stringent criteria governs. A conflict does NOT exist when both requirements can be met; in these instances the contractor shall comply with both requirements.

1.4 DOCUMENTS IN MULTIPLE LANGUAGES

If this contract includes documents in English and additional languages, the English language version shall govern over all other languages. In the event contract documents contain translations into non-English languages, the translation is provided solely for convenience.

For all purposes, the English language version shall be the governing instrument and understanding of the parties. In the event of any conflict between the English language version and any translation into any other language, the English language version shall govern and control.

1.5 COMMUNICATION IN ENGLISH

1.5.1 English Speaking Representative

All personnel required to communicate with the government on a recurring basis, including but not limited to Project Managers, Site Safety and Health Officers (SSHO), Superintendents, and Quality Control personnel shall be capable of explaining the work operations and receiving instructions in the English language whenever work is ongoing. This includes the ability to speak, read, write, and understand the directions of the Contracting Officer or their designated representatives when conducted in English.

1.5.2 Correspondence And Documentation

In addition to clause 252.225-7041, it shall be the responsibility of the Contractor to prepare all documents related to this contract, to include, change proposals, shop drawings, submittals, quality control reports, computations, and all correspondence, in the English language or with a

DOCUMENT 00 74 00 Page 3 translation of the original document into English.

1.5.3 Translations for Disputes

All documents originally produced in a language other than English submitted either as (a) part of a Request for Equitable Adjustment (REA),

(b) part of a claim under the Disputes clause or (c) as part of litigation, including actions at the ASBCA or actions in U.S. courts, shall be translated into English by a person who is recognized in accordance with the appropriate authorities to produce official/certified translations, and said translations shall be so certified.

This requirement applies to any document that would normally be considered to be within the scope of discovery in an ASBCA or court proceeding concerning the dispute. The term 'documents' includes electronic documents including but not limited to e-mail and includes documents generated by subcontractors or suppliers. In the event a dispute results in litigation, including actions at the ASBCA or actions in U.S. courts, the contractor will be responsible for providing translations of any documents that are within the scope of a discovery request filed by the U.S. Government and for providing certified translations upon request by the U.S. Government.

The contractor shall bear sole responsibility for any costs associated with translation, as well as with any errors, omissions, or discrepancies between the original and English version of a document. In the event of any difference between the English version and any other version in any language, the English version shall govern.

1.5.4 Additional Language Requirements

When any worker on site at any level (contractor, subcontractor, supplier, etc.) cannot communicate in English or a language spoken by the Contractor's key personnel, the contractor shall ensure that, at all times that person is on site, at least one person is present who can communicate to that worker in their native language. Failure to comply with this requirement will be considered a life-safety issue.

1.5.5 Language Fluency

Personnel required to communicate with the Government should be competent in the English language at a minimum level B2 of the Common European Framework of Reference for Languages: Learning, Teaching, Assessment.

The Contracting Officer shall have the right to determine without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer.

1.6 PERMITS

1.6.1 General Requirements

All documents required to be prepared in accordance with this paragraph (and sub-paragraphs) shall be prepared by the Contractor in the language(s) required by the HN. An English language translation prepared by a person with the appropriate qualifications shall be provided to the Contracting Officer concurrently. Submission of documentation shall be in accordance with HN requirements; either directly to the appropriate HN authority or through the Contracting Officer when the contractor is not permitted to

DOCUMENT 00 74 00 Page 4 provide the documents directly.

When U. S. Government signature is required, the Contractor shall obtain approval and signatures as needed for HN permitting and notification process from the COR. The contractor shall provide the required documentation sufficiently in advance of the date any approval or permit is required. The contractor is solely responsible for determining the amount of time the HN authorities will require to review and process the documentation. No additional time will be granted for delayed approval or rejection of contractor prepared documents.

A copy of all Approved Permits shall be furnished to the COR prior to the start of construction work.

1.6.2 Permits and Notifications

The contractor shall obtain all permits not required to be requested or obtained by the U.S. Government in accordance with FAR 52.236-7, Permits and Responsibilities. As incorporated herein, the requirements of FAR clause 52.236-7 extend to licenses, permits, and compliance with applicable Host Nation (HN) and local laws, codes, and regulations in connection with the prosecution of the work. The contractor is responsible for identifying and providing a comprehensive List of Required HN Permits.

Where the U.S. Government is required to obtain permits in accordance with Host Nation (HN) agreements, the Government will notify the contractor and the contractor shall prepare all necessary documentation. This includes providing documentation to show compliance with permit requirements.

1.6.3 Final Acceptance

Where final acceptance by the HN is required, the Contractor will coordinate with the HN Government, in conjunction with the U.S. Government, to determine the requirements for proper final inspection by the HN and provide any information required for proper final acceptance. The contractor shall incorporate the requirements for final acceptance into the design and construction of the project.

1.7 THIRD PARTY INSPECTION REQUIREMENTS

If, as a condition of any permit or to comply with HN laws, codes, and regulations, inspections by third parties are required, the contractor shall be responsible for ensuring those inspections are conducted and documented. The contractor shall be solely responsible for any and all costs associated with these inspections, including the actual inspection and any additional work or rework identified as part of the inspection process, to include the replacement of any materials or equipment determined to be not in compliance by the inspector.

No adjustment in the contract price or duration will be made based on events arising from these inspections, unless a delay occurs which is completely beyond the control and without the fault of the contractor, in which case an adjustment in the contract duration may be made under the DEFAULTS clause of the contract. No adjustment in price will be made should this occur. The contractor is solely responsible for identifying the period(s) of delay and substantiating an impact to the completion date.

These requirements are in addition to and separate from any requirements for Third Party Inspection Services identified in Section 01 10 00

DOCUMENT 00 74 00 Page 5

Statement of Work.

1.8 CONTRACTOR WORKFORCE

1.8.1 Foreign Employees

The contractor may arrange, through the appropriate Host Nation Government (HN) offices, to bring into the country nationals of third countries (TCN) having diplomatic relations with the host nation for purposes of employment in carrying out this contract work.

Contractors shall be responsible for timely and complete submittal of the necessary information and forms directly to the appropriate HN agency for the required customs clearances, passports, visas, licenses, or permits.

The contractor shall be responsible for the sponsorship of its employees and their dependents and shall process said permits directly with the appropriate HN agency. Offerors are advised that the HN reserves the right to limit access to designated security areas and refuse entry or employment of specified individuals, or to require their departure from the country, in accordance with national or local law and practice.

The U.S. Government does not have influence over the TCN issue and does not warrant the availability of TCN labor. The Contractor is cautioned to review any additional information specified elsewhere in this contract for more stringent requirements or specific restrictions or limitations on the use of foreign workers.

1.9 CONTRACTOR OBLIGATION

Contractors shall be responsible for timely and complete submittal of the necessary information and forms directly to the appropriate HN agencies for any and all required customs clearances, passports, visas, licenses, or permits.

1.10 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Required HN Permits; D Permits And Notifications Approved Permits

SD-11 Closeout Submittals

Final Acceptance

PART 2 PRODUCTS

Not Used.

DOCUMENT 00 74 00 Page 6

PART 3 EXECUTION

3.1 SITE ACCESS

3.1.1 General Access Requirements

The Contractor shall be responsible for obtaining access and adhering to all guidelines established by the local authorities for access to the work site and will be responsible for the daily access of their personnel and subcontractor workers.

The Contractor is cautioned to review any additional security guidelines specified elsewhere in this contract for more stringent requirements or specific access conditions.

3.1.2 Work on Military Installations (General)

When work is performed on a military installation, every employee of the prime contractor, all subcontractor employees, and all material suppliers' employees, who require access to the installation for any reason and for any length of time will be required to obtain an installation/base access pass.

Individuals who will be performing work onsite for five or more days in total - even if non-consecutively - shall apply for installation/base pass and may not be "signed in" or otherwise presented as a "visitor". Failure to comply with this requirement may result in the loss of sign-in privileges and/or loss of installation access.

3.1.3 Access to Operational Areas

Contractor personnel are expressly prohibited and shall be restricted from entering operational buildings or areas without the specific authorization of the Contracting Officer. To perform work, where "security escorts" are required for access to a facility, the Contractor shall coordinate with the Contracting Officer for access to such facilities.

3.2 CONTRACT EXECUTION IN THE HOST NATION

3.2.1 Prime Contractor Responsibility for Subcontractor Disputes

The Contractor agrees to indemnify and save harmless the United States Government against all claims and suits of whatsoever nature arising under or incidental to performance of this contract by any subcontractor against the United States Government.

The Contractor further agrees to waive his rights to bring suit or other legal action against the United States Government, except as provided in the "Disputes" clause of this contract and in the United States Federal Statutes.

3.2.2 Access to Areas Under Military Control

The laws of the Host Nation (HN) may prohibit access to certain areas of the country which are under military control. Clearances to access these areas must be obtained from the HN. It is understood that areas to which rights of entry are provided by the HN are to be used only for work carried out under the contract and no destruction or damages shall be caused, except through normal usage, without concurrence of the HN.

DOCUMENT 00 74 00 Page 7

3.2.3 Contractor Responsibility

The Contractor shall be responsible for providing the necessary information (such as but not limited to, names of personnel, type, and amounts of equipment, dates and length of time required at the site, and purpose of entering the HN) to the appropriate HN representatives, both civilian and military.

The following items are the sole responsibility of the Contractor to investigate, estimate as to cost, and assume the risk, as normally encountered by Contractors. The Contractor shall be responsible for determining the effect of the following on his own cost of performance of the contract and for including sufficient amount in the contract price:

a. Official language and type of accounts required to satisfy the officials of the Local Government.

b. Entry and exit visas, residence permits, and residence laws applicable to aliens. This includes any special requirements of the Host Government, including those required by local Labor Offices, which the Contractor may have to fulfill before an application for visas will be accepted.

c. Passports, health and immunization certificates, and quarantine clearance.

d. Compliance with local labor and insurance laws, including payment of employer's share of contribution, collecting balance from employee and paying into insurance funds.

e. Strikes, demonstrations and work stoppage.

f. Collection through withholding and payment to local Government, of any HN income tax on employees subject to tax.

g. Arranging to perform work in the HN, to import personnel, to employ non-indigenous labor, to receive payments and to remove such funds from the country.

h. Operating under local laws, practices, customs and controls, and with local unions, in connection with hiring and firing, mandatory wage scales, vacation pay, severance pay, overtime, holiday pay, days of rest or other non-work days, legal notice or pay in lieu thereof for dismissal of employees, slowdown and curtailed schedules during religious holidays, and ratio of local labor employed in comparison to others.

i. Possibility of claims in local bureaus, litigation in local courts, or attachment of local bank accounts.

j. Compliance with workmen's compensation laws and contributions into funds. Provisions of necessary medical service for Contractor employees.

k. Special license required by the local Government for setting up and operating any manufacturing plant in the HN, e.g. concrete batching, precast concrete, concrete blocks, etc.

l. Sales within the HN of Contractor-owned materials, and equipment.

DOCUMENT 00 74 00 Page 8

m. Special licenses for physicians, mechanics, tradesmen, drivers, etc.

n. Identification and/or registration with local police of imported personnel.

o. Stamp tax on documents, payments and payrolls.

p. Base passes for permanent staff, day laborers, motor vehicles, etc.

q. Compliance with all customs and import rules, regulations and restrictions, including, but not limited to, local purchase requirements.

3.2.4 Archaeological and Historical Sites

The contractor shall be aware of all archeological laws and work accordingly including stopping work in the vicinity and reporting should archeological items be uncovered during the course of this contract.

3.3 CONTRACTOR LIAISON AND COMMUNICATION WITH HOST GOVERNMENTS

All communication by the Contractor with all officials, representatives and/or offices of the Host Government (at any level) in all matters pertaining to the design or construction of this contract, shall be through and in full liaison with the Contracting Officer. This does not relinquish Contractor responsibility for obtaining routine items to conduct day-to-day business, such as visas, permits, and custom clearances.

The contractor is further reminded that only the Contracting Officer or their authorized representative may give the contractor direction in regards to contract interpretation. Only a Contracting Officer or Administrative Contracting Officer may modify the contract terms or conditions: directions received from Host Nation Government officials do not constitute direction to proceed in accordance with the Change clause and will not be considered a change to the contract without prior specific direction from the Contracting Officer.

3.4 RESTRICTIONS ON PAYMENT SUBMISSIONS

Reference is made to clause 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS. Due to financial cutoff periods, the Government will not accept any progress payments submitted between the last 5 work days of a given month and the first 3 work days of the following calendar month (second month). Invoices submitted during this time will not be considered "received" as described in the reference clause until the 4th working day of the second month.

-- End of Section --

DOCUMENT 00 74 00 Page 9

SECTION 00 74 02

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (NAU)

03/19

PART 1 GENERAL

1.1 DETERMINATION OF UNUSUALLY SEVERE WEATHER

1.2 MINIMIZING WEATHER IMPACTS

1.3 INCORPORATION IN PROJECT SCHEDULE

1.4 WEATHER CONDITIONS AT THE PROJECT SITE(S)

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 REPORTING

3.2 OCCURRENCE OF ACTUAL DELAY

3.3 CALCULATION OF DELAY AND CONVERSION TO CALENDAR DAYS

3.4 ISSUANCE OF MODIFICATION

3.5 DELAYS OUTSIDE STANDARD WORK DAYS

DOCUMENT 00 74 02 Page 1

SECTION 00 74 02

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (NAU)

03/19

PART 1 GENERAL

1.1 DETERMINATION OF UNUSUALLY SEVERE WEATHER

This specification prescribes the procedures to be used on this contract for determination of time extensions for "unusually severe weather" in accordance with the contract clause 52.249-10 "Default: (Fixed Price Construction)".

In order for the Contracting Officer to award a time extension for "unusually severe weather" under this clause, all of the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must exceed the weather which could reasonably be anticipated based on a minimum of 25 years of historical weather data.

b. The weather must actually cause a delay to the completion of the project or any specified contractual milestone beyond that which would reasonably be anticipated based on the contractors means and methods.

The delay must result from events which are beyond the control and without the fault or negligence of the Contractor.

c. The delay must occur during the contractual performance period.

1.2 MINIMIZING WEATHER IMPACTS

The contractor is responsible for identifying and implementing the means and methods to minimize the overall impact of weather during the contract period.

The means and methods and sequencing of work will impact the extent to which the work is sensitive to or may be impacted by the weather.

Separate payment will not be made for any costs associated with mitigating the impacts of weather.

1.3 INCORPORATION IN PROJECT SCHEDULE

The Contractor's progress schedule must reflect reasonably anticipatable weather in weather dependent activities. The Contractor shall be solely responsible for identifying anticipated weather days based on the activities scheduled during a given time period and the means and methods of executing the work.

Refer to Section 01 32 01 PROJECT SCHEDULE (NAU) for the procedures for incorporating these weather days into the schedule.

1.4 WEATHER CONDITIONS AT THE PROJECT SITE(S)

The Government makes no representation of the actual weather conditions to be expected at the site. No inference or conclusion shall be made

DOCUMENT 00 74 02 Page 2 regarding the actual weather conditions or the actual amount of weather delays based on any information included in the contract documents.

The Contractor shall, prior to submitting a proposal or offer, be solely responsible for determining the actual weather conditions prevalent at the project site or sites and accounting for this information in their proposal or offer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 REPORTING

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract performance period, the contractor will record on the CQC report the occurrence of weather and resultant impact to normally scheduled work. Impacted activities shall be identified by name and activity id on the CQC report.

When the use of RMS-CM (Section 01 45 01 RESIDENT MANAGEMENT SYSTEM - CONTRACTOR MODE) is required by the contract, weather shall be reported on the QC Report in RMS-CM and tracked therein.

3.2 OCCURRENCE OF ACTUAL DELAY

To be considered a day of actual weather delay, progress on critical path activities must be less than 50 percent of the progress scheduled to occur on that day, and the progress must be impacted due solely to the weather.

The delay must be recorded in accordance with paragraph 3.1: failure to provide this information at the time of the preparation of the CQC report will be considered an acknowledgement that no delay existed, however reporting on the CQC report will not automatically be considered concurrence by the Government that delay occurred and it was due solely to the weather.

Failure to make adequate preparations for weather or to adequately protect the work from reasonably anticipatable weather will not be considered an impact due solely to weather.

3.3 CALCULATION OF DELAY AND CONVERSION TO CALENDAR DAYS

Any adjustment in the contract period of performance resulting from unusually severe weather will be based upon the weather over a minimum period of six months.

The contractor shall be solely responsible for providing documentation to substantiate that the actual weather was "unusually severe" based on a minimum of 25 years of historical weather data, the critical path was impacted as a result, and the actual impact to the critical path could not have been prevented through reasonably prudent measures.

As part of this documentation, the contractor must substantiate the reasonableness of anticipated weather days included in the schedule as discussed in paragraph 1.3 INCORPORATION IN PROJECT SCHEDULE. Failure to substantiate the reasonableness of the anticipated weather days may result

DOCUMENT 00 74 02 Page 3 in a determination that the contractor failed to adequately plan and execute the work in a manner consistent with the requirements of the contract, making the delay within their control.

Additionally, the contractor shall provide a detailed listing of all weather days occurring from the Notice to Proceed through the date of the request and show a cumulative net impact to the performance period exceeding that which could be anticipated based on the aforementioned 25 years of historical weather data.

Any calculation performed within RMS-CM under the "Weather Delays" screens of the QA/QC Module shall not serve as the basis for determining the amount of adjustment required.

3.4 ISSUANCE OF MODIFICATION

If the contractor can substantiate an impact to the completion date of the project based on actual "unusually severe" weather as described herein, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause 52.249-10 entitled "Default (Fixed Price Construction)".

3.5 DELAYS OUTSIDE STANDARD WORK DAYS

Weather delays occurring prior to Notice to Proceed, during non-working days, and after the required completion date are not excusable under the Defaults clause.

When the contract performance period, or any extension thereof, has passed, no extensions for unusually severe weather will be granted. This applies as well to any interim milestone or completion date.

DOCUMENT 00 74 02 Page 4

DOCUMENT 00 74 17

SUPPLEMENTAL CONDITIONS FOR PROJECTS IN ITALY (NAU)

03/19

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SUBMITTAL OF PROOF OF QUALIFICATIONS AND EXPERIENCE

1.4 FINAL GOVERNING STANDARDS (FGS)

1.5 CERTIFICATION OF COMPLIANCE WITH ITALIAN LAWS

1.5.1 Certification

1.5.2 Static Load and Final Testing

1.5.3 Other Tests

1.6 CULTURAL RESOURCES

1.7 ITALIAN SAFETY LAW COMPLIANCE

1.7.1 Required Compliance With Italian Law 81/2008 And Amendments

1.7.2 Requirements Prior to Beginning Construction

1.7.3 Construction Safety Coordinator (Coordinatore per la

Progettazione)

1.7.4 Responsibility for Delay

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 IMPLEMENTATION OF LAW 81/2008

3.1.1 Preliminary Notification (Notifica Preliminare)

3.1.2 Planning (Pre-Construction) Phase

3.1.3 Construction Phase

DOCUMENT 00 74 17 Page 1

DOCUMENT 00 74 17

SUPPLEMENTAL CONDITIONS FOR PROJECTS IN ITALY (NAU)

03/19

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ITALIAN LAWS AND DECREES (D.M.)

LAW No. 1086 (May 11, 1971) Norms for Works in Reinforced Concrete and Steel and Application Instructions

Law No. 373 (April 30, 1976) Norms for the containment of energy consumption for thermal uses in buildings.

Law No. 46 (March 5, 1990) Safety Norms for Technological Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Technical And Professional Capabilities; G

Preliminary Notification (Notifica Preliminare)

Safety And Coordination Plan (Il Piano Di Sicurezza E Di Coordinamento)

Operational Safety Plan (Piano Operativo Di Sicurezza)

SD-11 Closeout Submittals

Certificate of compliance for all contract work; G

Certified credentials of proposed testing personnel; G

Certification of the static load tests results; G

Certification of actual testing personnel; G

Certificate of conformity for electrical system; G

DOCUMENT 00 74 17 Page 2

Certificate of compliance for heating system; G

Certificate of compliance for fire prevention system; G

Certificate for elevator system test(s); G

1.3 SUBMITTAL OF PROOF OF QUALIFICATIONS AND EXPERIENCE

Where qualifications or experience requirements are set forth in the specifications with respect to equipment and equipment installers, written proof of such qualifications or experience must be provided within thirty

(30) calendar days after Contract award, and before placing any order for such equipment or before dispatching equipment installers to the project site.

1.4 FINAL GOVERNING STANDARDS (FGS)

Final Governing Standards (FGS) for environmental protection at DOD installations and facilities in Italy went into effect June 1994. These standards were developed by comparing and adopting the more protective requirements of the Overseas Environmental Baseline Guidance Document (OEBGD), European Union and national, regional, and local environmental laws and regulations. The FGS are applicable to work under this contract.

1.5 CERTIFICATION OF COMPLIANCE WITH ITALIAN LAWS

1.5.1 Certification

As a condition of final acceptance of the work, the Contractor shall submit to the Contracting Officer a certificate of compliance for all contract work certifying that the work complies with Italian Law No. 46 and that the provided work is adequate and safe for the designated use. The certification shall be made by the responsible technician of the installation firm who shall have been regularly registered on the Installation National Professional Rolls of Italy for at least the last three years.

1.5.2 Static Load and Final Testing

The Contractor shall comply with the pertinent articles of Italian LAW No. 1086. Articles pertaining to notification and participation by civil authorities are not applicable.

The Contractor shall be fully responsible for construction, supervision, static load tests, and final testing, and for all costs associated with this procedure and specifically follow Article 7 of Italian LAW No. 1086 in performing the test. Any fees for these tests shall be in accordance with Italian Professional Law No. 143 of 2 March 1949 as amended.

Article 2 of Italian LAW No. 1086 requires the static load tests to be performed under the supervision of an engineer or architect registered on the National Professional Verifier Rolls of Italy.

Since GENIODIFE intends to participate in static load and final testing, the Contractor shall notify the Contracting Officer at least 21 calendar days prior to any static load or final test to enable the Contracting Officer to notify GENIODIFE.

DOCUMENT 00 74 17 Page 3

Prior to performing the tests, submit to the Contracting Officer the names and certified credentials of proposed testing personnel, engineer(s) or architects(s) they propose to perform the static load testing.

Upon completion of the tests, the Contractor shall submit to the Contracting Officer two original certification of the static load tests results of the static load tests together with a certification of actual testing personnel stating that each test was performed by the same engineer(s) or architects(s) whose certified credentials were previously submitted. The Contracting Officer will submit one original certification to GENIODIFE.

1.5.3 Other Tests

In addition to the certifications listed above, the Contractor shall provide with all other certifications and testing required by Italian Law.

The Contractor is also responsible for all permits required by Italian Law (See Contract Clause FAR 52.236-7, "Permits and Responsibilities". The Contractor shall submit to the Contracting Officer two originals of each certification required by Italian Law. Such certifications may include but not be limited by the following as applicable to the project:

a. Certificate of conformity for electrical system in accordance with Italian Law No. 46. Include a separate specific certificate of compliance for each electrical panel in accordance with Italian Law No. 46.

b. Certificate of compliance for heating system above 100,000 Kal/hr in accordance with Italian Law No. 373.

c. Certificate of compliance for fire prevention system in accordance with DM 16 February 1982 and UFC 3-600-01.

d. Certificate for elevator system test(s) in accordance with Italian Law 1415 of 24 October 1942.

1.6 CULTURAL RESOURCES

Cultural resources such as archaeological remains or villa remains may be uncovered during construction excavation operations. If during excavations, suspected cultural remains are found, excavation operations shall immediately cease and contractor shall notify the Contracting Officer.

1.7 ITALIAN SAFETY LAW COMPLIANCE

The requirements defined herein are in addition to those identified in Section 01 35 26 SAFETY REQUIREMENTS (NAU).

1.7.1 Required Compliance With Italian Law 81/2008 And Amendments

The contractor is responsible for conformance with the requirements of Italian law, including Law 81/2008, as amended, in effect at the time of award of the project. The contractor shall complete and provide any information in a timely manner when requested by the Government to carry out its responsibilities under Law 81/2008.

The Government will provide the contractor with a partial design or a scope of work. The contractor will be responsible for fully preparing any and all

DOCUMENT 00 74 17 Page 4 documents and fulfilling all conditions related to Italian safety legal requirements mandated for the planning and design phase of the project, even if the contractor is not furnishing any architectural-engineering services under the contract.

The contractor is responsible for completing and providing any information in a timely manner when requested by the Government to carry out its responsibilities under Law 81/2008

1.7.2 Requirements Prior to Beginning Construction

The contractor is responsible for demonstrating its technical and professional capabilities and to submit this documentation to the Contracting Officer Representative (COR) prior to receiving clearance to begin Construction, pursuant to Article 89 of Law 81/2008. This includes the documentation required by Article 90, paragraph 9b and Attachment XVII of Law No. 81/2008. The contractor is responsible for verifying the technical and professional capabilities of all subcontractors in accordance with Law 81/2008.

The contractor shall plan the works to allow for at least 45 calendar days review and approval of required plans, provided no corrections are required. If corrections are required, the contractor shall make the corrections and provide any additional documents or resubmittals.

1.7.3 Construction Safety Coordinator (Coordinatore per la

Progettazione)

The Government will provide the name of the construction safety coordinator (coordinatore per la progettazione) to the contractor after award of the contract or task order. This coordinator shall perform the duties specified in law 81/2008 during the construction phase of work.

No construction shall begin until all the appropriate plans have been submitted, reviewed, and accepted; and the coordinatore per la progettazione has confirmed all requirements of Italian safety laws have been met

1.7.4 Responsibility for Delay

Any delays and/or damages to the Contractor due to delays resulting from erroneous, incorrect, or inadequate information submitted become the sole responsibility of the Contractor.

Under no circumstance shall any direction from the coordinatore per la progettazione be subject to a claim or change to the contract

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 IMPLEMENTATION OF LAW 81/2008

3.1.1 Preliminary Notification (Notifica Preliminare)

The Government will provide a draft copy of the Preliminary Notification (Notifica Preliminare) to the contractor. The contractor shall complete the

DOCUMENT 00 74 17 Page 5 information on the form as indicated by the Government and return the form to the Government. The Government will coordinate completion of this document and provide through the local installation representatives to the appropriate host nation authorities (Italian Base Commander) before Construction may begin.

3.1.2 Planning (Pre-Construction) Phase

The contractor is appointed and considered to be the Works Manager (Il Responsabile Dei Lavori) for all phases of work prior to the physical performance of the construction works, even if the contractor performs no other architectural-engineering services. The contractor shall perform and complete any safety requirements mandated under Italian safety laws prior to the Execution phase of the project. This includes the requirement to:

a. Designate a qualified safety coordinator (coordinatore per la progettazione). The coordinator shall be qualified in accordance with Italian Law, meet all minimum training and experience requirements, and perform all duties required under Italian laws.

b. Prepare a Safety and Coordination Plan (Il Piano Di Sicurezza E Di Coordinamento) (PSC) meeting the requirements of the law.

c. Prepare the Operational Safety Plan (Piano Operativo Di Sicurezza))(POS) for construction.

The contractor shall be responsible for directly coordinating with the appropriate authorities for any necessary approvals. In addition, the Government will provide the PSC and the POS to the construction safety coordinator (coordinatore per l’esecuzione) for review and comment. They will coordinate directly with the contractor for any necessary corrections and implementation of the plans.

3.1.3 Construction Phase

During construction, the contractor shall comply with all aspects of Law 81, including and not limited to Articles 89 and 97, oversee safety at the site and the application and regulation of the POS, and comply with all directions and instructions of the coordinatore per l’esecuzione.

The contractor shall take direction from the coordinatore per l’esecuzione during the construction phase regarding inspections, implementation, integration, and updating of the PSC and POS during progress of the work.

-- End of Document --

DOCUMENT 00 74 17 Page 6

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

GENERAL REQUIREMENTS (NAU)

03/19

PART 1 GENERAL

1.1 PURPOSE

1.2 DESIGN-BUILD LANGUAGE

1.3 SUBMITTALS

1.4 DEFINITIONS

1.5 NO WAIVER BY GOVERNMENT

1.6 PROPRIETARY NAMES

1.7 PUBLIC RELEASE OF INFORMATION

1.7.1 Prohibition

1.7.2 Subcontracts and Purchase Orders

1.8 PERSONNEL AND SUBCONTRACTORS

1.8.1 Removal for Non-Compliance

1.8.2 Substitution and Replacement

1.8.3 Qualifications

1.8.4 Employment

1.9 REFERENCES

1.10 REFERENCED STANDARDS

1.10.1 Version and Date of Standard

1.10.2 Host Nation Standards

1.11 PRECONSTRUCTION CONFERENCE

1.12 PARTNERING

1.12.1 Informal Partnering

1.12.2 Formal Partnering

1.13 ELECTRONIC MAIL (E-MAIL) ADDRESS

1.14 ELECTRONIC CORRESPONDENCE

1.15 HOURS OF WORK

1.15.1 Normal Work Hours

1.15.2 Work Outside of Normal Hours

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 PHOTOGRAPHIC DOCUMENTATION

3.2 MOBILIZATION PLAN

3.3 PROJECT SIGN

3.4 TRAFFIC CONTROL

3.4.1 Haul Routes

3.4.2 Road Closures

3.5 CONTRACTOR SITE FACILITIES

3.5.1 Contractor Offices

3.5.1.1 Site Facilities - Other Than JOC Projects

3.5.1.2 Site Facilities - JOC Projects

3.5.2 Construction Fence/Screening

3.5.3 Maintenance of Construction Site

3.5.4 Storage Areas

SECTION 01 30 00 Page 1

3.5.5 Physical Security

3.5.6 Washing of Vehicles

3.5.7 Restoration of Construction Site

3.6 ENVIRONMENTAL PROTECTION

3.6.1 Environmental Protection Plan

3.6.2 Protection of Land Resources

3.6.3 Protection of Water Resources

3.6.4 Dust Control

3.7 EXCLUSIONS

3.7.1 Prohibited Materials

3.7.2 Hazardous Materials

3.7.3 Explosive Materials

3.7.4 Burning

3.8 PROTECTIVE MEASURES

3.9 UTILITY OUTAGES

3.10 TEMPORARY UTILITIES

3.11 EXCAVATION

3.11.1 Permission to Excavate

3.11.2 Utility Locations

3.11.3 Utility Location Verification

3.11.4 Weather Protection

3.12 UNEXPLODED ORDNANCE

3.13 DISPOSITION OF MATERIALS

3.13.1 Turn-In Salvage Materials

3.13.2 Title to Materials

SECTION 01 30 00 Page 2

SECTION 01 30 00

GENERAL REQUIREMENTS (NAU)

03/19

PART 1 GENERAL

1.1 PURPOSE

This specification provides general requirements which the contractor shall follow during the execution of the work. As they are general in nature, specific requirements identified in any other portions of the contract, including in other Division 01 specifications, shall take precedence in the event of a conflict. In this context, a conflict exists only when both requirements cannot be met; if both can be met there is no conflict and the contractor shall comply with both requirements.

1.2 DESIGN-BUILD LANGUAGE

References in the Division 00 and 01 specifications to "design" are not applicable to design-bid-build projects and to all Job Order Contract (JOC). Nothing in the aforementioned specifications shall be interpreted to require design effort unless required by other contract documents.

Where the contract documents refer to contractor prepared designs, these requirements apply.

Notwithstanding the above, design related activities, including extensions of design and shop drawings, required to perform the work and comply with other technical requirements are considered part of this contract and shall be included in the contractors pricing without separate or additional payment.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Pre-construction photos;

Mobilization Plan; G Environmental Protection Plan; G Traffic Control Plan; G Construction Fence/Screening; G

1.4 DEFINITIONS

The following definitions apply to terms as used in the sections identified above in paragraph 1.1. These definitions shall not change or infer a meaning in any other document made part of this contract either directly or via reference.

Fugitive Dust. Solid particles generated by the forces of wind or

SECTION 01 30 00 Page 3 machinery acting upon materials exposed as a result of the contractors operations

Installation. The entity considered to be the legal owner or authorized user of the location of the construction work.

Project. A "Project" is a single task or delivery order under an Indefinite Delivery, Indefinite Quantity award, including Job Order Contracts (JOC's) and Multiple Award Task Order Contracts (MATOCs). For all other contracts, it refers to a single contract award.

Superintendent. The highest level manager responsible for the overall construction activities on a project, including quality and production. The Superintendent maintains a physical presence at the site at all times work is being performed and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

Site. The location where construction work physically occurs. On a single project, when construction work occurs at more than one location, and the locations are geographically separated by more than 5 kilometers (as measured via travel distance), they are considered separate sites.

1.5 NO WAIVER BY GOVERNMENT

The failure of the Government, in any one or more instances, to insist upon the strict performance of any of the terms of this Contract or to exercise any option herein conferred shall not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.

1.6 PROPRIETARY NAMES

Unless specifically identified in the contract as a Sole Source Item, manufacturer's proprietary names indicated for colors, textures and patterns of materials are for the purpose of color, texture and pattern selection only. Other materials are acceptable provided they closely approximate colors, textures and patterns indicated. Any substitutions must conform to all other requirements and must be approved by the Contracting Officer

1.7 PUBLIC RELEASE OF INFORMATION

1.7.1 Prohibition

There shall be no public release of information, documents, or photographs concerning any aspect of the materials or services relating to this project without the prior written approval of the Contracting Officer.

1.7.2 Subcontracts and Purchase Orders

The Contractor agrees to insert the substance of above paragraph "Prohibition" in each subcontract and purchase order generated for this contract.

SECTION 01 30 00 Page 4

1.8 PERSONNEL AND SUBCONTRACTORS

1.8.1 Removal for Non-Compliance

All Quality Control, Safety, Superintendents, and contractor/subcontractor personnel are subject to dismissal and removal at any time based on the sole discretion of the Contracting Officer for non-compliance with the contract requirements.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8.2 Substitution and Replacement

Any in-house personnel, subcontractors, and outside associates or consultants identified in the Contractor’s proposal shall not be replaced or changed without the Contracting Officer's prior written consent.

1.8.3 Qualifications

When qualifications require experience or “related experience”, the experience must be on projects of the same type and nature as the work identified in the project scope of work, and be on contracts with the government of the United States of America, either with the US Army Corps of Engineers or Department of Defense agencies. References and experience must be sufficiently detailed to allow for verification of experience. The Contracting Officer shall have final authority on determining the relevance of any experience submitted.

1.8.4 Employment

Should the continued employment of any person in connection with this contract, or any subcontract hereunder, be deemed by the Contracting Officer to be prejudicial to the interests of the Government, that person shall immediately be removed from the work site. In this connection the Contractor agrees that:

a. Cases which may involve disciplinary action against such persons, or the necessity of reassignment or termination of their services, shall be investigated, processed, reported and disposed of, as directed by the Contracting Officer.

b. Employment contracts of all persons employed in connection with this contract or any subcontract hereunder shall include clauses containing the substance of this section.

1.9 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

SECTION 01 30 00 Page 5

1.10 REFERENCED STANDARDS

1.10.1 Version and Date of Standard

The contract documents make various references to Host Nation and US standards, including Unified Facilities Criteria (UFC) and design guides.

When a specific version (e.g. "UFC x-xxx-xx, with Change yy") or date is identified in the reference, that specific version of the reference will apply.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .